Download presentation
Published byCatherine Cooper Modified over 9 years ago
1
CVE 4070 Construction Engineering Shop Drawings Quality Control
Habitat Build Prof. Ralph V. Locurcio, PE
2
Schedule update
3
Project Delivery Process…
We are here
4
Project Organization…
5
Contract Documents… The Agreement or Contract The Specifications
The Drawings Important Note: Unless otherwise specified this list is the “order of precedence” of the contract documents
6
Drawings in standard set…
Title Sheet Index Sheet Architectural (A) Civil & site utilities (C) Structural (S) Mechanical (M) Plumbing (P) Electrical (E) Fire protection (FP) Finish schedules As-built/record drawings
7
The Specifications… Define the “qualitative” requirements of the project that is to be built. Provide a detailed description of the performance features of all components of the project. Describe the nature of the materials and the workmanship & procedures to be followed in constructing the project. Include those aspects of assembly or construction that affect the performance of the components.
8
The Drawings or Plans… Define the “geometry” of the project and all of it’s components. Include the general form, dimensions and details of all project features that are to be fabricated on site. Show the relationship of all components to each other. May include details, notes and instructions that amplify the specifications.
9
Specs in Contract Admin…
Drawings are never 100%… Drawings show “typical” conditions Field measurements required Do not cover means & methods Need to detail “actual” materials to be used Need to detail “installation” procedures PM must evaluate & respond Requires considerable judgment & experience Shop Drawings fill these voids
10
Materials used in the contract…
AE obligation to ensure that materials & products conform to those specified. Owner may claim negligence if don’t conform Care must be exercised in accepting “alternatives” Be especially aware of new or non-standard materials Builder constantly seeking lowest market price for “acceptable” materials & methods Must prove that all materials used meet spec Must obtain owner’s (representative) approval to substitute May not submit alternatives during bidding process
11
Shop Drawings & Samples…
Function of Shop Drawings Link between design & construction Show details of fabrication, assembly & installation Allow introduction of commercially tested products Show method of accomplishing “special” requirements Contracts usually require approval prior to ordering Approval of Shop Drawings Contract SPs usually specify list of shop drawings Builder must submit schedule of submissions Owner must “approve” submittals for conformance to specs Builder responsible for accuracy, methods & quality Misuse of Shop Drawings May not change requirements or design intent Builder’s responsibility to conform, even if missed by AE/Owner review
12
Examples of shop drawings
Drawings for mechanical, electrical and plumbing components. Ductwork fabrication drawings. Drawings for HVAC piping. Drawings of air handling units. Steel and sheet metal shop drawings. CAD shop drawings. Architectural woodworking shop drawings. Cabinet shop drawings.
13
Example of Shop Drawings-1
14
Example of Shop Drawings-2
15
Example of Shop Drawings-3
16
Example of Shop Drawings-4
17
Example of Shop Drawings-5
18
Example of Shop Drawings-6
19
Submittal Review… Include: shop drawings, samples, test results, certifications, criteria & standards List is prepared by designer Approval by owner’s rep – verify conformance & suitability Timing of approval is essential Special attention: blasting, excavation, compaction, water control, pile driving, hazmat, cranes
20
Submittal Review Process…
21
Dealings with subcontractors…
Concept of “one-to-one” authority PM/CM deals solely with the General Contractor. General Contractor is responsible to hire subcontractors Selection includes evaluation of the subcontractor’s competence Responsibility includes all acts & omissions of any sub General Contractor must have effective contracts, admin procedures & management Architect, Owner & PM not responsible for how the Builder subcontracts the work Contractor is responsible for subcontracts
22
One-to-One authority…
PM CM
23
One-to-One authority…
24
Part II – Specifications & Administration of Quality
25
Management of Quality…
Definition of Quality Control Definition of Quality Assurance Designer’s responsibility Contractor’s responsibility
26
Project Organization…
27
Quality Control Process…
Must have a Quality Control Plan… a routine system & schedule of inspections Special considerations: Timing of inspections; preclude delays Protection of work in place Most work is irreversible; i.e.. concrete, foundations Logistical sequencing Follow plans & specifications; changes not authorized Report and correct errors & deviations from spec; documents Three phased inspections system Preparatory inspection Pre-inspection Final inspection QC Staff must be qualified, trained & dedicated
28
Construction Inspections
Three phased inspection system Preparatory inspection – meeting Pre-inspection – on site; prior to construction Final inspection – after completion
29
Quality Control & Assurance…
Quality control vs. quality assurance Inspection & Testing manual Policy matters that govern acceptance Inspection procedures Technical checklists List of testing for materials & equipment Work flow diagrams Required on government contracts
30
Stopping the work… Work is defective… Unsafe conditions…
Owner’s right to stop work that is defective Contract provisions govern Communicate in writing Contractor may dispute Unsafe conditions… Risk of death or serious injury Obligation of Owner’s rep and Builder Follow verbal order with written order Risk of stopping work… Cost incurred for labor & materials Schedule slippage might incur damages Work must be torn out and rebuilt
31
Project Organization…
32
End of Part I
33
Habitat for Humanity Build
Organize into teams of 5-10 students Build dates are Wed thru Sat Starting Sept 16 Work on site 800am to 300pm Complete report on construction work I will schedule your build date
34
Habitat Location
35
Habitat Project Report
Review plans & specs Materials being used Equipment being used Team organization Who is PM Who is superintendent Tasks assigned to each team member Weather conditions Training involved Problems encountered & solved
36
Alternative = PM case study
Read PM case study assigned Write report on case study: Type of construction Materials used Team organization How scheduled Budget controls Problems encountered; how resolved Special techniques used
37
Scope of tour… Meet key officials Discussion items
Construction project manager Resident Engineer Discussion items Individual responsibilities Type of contract used on this job Organization for control of time & cost Coordination of subcontractors Training for this job Degree of experience needed Control of quality
38
Construction operations…
Observe construction progress – homework Turn in at class on 9/17/2007 Homework items Organization & scheduling of work Purchase & flow of materials Use of subcontractors Integration of subcontractors work Workmanship and quality control Problems encountered Correction of deficiencies Safety
39
That’s it for today…
40
Going forward… Sept 16… Project tour cancelled
Sept 16… Disaster Recovery & Study guide ALL ATTEND ON TUESDAY Class held in 500 OLS – Room 130 Sept 18… Test #1–The Basics–working on a room Sept 23… Begin section on “tools” Project Scheduling Project Budgets Payments Quality Changes Claims
41
Sep 14 – Construction Tour
42
Project Tour: Tue Sept 14…
Before: 1. Meet at parking 5:00pm 3. Pick up construction tour homework sheet. 4. Ask questions during the tour to get info you need. 5. No open toe shoes or shorts After: 1. Return to parking 6:00pm. 3. Tour homework sheet is next class. 4. Next class at regular time & place.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.