Download presentation
Presentation is loading. Please wait.
Published byEzra Beasley Modified over 9 years ago
1
Cable Rehabilitation at Oncor by Richie Harp – Distribution Standards Data provided by Mark Darilek – Maintenance Planning SWEDE 2009 – Tulsa, OK – Thursday, May 7, 2009
2
Cable Rehabilitation Overview Rehabilitated cable Cable repairs to facilitate future rehabilitation Oncor requirements for rehabilitation Further considerations 2 nd Responder process Another technology
3
Amount of Rehabilitated Cable Began in 1995 420 cbl-mi rehabilitated 8,000 cbl-mi in service – Pre-1993 cable 22,000 cbl-mi total cable
4
Amount of Rehabilitated Cable URD Cable size – Less than #4/0 AWG (#2 and #1/0 AWG, and minimal amount of #2/0 AWG) Began in 1995 405 cbl-mi rehabilitated 17,000 cbl-mi in service 2% of URD cables
5
Amount of Rehabilitated Cable Feeder Cable size – #4/0 AWG and larger (up to 1000 kcmil) Began in 2008 15 cbl-mi rehabilitated 3,400 cbl-mi in service 0.4% of feeder cable
6
Cable Repairs Standard cable (Began purchasing in 1990) #1/0 Al 19-Strands Strand-filled conductors 25 kV, 260-mil TRXLPE 16-#14 AWG Concentric Neutral Wires (Full neutral) Jacketed
7
Cable Repairs (Cont) Only for cable repairs (2-ft pieces) for future injection #1/0 Al 19-Strands Strands not filled 25 kV, 260-mil TRXLPE 8-#14 AWG concentric neutral wires (1/2 neutral) Unjacketed On 1000-ft composite reel
8
Oncor Requirements for Rehabilitation Do not rehabilitate: Cable installed in conduit 175-mil or 220-mil cable operating at 14.4 kV Butyl rubber cable Cable with tape conductor shield Corroded concentric neutral
9
Do not rehabilitate cable if… Corroded center conductor Loss of insulation shield conductivity Insulation shield with no adhesion Failures due to dig-ins or debris in trench There is a chance the cable will be converted to 14.4 kV in the future Oncor Requirements for Rehabilitation (cont)
10
Other Requirements There must be more than 25% concentric neutral remaining. There cannot be more that one joint per 100 feet of cable. The faulted cable section must not have been de-energized more than six months.
11
Comments: We tried to rehabilitate some open loops that had been de-energized for up to 2 years Very little success We quit rehabilitating open loops that had been de-energized for more than 6 months.
12
More comments: 2006 and 2007 Processes Left URD loops open after failures (direct buried cables) Only repaired cable to get customers’ lights back on.
13
More comments: Dec 2007 Process Began repairing failed loops again. Caught up with open loops (Feb 2009) – Inject cables or – Replace cable if not able to inject
14
More comments: Dec 2008 Process Change Install joint to repair cable Try to inject the cable After the repair, if the cable is not able to be injected, then just leave energized. Defer replacement of the cable until the next fault.
15
2 nd Responder Process System-Wide Process Repair failures on direct buried cable (not in conduit) Must be able to switch around to get lights back on. Not normally feeder exits (Only non-critical cables)
16
2 nd Responder Decision Process Flow Chart Available by request
17
2 nd Responder Process 1868 sections of failed cables came through the process since 2008 749 sections of cable were injected 1119 sections were not able to be injected 922 due to process requirements 197 not related to the process (already energized when arrived, in conduit, etc.)
18
2 nd Responder Process – Injected/Not Injected
19
2 nd Responder Process 12 cause codes for not being able to inject the 1119 sections of cable Age of fault (> 6 months) Could not flow (Blocked strands or joints) Inaccessible fault or joint location Deteriorated neutral (< 25% remaining) Previously injected, non-warranty or other Previously injected, warranty
20
2 nd Responder Process 12 cause codes for not being able to inject the cable (Cont) Corroded conductor Number of joints (> than 1 joint per 100 ft) Unknown Cable is in conduit Already energized upon arrival Other – These last three represent the 197.
21
2 nd Responder Process – Causes
22
Another technology Different formulations for injection fluid Formulation tailored to operating environment Tailored more for feeder cables with higher operating temperatures (»45°C) No soak tanks required Put back into service immediately after injection
23
Another technology (Cont) Must replace all joints Higher pressures for injection
24
Rehabilitated Cable That Is Failing Feeder URD
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.