SunGuide TM Software Development Project Release 4.2 FHP/CAD + AVL/RR Design Review January 8, 2009 Jan 8, 20091R4.2 Design Review
2
Jan 8, 2009R4.2 Design Review 2 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
3
Jan 8, 2009R4.2 Design Review 3 Introductions
4
Jan 8, 2009R4.2 Design Review 4 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
5
Jan 8, 2009R4.2 Design Review 5 Meeting Objectives Requirements: –Provide a high level review –Provide SwRI’s interpretation (via a design) of the requirements Design –High level architectural overview –Operator actions and reactions –Prototype screens / reports Not an objective: –Revise requirements
6
Jan 8, 2009R4.2 Design Review 6 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
7
Jan 8, 2009R4.2 Design Review 7 Release 4.2 Development Activities
8
FHP/CAD Overview Jan 8, 2009R4.2 Design Review 8 FHP CAD FHP CAD Interface Server Goal is to make the communication of event information between FHP dispatchers and FDOT operators faster and more efficient FHP CAD Interface Server consolidates, filters, and redistributes FHP CAD data to each subscribing SunGuide deployment SunGuide allows the operator to process incidents as well as process updates to those incidents.
9
Jan 8, 2009R4.2 Design Review 9 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
10
FDOT Concept of Operations
11
Operational Concept Fort Myers Jacksonville Lake Worth Miami Orlando Tampa Tallahassee Statewide FTP Site FHP CAD Interface Server FHP Incident DriverIDS FHP Incident DriverIDS FHP Incident DriverIDS SunGuide District 2 SunGuide District 7 SunGuide District 1 Regional Communication Centers
12
Operational Concept FHP Interface Service –Retrieves alerts from the FHP CAD FTP site and distributes to the FDOT districts based on subscriptions IDS FHP Incident Driver –Handles the connection between the FHP CAD Interface and Incident Detection Subsystem (IDS) IDS Subsystem Update –Notifies GUI of new and updated alerts –Stores alerts and responses to alerts in the database GUI Updates –Displays FHP Alerts to the operator –Provides response dialog and event creation dialog –Display events on the Operator Map Jan 8, 2009R4.2 Design Review 12
13
FHP Alert GUI FHP Incident Alert Dialog –Consistent with other types of alerts generated by IDS Jan 8, 2009R4.2 Design Review 13
14
FHP Alert GUI Action Choices –Create New Event –Create Secondary Event –Set Responder Arrival –Dismiss as Already Detected –Dismiss as False Alarm –Associate to Existing Event –Acknowledge, Take No Action Jan 8, 2009R4.2 Design Review 14
15
FHP Alert GUI Event Field Population –Populated with the closest EM location found –All information contained in the alert is logged in the comments section of the event Jan 8, 2009R4.2 Design Review 15
16
Alert Processing Choices Create New Event –Creates a new Event Create Secondary Event –Creates a new Secondary Event Set Responder Arrival –Fills in the FHP incident number in a selected event –Sets the responder arrival field in the selected event –Operator is required to own the event Associate to Existing Event –Fills in the FHP incident number in a selected event –Operator is required to own the event Jan 8, 2009R4.2 Design Review 16 *These actions will allow updates. When updates are displayed, the Event ID of the event that was previously created or associated is displayed in addition to the information about the alert.
17
Alert Processing Choices Acknowledge, Take No Action –Logs alarm as acknowledged –Allows updates Updates are treated as new alerts Dismiss (False Alarm or Already Detected) –Logs alarm as dismissed –Does NOT allow updates This action is NOT reversible so alert updates with the same ID will NOT be seen by the operator Jan 8, 2009R4.2 Design Review 17
18
Communication Alarms Loss of FHP Interface Server Connection –Occurs if the FHP Interface Server disconnects suddenly or is not connected within 1 minute of the FHP Incident Driver being started –All deployments will receive this alert Jan 8, 2009R4.2 Design Review 18
19
Communication Alarms Loss of FTP Server Connection –Occurs when the FHP Interface Server fails to connect to the FTP site to retrieve alert information –All deployments will receive this alert Jan 8, 2009R4.2 Design Review 19
20
Communication Alarms Stale FHP CAD RCC Files –Issued only if a file that contains a county that IDS has subscribed to has not been updated in a configured amount of time. –Only issued to the deployments subscribing to counties included in the stale file. Jan 8, 2009R4.2 Design Review 20
21
FHP Interface Server Configuration Options FTP Site –Host, port, username, password –Local Directory to store current FTP files –Interface only supports data from a single FTP site Access –List of usernames and passwords for all users Timing –Retrieve Interval How often to get new alerts from the FTP site –Stale Data The maximum time limit a file should go without an update –Stale Data Multiplier Number of retrievals containing stale data before next Stale Data Message is sent Jan 8, 2009R4.2 Design Review 21
22
FHP Incident Driver Configuration Options Each SunGuide deployment can have a unique filtering configuration County Filtering –Can subscribe to any county in the state –Supplying no counties will return all alerts in the state –Case-insensitive, punctuation insensitive St. Lucie = ST LUCIE, stLUCIE, ST.LuCiE “St. Lucie” DOES NOT match “South St. Lucie” Roadway Filtering –Filters alerts after the county filter has been applied –Case-insensitive and punctuation insensitive –Searches for given text inside a given roadway I-95 = i95, i 95, i-95, I 95, I95 (DOES NOT match SR-95) I-95 DOES match “South I-95” or “i-95 Florida Drive” FHP Interface Server location –Host, port, username, password Jan 8, 2009R4.2 Design Review 22
23
Limitations of FHP Data Inconsistent Roadway Naming –I-95 and SR-9 are the same road require two different entries in the subscription list (unless returning all roadways) Linear References and Directions –Uses a predefined list of references and directions to parse data Incorrect Formatting –Worst case 16450 SE FEDERAL HIGHWAY [JDSP MAIN ROAD] [HOBE SOUND] –Missing “x[“ to split the roadway and cross street –Alert is disregarded because it can not be parsed correctly –Other cases I-75 SB [I-75 SB] x[MM116.0] [BONITA SPRING] –Roadway = I-75, Dir = Southbound, Linear Reference = I-75 SB Could result in odd references, but will still result in a valid alert For parsing specifics, refer to the FHP Data Parsing document Jan 8, 2009R4.2 Design Review 23
24
Jan 8, 2009R4.2 Design Review 24 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
25
Jan 8, 2009R4.2 Design Review 25 Questions?
26
Jan 8, 2009R4.2 Design Review 26 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
27
Jan 8, 2009R4.2 Design Review 27 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
28
Overview Jan 8, 2009R4.2 Design Review 28 Current AVL/RR implementation feeds Event Update and EM and AVL configuration data from SunGuide to the Road Ranger. The information pushed into SunGuide from the Road Ranger is: Vehicle status and location (AVL information) Event comments AVL/RR communications interface needs to be enhanced to include a additional bi-directional flow of information.
29
Jan 8, 2009R4.2 Design Review 29 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
30
District 7 ConOps V2 Jan 8, 2009R4.2 Design Review 30
31
AVL/RR Architecture Jan 8, 2009R4.2 Design Review 31
32
Operational Concept Receive event data from tablet –Add a new, in-progress event –Update event data, including: Lane blockage RR activities Involved Vehicles –Ability to close an event (or leave open, ex: abandoned vehicles) Does not change existing functionality –Enhanced behavior is driven by new data being sent by the RR device. –If the RR device does not use any of the new schemas, then system maintains the SG 3.x functionality No changes to GUI (Operator Map, Admin Editor) Jan 8, 2009R4.2 Design Review 32
33
AVL/RR Modifications AVL/RR subsystem and driver updated to handle enhancements to RRMA ICD Three new messages added to RRMA ICD: –New Event –Update Event (lane blockage, RR activities, involved vehicles) –Change Event Status New data is forwarded on to EM subsystem for processing Jan 8, 2009R4.2 Design Review 33
34
EM Modifications / Limitations EM Modifications –EM subsystem updated to process an entire event record in one message –EM will process event updates from AVL/RR Limitations –TMC Operator and Road Ranger should avoid editing an event at the same time Events created by AVL/RR will initially show up as being owned by the AVL/RR subsystem A TMC operator can then take ownership of the event; however, this will not prevent updates received from the RR from being saved If RR provides new data, unsaved data entered on EM details window for that event will be lost Jan 8, 2009R4.2 Design Review 34
35
Jan 8, 2009R4.2 Design Review 35 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
36
Jan 8, 2009R4.2 Design Review 36 Questions?
37
Jan 8, 2009R4.2 Design Review 37 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
38
Documentation / Schedule Documentation (ones in yellow have already been provided to FDOT): –SRS (Software Requirements Specification) –SIP (Software Integration Plan) –SICP (Software Integration Case Procedures) –SDD (Software Design Document) –SUM (Software Users Manual) –VDD (Version Description Document) Schedule –FAT currently scheduled for week of Feb 16 th –Deployments are not yet scheduled Jan 8, 2009R4.2 Design Review 38
39
Jan 8, 2009R4.2 Design Review 39 Agenda TimeActivity Who 9:05 – 9:10High Level Overview – meeting objectives Heller 9:10 – 9:20FHP/CAD Overview (from FDOT specifications) Heller 9:20 – 10:00FHP/CAD Design Overview: Operational Concept FHP Alert GUI Alert Processing Choices Communication Alarms Limitations of FHP Data Configuration Options Brisco / Brown 10:00 – 10:25Questions / Answers All 10:25 – 10:40Break 10:40 – 10:50AVL/RR Overview (from FDOT specifications) Heller 10:50 – 11:20AVL/RR enhancements Design Overview Operational Concept AVL/RR Modifications EM Modifications Issues and Limitations Clauss / Alban 11:20 – 11:40Questions / Answers All 11:50 – 11:50Documentation / Schedule SwRI 11:50 – 12:00Action Item Summary All
40
Jan 8, 2009R4.2 Design Review 40 Action Item Summary