Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 1 EVLA Monitor & Control
2
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 2 Topics The Overall Design Module Interface Board Hardware & Software The M&C Transition Plan M&C Subsystem Design
3
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 3 Overall Design In June 2004 a high-level design for all EVLA software was completed This design is presented in a document entitled “ EVLA High Level Software Design” It is document # 33 on the EVLA Computing Working Documents web page: http://www.aoc.nrao.edu/evla/techdocs/computer/ workdocs/index.shtm
4
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 4 Overall Design Transparency of Data Flow Diagram
5
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 5 Module Interface Board Hardware The Module Interface Board (MIB) is the means by which EVLA antenna subsystems will be monitored and controlled. The hardware design has been finalized and is ready for quantity production. An M&C Hardware and MIB Software CDR was held on 10/20/2004 No significant impediments to quantity production of the MIB were found The report of the review panel for the CDR can be found on the CDR web page: http://www.aoc.nrao.edu/evla/admin/reviews/MIB/MIB.html
6
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 6 Module Interface Board Software Uniform, self-describing interface to all MIB-connected devices. Simple [set, get].. syntax Consists of a generic framework common to all MIBs plus module specific software Framework services include a Service Port, Data Port, Alarms & Alerts, Error Messages, Logging Messages Documents describing the Framework SW, Service Port and Data Port are available on the Computing Working Documents web page: http://www.aoc.nrao.edu/evla/techdocs/computer/workdocs/index.shtml
7
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 7 M&C Transition Plan The M&C Transition Plan referred to here is a plan for software development that accommodates the transition from the VLA to a hybrid VLA-EVLA array, and then to the EVLA. The document is entitled “VLA/EVLA Transition Observing System Development and Re-engineering Plan”, dated September 04, 2004, written by Tom Morgan of the ECD. Available on the Computing Working Documents web page: http://www.aoc.nrao.edu/evla/techdocs/computer/workdocs/index.shtml, as document # 37
8
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 8 M&C Transition Plan The M&C Transition Plan consists of 7 phases Phases I - III lead to the elimination of the Modcomp computers Phase IV develops support for on-the-sky testing of the WIDAR correlator prototype Phase V develops support for on-the-sky-testing of the production version of the WIDAR correlator At the end of Phase VI, shared risk observing by external users will be supported Phase VII completes EVLA support for regular science observing using EVLA antennas and the WIDAR correlator
9
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 9 M&C Transition Plan Phase I Primary Objectives (Jan 31, 2005) Basic software in place for use of one or more EVLA antennas in the VLA for observing Phase II Primary Objectives (Q2 2005) New VLA correlator controller Begin work on control of VLA antennas by EVLA Begin migration of Antsol, Pointing Offsets & Archiving Phase III Primary Objectives (Q4 2005) Transfer all remaining functionality to EVLA systems Retire the Modcomps and the Array Process
11
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 11 M & C Subsystem Design Synched with the phases of the M&C Transition Plan M&C Transition Plan software will serve as testbeds for subsystem design The mature form of the EVLA software must grow from the M&C Transition Plan software –To enable continuous operation of the array –Reasonable software development scenarios –Schedules –Manpower
12
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 12 M &C Subsystem Design At end of Phase I of M&C Transition Plan (1/31/2005) Designs for production versions of Observation Executor, Antenna Objects, CALC Design for User Interfaces to non-mib processes A more detailed description of remaining subsystems and their technical requirements A software development plan that includes task breakdowns, task interdependencies, time allocations, and resource allocations.
13
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, 2004 13 M & C Subsystem Design During Phase II of M&C Transition Plan (Q2, 2005) Refine subsystem designs developed during Phase I Specify designs for some of the remaining subsystems –Antsol as a Telcal precursor –Control of VLA correlator –VLA Data Capture & Format (DCAF) as EVLA DCAF prototype –Archiving (VLA format) by EVLA system Revise and update the SW development plan generated at the end of Phase I of the M&C Transition Plan