Download presentation
Presentation is loading. Please wait.
Published byEvelyn Page Modified over 9 years ago
1
Crisis in Shrewsbury Flooding impacts and risk management
2
Responsibility and management Under the ‘Water resources act 1991’ the Environment Agency have a duty to... ‘…protect people and resources threatened by river and sea flooding’.
3
Dealing with high risk Pre-disaster planning Preparation Response Recovery and reconstruction
4
Flood alleviation in Shrewsbury Flood alleviation strategies have been proposed from 1956 to the present day 1:100 floods cost an estimated £4m The NRA (now Environment Agency) commissioned the latest study in 1993. 3 options Upstream storage Channel enlargement by dredging Hard defences (cost effective option - £3.1m)
5
Floodwater Containment Upstream The River Vyrnwy doubles the River Severn discharge during flood risk periods. Water encouraged on farmland upstream of Shrewsbury at confluence Discharge slowed BUT – rejected on a cost benefit analysis - Compensation to landowners for loss of land = £18 million.
6
Channel Enlargement by Dredging This would: Deepen the river Increase the efficiency Allow the channel to contain more water within its banks during periods of peak flow. However, the channel would need to be 35 meters deep! This would be prone to re-silting which would incur even more costs.
7
Hard defences and drainage modification within the town Defence walls at key locations in the town to hold back flood water. One way valves included to stop water backing up and flooding out of the drains. Cost would be £3.1 million. This was the only option considered cost effective by the EA.
8
Planning application was made in 1993 Proposed scheme… Include walls, floodgates and ‘one-way’ drain valves in a two phase development… Phase 1 - Based in Frankwell Phase 2 - Based on English Bridge Proposal rejected - May 1996 ‘unacceptable impact on the town’s river side character’ NRA (1996) Hard defences...
9
In Oct. 1998 Shrewsbury experienced its largest flood for 30 years (1:60 yr. event) And in Nov. 2000 Shrewsbury again was devastated by its largest flood for 50 years (1:50-70 yr. event) EA have acknowledged a significant increase in the frequency of floods events since 1998 ( EA 2001 ) And what happened...
10
B4393 Crew Green to Llandrinio Road
11
Frankwell, Shrewsbury.
12
Frankwell Car Park, Shrewsbury.
13
English Bridge, Shrewsbury.
14
Gay Meadow Football Ground, Shrewsbury.
15
Linked to the River Severn Strategy (EA)... ...the EA have proposed the latest flood alleviation strategy for Shrewsbury. Based on… the work in 1993 the latest flood protection systems and full communication with interested parties Renewed calls for action...
16
What is happening? The EA split Shrewsbury into “Cells” – each for consideration and Cost Benefit Analysis - Work is funded by local authorities and grants from Central Government.
17
Frankwell River Severn Car park Housing
18
Shrewsbury and Atcham Borough Council granted planning permission for Phase 1 on 4th July 2001... Formal application made to DEFRA (Department for the Environment, Food and Rural Affairs) for funding... Accepted - construction work started early 2003 Completed Autumn 2003 So what’s the latest?
19
Frankwell – hard defences The scheme incorporated demountable barriers which are only deployed prior to flooding.
20
Temporary Flood Defences Two other temporary flood defences will be trialled in Shrewsbury Mobile Dam – which consists of two tubes fitted together and filled with water to create a dam.
21
Temporary Flood Defences Pallet Barrier – which is a metal frame on which wooden pallets and plastic sheeting are placed to retain the water
22
Defences tested Defences were tested during the flooding in Feb 2004
23
Defences tested
24
Other areas not so protected
27
They await the success of Phase 1 Phase 2 - English Bridge area - does not currently meet cost benefit requirements. R. Severn Management Strategy Continued monitoring... R. Severn Climate Catchment response Pre-planning (e.g Flood Warnings) Increase awareness (e.g. Floodline) Continuing work by the EA...
28
Summary of the proposed schemes SchemeCostEffectiveness Environmental Impact Containment Too high at over £18 million Would protect area downstream, including Shrewsbury Loss of agricultural land, but creation of new wetland Dredging Too high would require repeat dredging Would only work in channel re-dredged Destroys aquatic habitats and river would have high muddy banks during low discharge Hard Defences £3.1 million Would protect Shrewsbury with minimal impact elsewhere Minimal impact
29
Flood defence options OptionPositiveNegative Cost (£million) Do Nothing 0 Maintenance only 0.1 Upstream Containment/storage 24.3 Hard Defences 6 Storage and hard defences 7.9 Dredging and re-routing river channel 30+
31
Why locate in high risk areas? Risk perception Understanding based on experience Low frequency of high magnitude events may induce complacency Knowledge Benefits outweigh potential costs Necessity
32
EIA for Phase 1 completed Jan 2001. Work based in Frankwell, Shrewsbury Objective analysis of impacts by new developments Statutory obligation for major projects Stages… Problem Identified - national and local relevance Scoping Report - sets out problems Consultation, feedback and option evaluation Planning application with env. action plan EIA ( Environmental Impact Assessment) EIA ( Environmental Impact Assessment)
33
Rejected for aesthetic reasons? or was it something else…?
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.