Download presentation
Presentation is loading. Please wait.
Published byBelinda Lang Modified over 9 years ago
1
Mod 0273: 3 rd Development Group Workshop 4 th March 2010
2
Contents 1.Answers to 1 st Workshop Questions Number of large Projects Capacity Application/Connection Timeline 2.Overview of Shipper and GT issues identified at 1 st Workshop 3.Possible solutions to issues identified 4.Appendix A – Issues Summary
3
Answers to 1 st Workshop Questions
4
More information on CUSC process Number of large projects 3/4 power stations in Gas Similar number of power stations in Electricity 20~ other large electricity projects (tbc)
5
How does gas connection process fit in with associated capacity request? Conc. DesignDetailed Design Gas Year +1 Gas Year +2Gas Year +3Gas Year +4 Annual Window (July) For a new Exit Connection, Shippers / Developers should approach National Grid’s Customer Services Team as early as possible to discuss the capacity & connection process Initial Discussion NTS License Amendment NTS Re-enforcement (if necessary) Siteworks Feasibility Study Agree & Sign NExA Capacity New Connection NExA NTS Exit (Flat) Capacity Request (For Capacity from Gas Year +4)
6
Shipper and GT issues identified at 1 st Workshop See appendix A for full details
7
Summary of Key Issues Identified Lack of process transparency Unknown timescales & costs at outset Difficulties in understanding requirements /agreeing study scope Elongated contractual negotiation Poor communication Difficulties in providing information No set timescales
8
Process – Possible Solutions Potential SolutionAdvantagesDisadvantages Develop template to ensure all required info is provided up front Able to implement relatively quickly Will reduce admin timescales & enable projects to be agreed & start ASAP May reduce flexibility of transporters to begin project with minimal data and build up info as project progresses Customers may need time to populate, especially if info is required from elsewhere or it may be seen as bureaucratic if unnecessary info is requested Standard contractual terms Able to implement relatively quickly Will reduce admin timescales & enable projects to start ASAP/once scope of study is agreed Does not provide contractual flexibility Delays may still occur in signing contract and have a knock on effect to study start times Customer Enquiry Form A Standard Form has now been developed for new connections (see form) A Form for Modification requests is under development Standard Contractual Terms NG already have standard T&Cs but a review is underway to assess whether they are fit for purpose/could be enhanced (Design & Build Agreement first, then Feasibility Agreement) Would an industry consultation be advantageous?
9
Communication – Possible Solutions Potential SolutionAdvantagesDisadvantages Create standard project communications documents Formalised Comms. Process will report regular progress, next steps & risks / issues (on monthly basis) Could be applicable to all ongoing projects irrelevant of size Additional admin work for both parties Does not capture (future) work not yet progressed/discussed Increased Cost Increased red tape Potential delays to study process Develop & agree a high-level project plan to highlight key milestones Visibility of important milestones Manages customer expectations & allows customer to plan activities accordingly Planned timescales may be subject to change Provision of key contact information Will enable right people to talk to each other direct and reduce hand time taken to obtain information, etc. Include key Engineer & Commercial contacts within new modification enquiry form (see previous slide) A high-level project plan template is under development
10
Timing – Possible Solutions (1) Potential SolutionAdvantagesDisadvantages Review NTS website to ensure new connection & modification processes timescales are transparent and meet customer requirements Able to implement relatively quickly Low cost Aid visibility of end-to-end process (inc feasibility) Manage customer expectations of overall process duration Unlikely to directly ‘speed up’ process Case studies may not cover every scenario Improve case studies both on-line and within Charging Methodology Statement Review of connection information on National Grid website Website Improvements are due to be implemented this summer Review of Gas Connection Charging & Methodology Statement See further examples – Do they aid understanding of timescales / likely costs? Development of Feasibility Study Cost / Timescale Matrix Combined with the above example, does this provide enough indicative information?
11
Timing – Possible Solutions (2) Potential SolutionAdvantagesDisadvantages Introduce ‘no longer than’ timescale for all feasibility studies Provides users with confidence in timescales Allows ‘worst case’ date to be utilised in user planning process Longer term solution – how would it be introduced (licence change)? Blanket ‘worst case’ date may not be suitable for all types of study Does not focus on root cause of issue (time spent to agree scope/costs, etc.) May increase cost of survey if required timescales are shorter than current times Defining appropriate fixed timescales up front may be difficult given complexity of requests Introduce ‘fixed’ timescales for feasibility studies Fixed timescales? When would clock start??
12
Costs – Possible Solutions Potential SolutionAdvantagesDisadvantages Develop on-line ‘decision tree’ & develop time/cost matrix to support Able to implement in medium term Medium cost Will provide a more accurate indication of cost & timescale to users May prove difficult to capture all eventualities / variety of projects If not robust may cause customer challenges Develop fixed prices Published fixed prices will manage customer expectations/reduce challenges (take it or leave it?) May prove difficult to price up all possible projects Current process requires obtaining price from external contractors May frequently change due to market prices Some Customers may still want indicative prices (possible refund) and any effort spent in developing fixed prices will have been wasted See timing solution slide 1 (improved indicative price information/examples) Fixed Prices? Very rarely chosen in Electricity!
13
Summary of Possible Solutions Enhance process information to provide greater clarity / transparency Streamline process - templates Provide enhanced indicative timescales & costs Revised terms and conditions Set timescales ? – costs and benefits
14
Appendix A – Issues Summary
15
Process - Issues UserTransporters No standardisation across Transporters. No standard documentation / T&Cs / applic. process. Number and nature of studies required unknown until well into the process and can change as project develops within Transporter. Lack of process transparency. No guarantee of non-discrimination in treatment by Transporter – e.g. how can we be certain that Transporter not prioritising all the “easier” requests? Unclear definitions of types of study – e.g. what is the difference between “feasibility study” and “pre-feasibility study”? Transporters not always clear what info they want from Shippers and is what they ask for always relevant / necessary? Number of gas enquiries is small compared to electricity Some enquiries are speculative in nature Scope creep is sometimes a problem Customers don’t always know what they want! Customers often experience difficulties in providing the information requested, especially if it needs to be provided by their equipment suppliers Difficulties in agreeing Contractual terms (between Customer and NG) By offering flexibility and offering new products (e.g. pre-feasibility) definitions have been diluted
16
Communication - Issues UserTransporters Relies on individuals within Transporter to progress request, rather than established process. May require Shippers to do lots of chasing to obtain updates on progress. No visibility of upcoming work (types, number, nature and frequency) - receiving a number of enquiries in a relatively short period can cause workload planning difficulties
17
Costs - Issues UserTransporters Unknown at outset. True costs often not known until well into the application process and can differ substantially from initial estimate (where provided) No idea whether costs are currently “cost- reflective” and Shippers in a poor position to challenge them Breakdown of costs – not always clear what we are actually paying Rough costs are provided upon initial application Refined costs are provided upon agreement of scope Complexity of exit connections/modifications and associated differences in scope make it difficult to define exact costs upfront License states that Transporters can charge users in respect of the cost incurred
18
Timing - Issues UserTransporters Open-ended process – no established time limits. Unable to initially gauge how long Transporter will take to deal with request(s). No obligation on Transporter to respond by any set date(s). Indicative timescales are provided and contracts include end dates for scheduled completion of works Complexity of exit connections/ modifications and associated differences in scope make it difficult to define exact timescales upfront
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.