Advanced Metering Working Group (AMWG) Update to RMS 1 August 5, 2014
2
Remains on target for a 4 th quarter release UAT In Progress Third-Party Volunteer Testers Technical Integration Sessions and Testing is ramping up Third-Party Market Integration / Instruction Webinars being scheduled for September and November. Details to be sent out via RMS and AMWG List Servs 2 3 rd Party Access
3
3 Status of AMWG Change Requests 17 Total AMWG Change Requests 3 AMWG Change Requests in Delivery for Q4 2014 with Third Party AMWG CR 2013 012, AMWG CR 2013 013, and AMWG CR 2013 014 The SMT Usability Study Conducted in 2013 Identified Enhancements Approved for Implementation to SMT These 3 AMWG Change Requests are Covered by the Approved Enhancements from the Usability Study and Were Already Targeted to be Delivered with Third Party 2 AMWG Change Requests Targeted for Delivery Q2/Q3 2014 AMWG CR 2013 016 - Q3 2014 and AMWG CR 2013 017 - DELIVERED These 2 AMWG Change Requests were Already Covered by Efforts in Progress by SMT to Relieve Market Requests Causing Significant Challenges to SMT Help Desk Ticket Volume, SMT Maintenance Backlog, and Infrastructure Resource Utilization
4
4 Status of AMWG Change Requests 5 AMWG Change Requests DELIVERED in Q2 2014 AMWG CR 2013 002, AMWG CR 2013 005, AMWG CR 2013 006, AMWG CR 2013 007, and AMWG CR 2013 009 These 5 AMWG Change Requests are Covered by Reports Already Existing in Place Internally to the SMT Joint TDSPs. These Required Minimal Effort to Repurpose to the Market and are Zero Dollar Estimates Minor Contract Revisions were Required with SMT Vendor to Publish These Existing Reports Externally to the Market. 7 AMWG Change Requests in Process for SMT Joint TDSP Estimation Process Step AMWG CR 2013 001, AMWG CR 2013 003, AMWG CR 2013 004, AMWG CR 2013 008, AMWG CR 2013 010, AMWG CR 2013 011, and AMWG CR 2013 015 These 7 AMWG Change Requests are all New Requirements requiring New Development and will be in Process of Estimation with the SMT Joint TDSPs as Resources are Available in 2014
5
Training completed in the July AMWG meeting Market Notice was sent to RMS List Serve on July 9 th and July 21 st to notify the market of the training Approximately 65 market participants attended Training documents will be posted to the AMWG main page on the ERCOT website at http://www.ercot.com/committees/board/tac/rms /amwg/ http://www.ercot.com/committees/board/tac/rms /amwg/ 5 Change Request 16 & 17 SMT ROR Historical Backfill Functionality and Subscription for New Customer Enrollment History Functionality
6
Report Types 02 - Data Timeliness Measurements 05 - Number of SMT Help Desk Tickets Monthly by Ticket Type 06 - Availability of SMT API 07 - Availability of SMT FTPS 09 - Number of Accounts by Type Delivery Mechanism Reports to be distributed along with the AMWG meeting materials via the email to the AMWG list serve and posted to the AMWG main page on the ERCOT website at http://www.ercot.com/committees/board/tac/rms/am wg/ http://www.ercot.com/committees/board/tac/rms/am wg/ 6 SMT Reports for CR’s 02, 05, 06, 07 09
7
3 rd Party Registration & Account Management 7 AMWG Change Request AMWG CR Document Status Estimated Delivery Date Estimated Cost AMWG CR 2013 001 – Report for AMWG Data Monitoring – Data Completeness Measurements JDOA Estimation 2015In Process AMWG CR 2013 002 – Reports for AMWG Data Monitoring – Data Timeliness Measurements CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 003 – Reports for AMWG Data Monitoring – Measurement of Percentage of Actual Meter Reads JDOA Estimation 2015In Process AMWG CR 2013 004 – Reports for AMWG Data Monitoring – Measurement of Estimates JDOA Estimation 2015In Process AMWG CR 2013 005 – Reports for AMWG Data Monitoring – Number of SMT Help Desk Tickets Monthly by Ticket Type CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 006 – Reports for AMWG Data Monitoring – Availability of SMT API CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 007 – Reports for AMWG Data Monitoring – Availability of SMT FTPS CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 008 – Reports for AMWG Data Monitoring – Average Time to Deliver HAN Messages JDOA Estimation 2015In Process AMWG CR 2013 009 – Reports for AMWG Data Monitoring – Number of Accounts by Type CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 010 – Reports for AMWG Data Monitoring – Number of Reports Requested by GUI (Portal) and Number of FTPS Accesses JDOA Estimation 2015In Process AMWG / RMS Change Requests
8
3 rd Party Registration & Account Management 8 AMWG Change Request AMWG CR DocumentStatus Estimated Delivery Date Estimated Cost AMWG CR 2013 011 – Average Time from HAN Provision Request to Meter Ready Status JDOA Estimation 2015In Process AMWG CR 2013 012 – Bypass redundant screen for Users with only one meter when accessing HAN device information In Development Q4 2014 Included in Third-Party AMWG CR 2013 013 – Timeout on SMT takes user to “incorrect login” screen In Development Q4 2014 Included in Third-Party AMWG CR 2013 014 – Allow SMT user to toggle between 15-Minute Reads and Daily Reads without having to reset the date range In Development Q4 2014 Included in Third-Party AMWG CR 2013 015 – Expand Daily Usage Graph to show 35 days of daily usage on the SMT GUI JDOA Estimation 2015In Process AMWG CR 2013 016 – Capability for RORs to grant access to vendors on their behalf to the ROR’s customers via API (energy usage, HAN messaging, and HAN provisioning) and FTPS files In Development Q3 2014 Included in Maintenance Contract AMWG CR 2013 017 – REP API for Energy Usage on SMT (Backfill of Historical Usage Data for Existing Customers- “Interim”) See Below CR 2013 017 Permanent CompleteQ4 2013Completed AMWG CR 2013 017 – REP API for Energy Usage on SMT (Subscription for New Customer Historical Usage – “Interim”) See Below CR 2013 017 Permanent CompleteQ2 2014 Included in Maintenance Contract AMWG CR 2013 017 – REP API for Energy Usage on SMT – Permanent Solution to Replace Interim Solution JDOA Estimation 2015In Process AMWG / RMS Change Requests (Cont.)
9
Distributed Generation Change Request Excess production is available via downloading usage reports from SMT Goal is to have the data viewable on the SMT portal Future AMWG Meetings August 26: 1:30 p.m. – 4:30 p.m. via WebEx September 23: 1:30 p.m. – 4:30 p.m. via WebEx October 22: 9:00 a.m. – noon via WebEx Nov & Dec = TBD @ October meeting 9 Additional Items
10