Madrid, April 1 th 2008 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
2
2 LARRAU 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. Reviewed figure
3
3 LARRAU Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions.
4
4 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
5
5 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Pipeline Falces – Irurzún 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
6
6 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU CS Zaragoza 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
7
7 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU DECIDED & ON TIME Pipeline Barcelona – Arbós (duplicate) 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
8
8 Pipeline Barcelona - Arbós Investment figures are merely tentative and correspond with the current best estimation.
9
9 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU CS Navarra 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
10
10 CS Navarra Investment figures are merely tentative and correspond with the current best estimation.
11
11 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Pipeline Lemona – Haro (duplicate) 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
12
12 Pipeline Lemona – Haro (duplicate) Investment figures are merely tentative and correspond with the current best estimation.
13
13 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Reinforce CS Haro 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
14
14 Reinforcement CS Haro Investment figures are merely tentative and correspond with the current best estimation.
15
15 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Pipeline Tivissa – Paterna (duplicate) 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
16
16 Pipeline Tivissa – Paterna (duplicate) Investment figures are merely tentative and correspond with the current best estimation.
17
17 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Pipeline Tivissa – Castelnou (duplicate) 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
18
18 Pipeline Tivissa – Castelnou (duplicate) Investment figures are merely tentative and correspond with the current best estimation.
19
19 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU Pipeline Zarza de Tajo – Villar de Arnedo 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
20
20 Pipeline Zarza de Tajo – Villar de Arnedo Investment figures are merely tentative and correspond with the current best estimation.
21
21 Delays in the Spanish infrastructures side are due mainly to the administrative permitting process. Delays in the French infrastructures side will allow to achieve simultaneously an homogeneous capacity in both directions. LARRAU CS Villar de Arnedo 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
22
22 CS Villar de Arnedo Investment figures are merely tentative and correspond with the current best estimation.
23
23 5 th SG Meeting South Gas Regional Initiative Spanish Infrastructure Development: Advancement Status
24
24 5 th SG Meeting South Gas Regional Initiative Infrastructures Development Status after > 1 year
25
Thank you for your attention