Download presentation
Presentation is loading. Please wait.
Published byMaud Mosley Modified over 9 years ago
1
Eric Prebys, Fermilab Director, US LHC Accelerator Research Program (LARP) February 16, 2010
2
Background Previously assumed upgrade schedule Key Results from Chamonix LARP Highlights since last meeting I will present the items that were discussed at CERN, annotated as appropriate. February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 2
3
Initial operation (now) Ramp up to 1x10 34 cm -2 s -1 Phase I upgrade After ~2 years of operation (~2014) Replace 70 mm triplet quads with 120 mm quads * goes from 50->30 cm Linac4 to increase PSB injection energy to reduce space charge effects Luminosity goes to 2-3x10 34 cm -2 s -1 Phase II upgrade After Phase I triplet burns up (nominally ~2020) Peak luminosity goal: 1x10 35 Details still under study New technology for larger aperture quads (Nb 3 Sn) crab cavities? Improved injector chain (PS2 + SPL)? No major changes to optics or IR’s Possible Significant Changes February 16, 2010 3 Eric Prebys - LARP Annual DOE Briefing Focus of APUL LARP Magnet Program
4
Energy Joints not reliable above 3.5 TeV Run at 3.5+3.5 for ~fb -1 or roughly end of 2011 Shut down for ~18 months to do all repairs to get to 7+7 (or as high as quench problem will allow). Collimation Initial (Phase I*) collimation only good to a luminosity of a few 10 33. A plan is in place for collimation which is good to “ultimate” luminosity of a few 10 34. Schedule being worked out Will involve LARP collimators, if they survive tests. Crab Cavities In a major shift from last year, crab cavities are now considered part of the base line plan for the Phase II upgrade LARP has played a major role in this February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 4 *note confusing inconsistent “phases” for collimation and triplet upgrade
5
February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 5 Projection assuming Phase II collimation and Phase I upgrade done in 2013/2014 shutdown* *R. Assmann, “Cassandra Talk” Limit of Phase I (existing) collimation
6
The current studies seem to suggest that the bottleneck in the LHC will be not be the (50 year old) PS, but rather the SPS or the LHC itself. CERN is forming a working group to discuss the fate of PS2 Expect decision in ~6 weeks We consider it unlikely at this point February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 6 Intensity Limitations (10 11 protons per bunch) PresentSPL-PS22GeV in PS LINAC44.0 PSB or SPL3.64.03.6 PS or PS21.74.03.0 SPS1.2 LHC??? Proposed alternative: increasing PSB energy
7
Two years at 3.5 TeV 2010: should peak at 10 32 and yield up to 0.5 fb -1 2011: ~1 fb -1 at 3.5 TeV 2012: splice consolidation (and cryo collimator prep.) 2013: 6.5 TeV - 25% nominal intensity 2014: 7 TeV – 50% nominal intensity February 16, 2010 7 Eric Prebys - LARP Annual DOE Briefing Aggressive Year Months energy beta ibnbPeak Lumi Lumi per month Int Lumi Year Int Lumi Cul 201083.52.57 e107201.2 e32-0.2 201183.52.57 e107201.2 e320.10.81.0 2012Joint Repair 201366.511.1 e117201.4 e331.178 20147711.1 e1114043.0 e332.31624 fb -1 *From Mike Lamont’s Chamonix talk
8
In 2014, the LHC will optimistically accumulate ~10’s of fb -1, and the luminosity will still be increasing. The lifetime of the existing triplet magnets is ~500 fb -1 Is it likely the experiments will want to stop for a year upgrade followed by a year of re-commissioning? Consider two possibilities Delayed scenario Phase I upgrade delayed until ~2017 Phase II upgrade delayed until ~2023 Skip Phase I entirely Phase II still in 2020, or maybe even earlier CERN is supposed to make a decision regarding the Phase I upgrade in about 6 weeks Need to start moving on magnet production if it’s really going to happen. February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 8
9
Instrumentation Luminosity monitors fully installed and ready at IP1 and IP5 Intensity and energy too low to see so far Analyzing potential for 3.5 TeV operation Schottky DAQ application complete (LAFS), ready for data Intensity too low to see so far Issues with remote data access AC Dipole ready for use Awaiting permission for commissioning Synchrotron Light Monitor Already delivering useful information about beam Used to measure emittance growth February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 9
10
Instrumentation (cont’d) LLRF tools developed at SLAC (J. Fox, et al) were very useful in optimizing LHC RF system February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 10
11
What is the model for remote access to data? This has been an issue for Schottky already. (Working to put a liaison in the controls group) Handoff and support? eg, who’s responsible for software? Increased commissioning time for lumi, given new energy schedule (agreed to help during commissioning of Lumi while energy ramps up, but CERN will maintain) What will be the impact of IR upgrade(s) (TAN rebuilt) on the luminosity monitor? (There will still be a slot for the Lumi in the new TAN) What is the future of the AC dipole? Should LARP continue to support it? (agreed we need to work on this) Are there additional instrumentation topics where we could contribute? (no big ideas) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 11
12
Rotatable Collimators Continued good coordination with CERN Phase II collimation plan On track for prototype delivery, August 2010 Planning for SPS installation and testing after the 2010 run. Will test in HiRadMat facility when facility is complete (mid-2011). Crystal Collimation Exciting demonstrations from both T980 (FNAL) and UA9 (CERN) Test proposed in LHC T980 UA9 February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 12
13
New idea: hollow electron lenses as collimators/scrapers Lots of interest from CERN Demonstration of hollow beams at FNAL February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 13
14
Are LARP plans consistent with CERN expectations regarding prototyping and testing of the rotatable collimators? Current plan is one prototype for both SPS and HiRadMat facility. Do we need two? (Yes) If rotatable collimators are found acceptable for CERN use, what model is envisioned for construction CERN? US project (a la APUL)? (either is a possibility. Needs to be discussed) Are crystal collimation and/or hollow electron beam seen as possibilities for the LHC future? Given our limited resources, how much effort should LARP commit? (very excited about hollow electron beams as scrapers; want to keep investigating crystal collimation) Are there other ways LARP can contribute to the collimation effort? eg, redirect accelerator physics effort from electron cloud and/or beam beam? (Can probably use help) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 14
15
e-cloud E-cloud simulations have focused on developing the specifications for an RF feedback system in the SPS, based on MD periods in 2008 and 2009. These studies have also contributed to new vaccuum chamber design Prototype inserts to be installed in the SPS. Data Simulation February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 15
16
Beam-beam Electron lens Gaussian gun installed in Tevatron Evaluating multiple simulation tools for Tevatron, RHIC, and LHC BNL received $4M in stimulus money to work on electron lenses for RHIC, and we’re investigating how to profit from that program. February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 16
17
Beam-beam (cont’d) Flat beam studies for LPA solution C. Bhat undertook a series of studies in PS to investigate flattening bunches with higher harmonic for LPA solution Theory: Measurements and simulation at 26 GeV in PS February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 17 Note: Bhat starts as an LTV later this year
18
Accelerator physics is one of the areas where LARP can make significant contributions to the LHC This is because much of the scientific effort comes “for free” from the labs Is it CERN’s impression that we are using our resources as effectively as we can? Electron cloud? (Very important to PS2 and SPS) Beam beam? (Calculations are important; agreed we should keep an eye on RHIC wrt electron lens) Are there other areas where we can assist? Collimation? (Very likely) Crab cavity issues besides cavity design? (Part of the greater crab cavity issue) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 18
19
Crab cavities have now become the base line plan for Phase II luminosity and luminosity leveling. LARP has played a major role in bringing crab cavities to this point, however the resources needed to fully manage this effort are well beyond LARP The infrastructure requirements alone demand a central CERN role. (They agree) Discussion: What are CERN’s plans to move forward with the crab effort and how can we best contribute? (They don’t have a plan, but are working on one) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 19
20
LARP has planned to commit significant resources to the PS2 white paper. Agreed to write chapter on collective effects and feedback Uli Wienands is currently here as a Long Term Visitor to coordinate the effort In light of Chamonix, need to think about re-scoping We don’t want to put a lot of effort into a paper if the project isn’t going to go forward. Consider a de-scoped conceptual design to be completed this calendar year? Given our interest in collective effects, does it make sense to make the studies generic enough that they’re also applicable to a consolidation of the PS? (CERN agreed strongly on all points) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 20
21
Toohig Fellows (postdocs) Helene Felice (LBNL) ended Toohig Fellowship, now LBNL staff Riccardo di Maria (BNL) Beam beam studies Analyzing SPS e-cloud data Investigating crab cavities Ryoichi Miyamoto (BNL) AC Dipole Luminosity monitor Dariusz Bociam (FNAL) Modeling heat transfer in Nb 3 Sn magnets Temperature effects on Nb 3 Sn conductor February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 21
22
Long Term Visitors Steve Peggs (BNL) UA9 (Now moved on to ESS) Jim Strait (FNAL) Played an important role in data analysis and diagnostic development for superconducting joints following Sep. 19. Alan Fischer (SLAC) Significantly improved optical design of synchrotron light monitor Elian Gianfelice-Wendt (FNAL) Commissioning Rama Calaga (BNL, former Toohig Fellow) Commissioning, coordinating crab cavity effort Uli Wienands (SLAC) Coordinating US PS2 effort, UA9, and LHC machine studies Chandra Bhat (FNAL) Starting later this year to work on flat bunches for LPA. Discussion: Are there other efforts that could benefit from an increased US presence? (Nothing specific, but agreed that the LARP personnel had been very effective) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 22
23
LARP Magnet Development Chart Completed Achieved 200 T/m 1 st test 4/2010 Length scale-up High field Accelerator features February 16, 2010 23 Eric Prebys - LARP Annual DOE Briefing
24
The 54/61 conductor which we have traditionally used showed instability problems at 1.9K These appear to be solved with the finer filament 108/121 conductor The 108/127 conductor will be the choice for all future magnets. SSL 4.4K SSL 1.9K TQS02c test (CERN) TQS03a test (CERN) SSL 4.4K SSL 1.9K February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 24
25
The first LQ met 200 T/m design spec !!, However, based on TQ results, we expect it to go higher Believe this can be done by mechanically shimming the coils First long quad February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 25
26
Winding/curing (FNAL) Reaction/Potting (BNL and FNAL) Instrumentation and heater traces (LBNL) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 26
27
Structural pre-assembly complete Will be tested in 2010 Structure assembly Layer 1 Winding Layer 2 Winding February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 27
28
2010-2012: complete technology demonstration/qualification LQ addresses all length-related issues HQ addresses performance limits and accelerator features 2012 +: full scale prototypes and production Preparations (2010-2012): Converge on design specifications Project planning, infrastructure upgrades Nb 3 Sn design options and timelines: 120 mm aperture & <4 m length: ~2016 Larger aperture & longer length: ~2018 Discussion: How does this match with CERN’s plans and expectations? (This makes sense, given the earliest conceivable Phase II date) February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 28
29
February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 29
30
February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 30
31
In a major shift from last year, crab cavities have gained significant priority in CERN’s overall planning February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 31
32
Kills Phase I Test February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 32
33
In response to requests from CERN, LARP has organized significant effort to support the PS2 white paper (nominally due in 2012) Ultimately endorsed by review committees, the member labs and DOE Committed to writing the “Collective Effects and Feedback” chapter: Space-charge: check results for validity, scan working point, effect on lattice functions (if possible). Add E-ramp. Instabilities: Continue (Cu-)coating investigations; impedance of components as available. e-Cloud: include quadrupoles in build-up model, refinement of beam-instability estimates. Feedback: Spec. needed to deal with res. wall growth time(?) IPM needs re-grouping. Uli Wienands is currently at CERN as a Long Term Visitor to coordinate effort But… February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 33
34
Made the important technology decision between “collared” (traditional) and “shell” pre-load design: all future LARP work will focus on shell *see G. Sabbi, CERN BE Seminar, Jan. 12, 2010, for details February 16, 2010 Eric Prebys - LARP Annual DOE Briefing 34
35
Schottky detector Used for non-perturbative tune measurements (+chromaticities, momentum spread and transverse emmitances) Tune tracking Implement a PLL with pick-ups and quads to lock LHC tune Investigating generalization to chromaticity tracking AC dipole US AC dipole to drive beam Measure both linear and non-linear beam optics Luminosity monitor High radiation ionization detector integrated with the LHC neutral beam absorber (TAN) at IP 1 and 5. Low level RF tools Leverage SLAC expertise for in situ characterization of RF cavities Synchrotron Light Monitor Not originally LARP project Optics significantly improved by Alan Fisher Personnel Toohig Fellowship Postdoc program Long Term Visitors February 16, 2010 35 Eric Prebys - LARP Annual DOE Briefing
36
Rotating collimators Can rotate different facets into place after catastrophic beam incidents Aim for prototype in CY09 Crystal Collimation CRYSTAL Collaboration T980 Beam-beam studies General simulation Electron lens Wire compensation Flat beam studies Electron cloud studies Study effects of electron cloud in LHC and injector chain February 16, 2010 36 Eric Prebys - LARP Annual DOE Briefing
37
Coordination and basic lattice design Linear correction systems Non-linear dynamics and correction systems Collective effects and feedback systems Space charge studies Impedance estimates and instabilities e- cloud effects and vacuum system requirements Damping system specifications Collimation aspects Machine protection Instrumentation specifications and commissioning strategy *M. Benedikt and Y. Papaphilippou LARP will write this chapter February 16, 2010 37 Eric Prebys - LARP Annual DOE Briefing
38
Coax LOM/SOM coupler WG HOM coupler Power coupler At September review, CERN formally endorsed crab cavities for phase II Contingent on a plan to operate system safely!! They cancelled a proposed Phase I test of an 800 MHz cavity and recommended focusing all efforts on the final solution. Because of space limitations, will probably require “compact” cavity. R&D options might include tests of the KEK cavity at the SPS or elsewhere. LARP is working to decide its proper role: Overall concept? Machine protection? Cavity/cryostat design? SLAC half wave JLAB “toaster” Fermilab “mushroom” February 16, 2010 38 Eric Prebys - LARP Annual DOE Briefing
39
Magnet groups at FNAL, BNL, and LBNL working to demonstrate Nb 3 Sn magnet appropriate for use in the LHC Phase II upgrade. Currently pushing all parameters Long Quad (LQ): 4m quad with 90 mm aperture High field Quad (HQ): 1m quad with 130 mm aperture Accelerator physics questions: Optical design Field quality requirements Beam loss/heat loading issues Radiation damage. Working with CERN to assure that we’re in agreement as to what will validate the technology 120 mm aperture Phase I magnets February 16, 2010 39 Eric Prebys - LARP Annual DOE Briefing
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.