Northstowe Phase 1 Infrastructure Works Construction Phasing.

Similar presentations


Presentation on theme: "Northstowe Phase 1 Infrastructure Works Construction Phasing."— Presentation transcript:

1 Northstowe Phase 1 Infrastructure Works Construction Phasing

2 Established 1952 Based in Ipswich 7 regional offices 300 employees £70m turnover Introduction to Jackson

3 Regional office – Huntingdon Head office - Ipswich Support services Environment Health & Safety Quality Procurement Planning Locally based workforce

4 Over 35 contracts completed in Cambs since 2004

5 Addenbrookes Access Road

6 Cambridge Guided Busway

7 Bar Hill Roundabout

8 Huntingdon West of Town Centre Link Road

9 Site Access Overview

10

11 Site Compound Location

12 Compound Layout

13

14 some localised temporary diversions and temporary surfacing will be required

15 Only in operation 0930 to 1530 (Mon-Fri), occasionally Saturday 0800 to 1300

16

17

18 or temporary lighting as required

19

20 Proposed B1050 Reconstruction Works

21 Overall Northstowe Phase 1 Layout

22 Key points JCE long experience with local, similar schemes. Safe pair of hands Minimised impact of deliveries through recycling material, primary road access when possible, restricted access/egress using bypass. Maintain safe cycleway/footway at all times.