LOW COST SURFACING APPROACHES IN ZIMBABWE CASE STUDY: Marondera - Musami Road Construction Project K. Mukura TRL Ltd
2
Introduction Constructed in 1993-1994 period Before construction: 22 km was narrow mat 41 km was gravel road in poor condition After construction: 22 km is narrow mat 41 km is surfaced to a 7/8 standard Low cost surfacing method was used
3
Introduction Location: HARARE CITY Marondera- Musami Road Marondera Town Cross To Mozambique Malawi MUTARE CITY To Mozambique Beira Port 63km 73km 60km
4
Construction Standards Alignment: closely followed the existing gravel road cuts and fills were designed by eye curvature was designed by eye except in complicated situations very sharp curves were acceptable to minimise costs Super-elevation was difficult to set by eye
5
Construction Standards Pavement Design: x-section: 7/8, 3% camber, 2m wide drains ( detour) 150mm sub-grade and base 1 thickness Compaction: Ls 91% HCE for sub-grade Ls 93% HCE for base 1 Materials specification: base 1: triaxial class 2.8, laterite & decomposed granite sometimes marginal sub-grade: SG9
6
Construction Standards Pavement Design: Surfacing: single seal 10mm crushed stone @ 10x10 -3 m3/m2 TP7 prime @ 0.9 litres/m2 bitumen 150/200 @ 1.2 litres/m2
7
Observations Traffic: traffic increased beyond design capacity of road heavy to opted for the short cut bypassing Harare despite 22km of narrow mat Pavement: still sound to date in spite of marginal materials used. re-sealing was done after 5 years and the carriageway looks good
8
Conclusion Most sealed rural roads in Zimbabwe have been over-designed Low-cost surfacing technique is used widely now to upgrade rural roads Drainage system should be good enough to prevent water seeping into pavement