How to Perform Project Risk Management for Oil and Gas Projects
Intaver Institute 2011 How to Perform Project Risk Management for Oil and Gas Projects Intaver Institute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1(403) Fax: +1(403)
2
Introduction + Intaver Institute Timeline RiskyProject Clients
2002: Established 2004: V.1 RiskyProject 2009: v 3 Integrated Risk Register 2012: v 5 RiskyProject Full Project Risk Management Lifecycle Integrated Risk Register Risk Matrix, Risk Planning + Quantitative Monte Carlo Cost and Schedule Risk Analysis Clients 4/24/2017 2013 Intaver Institute
3
Gorgon Natural Gas Project
A three-train liquefied natural gas (LNG) facility on Barrow Island (Australia) that will produce 15.6 million metric tons of LNG per year. Project Cost Estimate in Billions A$ Date of cost estimate 4/24/2017 2013 Intaver Institute
4
Corporate Portfolio Management Process
Project Cost and Schedule risks and uncertainties Quantitative cost and schedule risk analysis is an important component of portfolio management Geological and other Uncertainties affecting production Economic Analysis of the Projects Corporate Portfolio Management Strategic Decision Price Uncertainties Other Risks and Uncertainties: Political risks Uncertainties in Royalties regimes …. 4/24/2017 2013 Intaver Institute
5
Risk Management Affects Project Profitability
Full circle cost of gas $/Mcf Quantitative risk analysis provides realistic risk adjusted and risk mitigated cost estimates 4/24/2017 2013 Intaver Institute
6
Identifying and Managing Critical Risks is Key
Quantitative risk analysis identifies and prioritizes critical risks Opportunity? Risk Threat? 4/24/2017 2013 Intaver Institute
7
Which risks are critical?
Schedule risk Cost Risk Safety Risk Legal Risk Quality Risk Enviromental Risk …………….. Risk 4/24/2017 2013 Intaver Institute
8
Time is Money: Cost and Schedule Risks
Schedule risk drives Costs due to time dependent resource costs 40% -70% cost risk is schedule driven Schedule risk Cost Risk Time Dependent Costs 4/24/2017 2013 Intaver Institute
9
Assign Risks to Project Tasks and Resources
Intaver Institute 2011 Risk Events Approach Input 1: Project Schedule Perform Analysis Assign Risks to Project Tasks and Resources Input 2: List of Risks (Risk Register)
10
Intaver Institute 2011 Schedule Import project schedule from project management tool (Primavera, MS Project, etc.. 4/24/2017 2013 Intaver Institute
11
Intaver Institute 2011 Costs Schedules can include cost data for quantitative risk analysis of fixed costs 4/24/2017 2013 Intaver Institute
12
Intaver Institute 2011 Resources To model schedule driven cost, we have included high level resources that have been assigned to specific tasks. Resources with rates are loaded with the project schedule to allow for risk analysis of time dependent costs 4/24/2017 2013 Intaver Institute
13
Project risk register is integrated to the project schedule and cost
Intaver Institute 2011 Risk Register Project risk register is integrated to the project schedule and cost 4/24/2017 2013 Intaver Institute
14
Risks are assigned to project activities
Intaver Institute 2011 Risk Assignment Task R1 R2 R3 R4 R5 R6 Installing Microsoft Seismic monitoring x Deliver frac fleet and install equipment Deliver rig and equipment Well 1,2,3 (share common risks) Rig Mobilization Drilling Installing Service Rig Completion (8 stages fracing) Risks are assigned to project activities 4/24/2017 2013 Intaver Institute
15
Risk Assignment Interface
Intaver Institute 2011 Risk Assignment Interface 30 % chance that risk causes a delay and increase in cost of drilling Risk Assigned to task ‘Drilling’ Risk probability and cost and schedule impact are assigned to activities 4/24/2017 2013 Intaver Institute
16
Run Monte Carlo Simulation
Intaver Institute 2011 Run Monte Carlo Simulation Monte Carlo simulation prioritizes risk based on impact on cost, schedule or other parameters 4/24/2017 2013 Intaver Institute
17
Intaver Institute 2011 Results of Analysis Monte Carlo simulation results for cost and schedule can be viewed as histograms or cumulative probability 4/24/2017 2013 Intaver Institute
18
Risk Adjusted Project Schedule
Intaver Institute 2011 Risk Adjusted Project Schedule Schedule with risks Schedule without risks Arrows show risk assignments 4/24/2017 2013 Intaver Institute
19
Project Cost Schedule without risks Schedule with risks
Intaver Institute 2011 Project Cost Schedule without risks Schedule with risks Results of quantitative cost risk analysis are shown on the Cost view 4/24/2017 2013 Intaver Institute
20
Risk Planning – Mitigation Plan
Intaver Institute 2011 Risk Planning – Mitigation Plan Risk response plans can be plotted on a Risk Mitigation Waterfall chart 4/24/2017 2013 Intaver Institute
21
Pre and Post Mitigation Risk Scores
Intaver Institute 2011 Pre and Post Mitigation Risk Scores Pre-mitigation Post-mitigation 4/24/2017 2013 Intaver Institute
22
Risk Planning Risk: Mechanical Problem with instrument
Intaver Institute 2011 Risk Planning Risk: Mechanical Problem with instrument Pre-Mitigation Cost 17, 178, 397 Post Mitigation $16, 734, 906 Risk response plans can reduce the expected cost of the project 4/24/2017 2013 Intaver Institute
23
RiskyProject Enterprise
Intaver Institute 2011 RiskyProject Enterprise Enterprise Risk Database: Schedules, Risks, Mitigation Plans RiskyProject Professional RiskyProject Lite RiskyProject Web 4/24/2017 2013 Intaver Institute
24
Contact Future Reading
Intaver Institute 2011 Future Reading Virine, L. and M. Trumper Project Decisions: The Art and Science. VA: Management Concepts Virine, L. and M. Trumper Project Think: Why Good Managers Make Poor Project Choices. England: Gower Publishing P. Leach Late and Over Budget: Why Projects Always Seem to Take Longer and Cost More Than Planned. Projects & Profits, Vol. V Issue - XI, November 2005 decisions.org Contact Michael Trumper Intaver Institute Inc. 4/24/2017 2013 Intaver Institute