JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004.

Similar presentations


Presentation on theme: "JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004."— Presentation transcript:

1 JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

2 Contract Status All FY04 contracts awarded  IU contract to evaluate Pb glass and pmts awarded this week Budget spent

3

4 Producing the 12-GeV CDR Updating pCDR reenergized by CD-0 Cardman to outline process to go to CDR at summer User’s Group Meeting  Create a new editorial board Suggestions requested from User’s Group for membership  CDR will consist of pCDR + updates with sections of recent interest + cost/schedule/performance document (ala G0)

5 Producing the 12-GeV CDR (cont.) Open process  Experimental equipment available to anyone with scientifically viable idea, e.g. new experiments in Hall D.

6 Management of 12-GeV Project Project management structure  Allison Lung has been appointed (interim) project director for the 12-GeV project  Project services office to track progress  Management structure will parallel the current management for 6-GeV operations Three associate project managers (accelerator, physics and civil) Below this level, appoint “matrixed” staff as deputies Search for a Hall D manager

7 Management of 12-GeV Project (cont.) Adjust staffing to scope of WBS structure  Careful to not put 6-GeV program at risk  Management structure clarified within about one month

8 Budget profiles Now that the project has begun with CD-0, a careful line must be drawn between operations and 12-GeV project spending. (Cost) baseline for 12-GeV project will not be established till CD-1 CD-1 (Lehman Review) will take place in summer of 2005 The entire community must focus on passing this review.

9 Budget profiles (cont.) Project director (Allison Lung) will conduct discussions with DOE (Joanne Simon-Gillo) to obtain a  proposed schedule  target milestones, etc. Discussions with DOE specifically about Hall D management structure regarding  guidelines for creating the group  rate of hires

10 Hall D proposed staffing

11 Hall D Budget for FY05 Budget for next year  $600 K  + incremental 12-GeV funds, depending on funding and determined by 12-GeV management R&D will be prioritized for entire project  Can become upgrade-specific  Priority will be given to activities which will establish technical feasibility of project

12 Impact of budget profile on schedule Fiscal years 020304050607 01 Constant-effort budget continues thru FY03 * 10 CD-0 CD-1CD-4CD-2CD-3 Orig. schedule Constant-effort budget in FY02 * & O413.3 0809 * Assumes increases beyond constant-effort in subsequent years.

13 Idaho Accelerator Center (Phil Cole) Idaho State University (ISU) would like to develop ties with JLab, and is considering joining SURA. Facilities  It offers beam time at its 40 MeV electron Fast Pulse LINAC for detector tests  A 100 MeV electron accelerator (25% d.f.) should be operational within 3 years.  http://iac.isu.edu/Facilities_&_Equipment.htm

14 Coherent photon beams Contacts made with Hrachya Asatryan (director of YerPhI)  Invitations sent to R. Avakyan and S. Taroyan to visit JLab for two weeks in October to carry out initial discussions. Workshops  NATO Workshop at Yerevan on “Advanced Photon Sources and their Applications,” Aug 29-Sep 2, http://moon.yerphi.am/~a_albert  Workshop on Charged and Neutral Particles Channeling Phenomena “Channeling 2004” in Frascati, Nov 2-6, http://www.lnf.infn.it/conference/channeling2004

15 Actions and prerequisites

16 Project phases and federal budget

17 Notes to Typical Project Phases Correlate with the Federal Bubget Process