Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04.

Similar presentations


Presentation on theme: "Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04."— Presentation transcript:

1 Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26

2 VIEW 1 2014-7-6 Descriptions -Paint to wall was completed 2014-8-14 2014-8-21

3 VIEW 2 Descriptions -Paint to wall was completed -A/C equipment has installed on site 2014-8-14 2014-7-6 2014-8-21

4 VIEW 3 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21

5 VIEW 4 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21

6 VIEW 5 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21

7 VIEW 6 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21

8 Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Ground Floor VIEW 1 VIEW 2 VIEW 5 VIEW 3 VIEW 6 VIEW 4 VIEW 7 VIEW 8 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26

9 VIEW 1 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21

10 VIEW 2 Descriptions -Paint to wall was completed -The door frame has installed 2014-8-14 2014-7-6 2014-8-21

11 VIEW 3 Descriptions -Paint to wall was completed -Furniture arrived on site 2014-8-14 2014-7-6 2014-8-21

12 VIEW 4 Descriptions -Plastering works in progress -The door has installed -Furniture has installed 2014-8-14 2014-7-6 2014-8-21

13 VIEW 5 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21

14 VIEW 6 Descriptions -Paint to wall was completed 2014-8-14 2014-7-6 2014-8-21

15 VIEW 7 Descriptions -Site condition 2014-8-14 2014-7-6 2014-8-21

16 VIEW 8 Descriptions -All the existing finish will be demolish 2014-8-14 2014-7-6 2014-8-21

17 Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C First Floor B Ground Floor A Ground Floor VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 9 VIEW 10 VIEW 13 VIEW 14 VIEW 12 VIEW 11 VIEW 5 VIEW 6 VIEW 7 VIEW 8 VIEW 4 VIEW 2 VIEW 1 VIEW 3 VIEW 5 VIEW 6 VIEW 7 VIEW 8 VIEW 9 VIEW 10 VIEW 1 VIEW 2 VIEW 5 VIEW 6 VIEW 3 VIEW 4 VIEW 7 VIEW 8 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26

18 VIEW 1 Descriptions -Paint to wall was completed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

19 VIEW 2 Descriptions -Paint to wall was completed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

20 VIEW 3 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

21 VIEW 4 Descriptions -Paint to wall was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

22 VIEW 5 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

23 VIEW 6 Descriptions -Site condition A Ground Floor 2014-8-14 2014-7-6 2014-8-21

24 VIEW 7 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

25 VIEW 8 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

26 VIEW 9 Descriptions -Plastering works was completed -Furniture has installed A Ground Floor 2014-8-14 2014-7-6 2014-8-21

27 VIEW 10 Descriptions -Site condition A Ground Floor 2014-8-14 2014-7-6 2014-8-21

28 VIEW 1 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

29 VIEW 2 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21

30 VIEW 3 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

31 VIEW 4 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

32 VIEW 5 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

33 VIEW 6 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21

34 VIEW 7 Descriptions -Plastering works was completed -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

35 VIEW 8 Descriptions -Furniture has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

36 VIEW 9 Descriptions -Paint to wall was completed -The door frame has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

37 VIEW 10 Descriptions -Paint to wall was completed -The door frame has installed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

38 VIEW 11 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21

39 VIEW 12 Descriptions -Site condition B Ground Floor 2014-8-14 2014-7-6 2014-8-21

40 VIEW 13 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

41 VIEW 14 Descriptions -Paint to wall was completed B Ground Floor 2014-8-14 2014-7-6 2014-8-21

42 VIEW 1 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

43 VIEW 2 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

44 VIEW 3 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

45 VIEW 4 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

46 VIEW 5 Descriptions -Furniture has installed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

47 VIEW 6 Descriptions -Plastering works was completed -Furniture has installed C Ground Floor 2014-8--14 2014-7-6 2014-8-21

48 VIEW 7 Descriptions -Paint to wall was completed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

49 VIEW 8 Descriptions -Paint to wall was completed C Ground Floor 2014-8-14 2014-7-6 2014-8-21

50 Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road B First Floor E First Floor E First Floor VIEW 2 VIEW 3 VIEW 1 VIEW 2 VIEW 1 VIEW 2 PROGRESS PHOTO REPORT - 04 Date : 2014-8-26

51 VIEW 1 Descriptions -Tile works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21

52 VIEW 2 Descriptions -Plastering works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21

53 VIEW 3 Descriptions -Tile works was completed B First Floor 2014-8-14 2014-7-6 2014-8-21

54 VIEW 1 Descriptions -Tile works was completed E First Floor Female Toilet & Disable toilet 2014-8-14 2014-7-6 2014-8-21

55 VIEW 2 Descriptions -Tile works was completed E First Floor Female Toilet & Disable toilet 2014-8-14 2014-7-6 2014-8-21

56 VIEW 1 Descriptions -Tile works was completed E First Floor Male Toilet 2014-8-14 2014-7-6 2014-8-21

57 VIEW 2 Descriptions -Tile works was completed -The door frame has installed E First Floor Male Toilet 2014-8-14 2014-7-6 2014-8-21


Download ppt "Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04."

Similar presentations


Ads by Google