NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 1/18 SHORT MODEL COILS PROGRAM SMC meeting #18 Pierre MANIL CEA/IRFU/SIS 1. SMC assembly Modeling, Conception, Outstanding points 2. SMC tooling Bladders & Slipshims, Bladder testing device, CERN implication 3. Ceramic insulation winding RAL experience, possible improvements 4. Schedule Back on the agenda…
2
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 2/18 1. SMC assembly P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 2/18
3
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 3/18 SMC ASSEMBLY 1/3 MECHANICAL DESIGN PRINCIPLE Y-pad (iron-steel) External tube (aluminum) X-pad (iron-steel) Yoke (iron-steel) COIL PACK Keys (iron) Bladder location courtesy of François Nunio, CEA Y X Z Shell-based structure: -Aluminum shell -Iron & steel pads -Iron & steel yoke Pre-stress at room temperature w/ bladders and keys (in the models to come, the keys width will include their own nominal size + the interference key gap) In-situ stress control -on tube -in coil pack We have to combine relevant shell pre-stress (controlled by tube’s thickness) and bladders pre-stress (controlled by keys interferences) to define the range of coil pre-stress
4
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 4/18 SMC ASSEMBLY 2/3 KNOWN / UNKNOW… Courtesy R. Hafalia H. Félice Coil properties OK expected field OK Rods geometries TBD Interface with external world TBD Interface between RAL’s coil pack And assembly TBD Instrumentation TBD Lateral prestress OK Bladders being tested Assembly parameters OK r yoke ~230 mm e tube ~20 mm Iron extension OK Detailed conception TBD Finer mechanical studies TBD - Sensitivity - Mouting steps modeling… Picture= SD01 magnet (as an example)
5
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 5/18 2D MODEL r yoke 230 e tube 20 ixix 300 iyiy 0 µ 0.3 -113 MPa-125 MPa -92 MPa -140 MPa-129 MPa -52 MPa -156 MPa-136 MPa -37 MPa -163 MPa-140 MPa 20% 50% 100% 120% 100% Lorentz 138 MPa 270 MPa 168 MPa 52MPa 80 MPa 147 MPa No separation Bladder Cool- down σxσx σ VM -102 MPa-113 MPa -31 MPa-43 MPa Lorentz 107 MPa 225 MPa 80 MPa 93 MPa 70 MPa 137 MPa Bladders + Cooling Very homogeneous ~ -110 MPa Very homogeneous ~ -35 MPa Very homogeneous ~ -120 MPa
6
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 6/18 SMC ASSEMBLY 3/3 PRESENT STAKES 3D modeling (CEA part) - defining rods prestress and geometries - validating the whole structure comportment Mechanical steps - validating the new bladders (see next part) integrating 60 mm-wide bladders in the structure with Federico - validating the LHC iron needs - detailed conception and drawings Interface with the coil pack (coherent conception): - how to offset the different coil pack sizes? Horseshoe or shims (SMC size: 419.2 x 189.2 mm – ceramic insulated coil size: 436.0 x 206.0 mm) - what horseshoe geometry? - current leads Superconducting cable needs I confirmed this week to Thierry Boutboul and Federico that we need: - 80 m for Saclay (1 dipole = 2 double pancakes) - 160 m for RAL (2 dipoles)
7
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 7/18 2. SMC tooling P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 7/18
8
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 8/18 SMC TOOLING 1/3 BLADDERS AND SLIPSHIMS Bladders are 420 x 60 mm (SD01: 320 x 54 mm) A set of 3 has been manufactured for tests and qualification Laser winding all along, supplier test under 5 bars pressure Slipshims are 570 x 62 mm, already manufactured Laminated steel shims Courtesy R. Hafalia
9
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 9/18 SMC TOOLING 2/3 BLADDER TESTING DEVICE Von Mises stresses for i x =300 μm Strain gauge
10
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 10/18 SMC TOOLING 3/3 CERN IMPLICATION Final test cryostat has been identified at CERN (with Christian Giloux & Patrick Viret in Remo Maccaferri’s lab) - AUTOCAD drawings are available (for integration at Saclay) - Power supply is OK (up to 15-20 kA available – quench current around 14 kA) - Thinking asked about external residual field: seems to be OK CERN has to supply: - water compressor or hand pump (very high pressure ~500 bars) - instrumentation & electronics apart from mechanical (uniaxial?) gauges on assembly - hydraulic press for rods prestress Courtesy R. Hafalia
11
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 11/18 3. Ceramic insulation winding P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 11/18
12
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 12/18 CERAMIC INSULATION WINDING 1/4 SMC WINDING TRIAL 2 (RAL work)
13
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 13/18 CERAMIC INSULATION WINDING 2/4 POSSIBLE IMROVEMENTS Cable clamping during winding - improving clamping on straight sections (butterfly screws…) - adding clamps on heads (cf. picture) - thinking about the need for final compression of the pancake for planarity ’S’ layer transition - softening the edges - machining a head clamp to maintain the transition - thinking about pre-forming… Question : are metal shavings due to screws a danger? if it is: Teflon screws? Courtesy Ph. Daniel- Thomas
14
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 14/18 CERAMIC INSULATION WINDING 3/4 NB3SN QUADRUPOLES We will use Nb3Sn quadripoles’ winding machine for ceramic insulated coil. To re-design: -Support and fixation plate -Coil pack ends -Winding clamps Courtesy M. Segreti Rotating support (re-used) Cable stock Fixation plate Coil pack end
15
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 15/18 CERAMIC INSULATION WINDING 4/4 OVERLOOK ’S’ layer transition Titanium parts Clamping (or alternative solution)
16
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 16/18 4. Schedule P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 16/18
17
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 17/18 SCHEDULE 1/2 Steering committee of October 15 (CERN) : Deadlines for Saclay: - SMC support structure (+ tooling) for June 15 - Ceramic-insulated coil for late October Mechanical caraterization of ceramic insulation Courtesy G. de Rijk
18
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 18/18 SCHEDULE 2/2 Starting point: NED deliverable on innovative insulation (EDMS Id. 885715) Next step: Performing “stack tests” on ‘very little’ racetrack coils (5 turns, approx. 5 x 10 cm size) for 3 reasons: -To avoid tin losses -To limit the structural relaxing effect dur to twist pitch -To improve the sample cohesion when reaction prestress is relaxed Winding and tests should be launched during this Trimester CERAMIC CARACTERIZATION 8-stack test (insulated)(without insulation)