Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26
2
VIEW 1 2014-7-6 Descriptions -Paint to wall was completed 2014-8-14 2014-8-21
3
VIEW 2 Descriptions -Paint to wall was completed -A/C equipment has installed on site 2014-8-14 2014-7-6 2014-8-21
4
VIEW 3 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21
5
VIEW 4 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21
6
VIEW 5 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21
7
VIEW 6 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21
8
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Ground Floor VIEW 1 VIEW 2 VIEW 5 VIEW 3 VIEW 6 VIEW 4 VIEW 7 VIEW 8 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26
9
VIEW 1 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21
10
VIEW 2 Descriptions -Paint to wall was completed -The door frame has installed 2014-8-14 2014-7-6 2014-8-21
11
VIEW 3 Descriptions -Paint to wall was completed -Furniture arrived on site 2014-8-14 2014-7-6 2014-8-21
12
VIEW 4 Descriptions -Plastering works in progress -The door has installed -Furniture has installed 2014-8-14 2014-7-6 2014-8-21
13
VIEW 5 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21
14
VIEW 6 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21
15
VIEW 7 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21
16
VIEW 8 Descriptions -All the existing finish will be demolish 2014-8-14 2014-7-6 2014-8-21
17
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C First Floor B Ground Floor A Ground Floor VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 9 VIEW 10 VIEW 13 VIEW 14 VIEW 12 VIEW 11 VIEW 5 VIEW 6 VIEW 7 VIEW 8 VIEW 4 VIEW 2 VIEW 1 VIEW 3 VIEW 5 VIEW 6 VIEW 7 VIEW 8 VIEW 9 VIEW 10 VIEW 1 VIEW 2 VIEW 5 VIEW 6 VIEW 3 VIEW 4 VIEW 7 VIEW 8 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26
18
VIEW 1 Descriptions -Paint to wall was completed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
19
VIEW 2 Descriptions -Paint to wall was completed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
20
VIEW 3 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
21
VIEW 4 Descriptions -Paint to wall was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
22
VIEW 5 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
23
VIEW 6 Descriptions -Site condition A Ground Floor 2014-8-14 2014-7-6 2014-8-21
24
VIEW 7 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
25
VIEW 8 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
26
VIEW 9 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21
27
VIEW 10 Descriptions -Site condition A Ground Floor 2014-8-14 2014-7-6 2014-8-21
28
VIEW 1 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
29
VIEW 2 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21
30
VIEW 3 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
31
VIEW 4 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
32
VIEW 5 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
33
VIEW 6 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21
34
VIEW 7 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
35
VIEW 8 Descriptions -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
36
VIEW 9 Descriptions -Paint to wall was completed -The door frame has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
37
VIEW 10 Descriptions -Paint to wall was completed -The door frame has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
38
VIEW 11 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21
39
VIEW 12 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21
40
VIEW 13 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
41
VIEW 14 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21
42
VIEW 1 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
43
VIEW 2 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
44
VIEW 3 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
45
VIEW 4 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
46
VIEW 5 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
47
VIEW 6 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8--14 2014-7-6 2014-8-21
48
VIEW 7 Descriptions -Paint to wall was completed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
49
VIEW 8 Descriptions -Paint to wall was completed C Ground Floor 2014-8-14 2014-7-6 2014-8-21
50
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road B First Floor E First Floor E First Floor VIEW 2 VIEW 3 VIEW 1 VIEW 2 VIEW 1 VIEW 2 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26
51
VIEW 1 Descriptions -Tile works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21
52
VIEW 2 Descriptions -Plastering works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21
53
VIEW 3 Descriptions -Tile works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21
54
VIEW 1 Descriptions -Tile works was completed E First Floor Female Toilet & Disable toilet 2014-8-14 2014-7-6 2014-8-21
55
VIEW 2 Descriptions -Tile works was completed E First Floor Female Toilet & Disable toilet 2014-8-14 2014-7-6 2014-8-21
56
VIEW 1 Descriptions -Tile works was completed E First Floor Male Toilet 2014-8-14 2014-7-6 2014-8-21
57
VIEW 2 Descriptions -Tile works was completed -The door frame has installed E First Floor Male Toilet 2014-8-14 2014-7-6 2014-8-21