EGIS Working Group Meeting March 18th, 2013 3/18/20131
2
Agenda 1.PAO Tax Parcel Viewer Demo 2.Staff News 3.MapGuide Retirement Strategy Update 4.MapGuide Solution Design Status 5.Q1 Release Status 6.Data Migration Schedule 7.Q2/Q3 Work Program 8.Eligible Agency Agreement Review 3/18/20132
3
Demo PAO Tax Parcel Viewer 3/18/20133 http://paogisvrt2/paotpv/default.htm
4
Staff News 3/18/20134
5
MapGuide Retirement Strategy Update Rationale Loss of MapGuide / Oracle Spatial expert Loss of institutional knowledge critical to executing data migration Need to minimize investment of scarce resources in the legacy system and to focus energy on transitioning to the Esri platform 3/18/20135
6
MapGuide Retirement Strategy Update Three Parts ArcGIS Online Rollout Data Migration Solution Implementation 3/18/20136
7
MapGuide Retirement Strategy Update Rollout ArcGIS Online Rollout to Working Group and some delegates by 3/15 Focus group webinars for training. Bikes & Trails for sample data, week of 3/18 Initially ArcGIS Online will take advantage of Esri base map data and data imported by end users 3/18/20137
8
MapGuide Retirement Strategy Update Data Migration Migrate legacy data into the Esri database prior to April 1st, 2013 Includes Planning, Emergency Management, Public Safety Services, and Base data DEI and Web Enforcer data (vendor-timeframe TBD) Institute data editing in the Esri database, April 1 st Suspend backfill of data from Esri back to MapGuide/Munsys Manual dual entry if data must be updated in MapGuide BTS Bureau performs Esri editing until data stewards assume responsibility Schedule Esri training to support data stewards commencing Esri editing 3/18/20138
9
MapGuide Retirement Strategy Update Solution Implementation Connect ArcGIS Online and ArcGIS Desktop to eGIS data by April 1 st Planning, Emergency Management, Public Safety Services, and Base data Implement Pinellas Base map to ArcGIS Online and ArcGIS Desktop by April 1 st Implement Esri software apps and DEI data migration by July 1 st ** Esri partner to perform data migration for DEI datasets Environmental, Public Works (Non-EAM) Esri partners to replace critical MapGuide functions Connect ArcGIS Online and ArcGIS Desktop to DEI data by July 1 st ** ** Target date, pending vendor negotiation 3/18/20139
10
MapGuide Retirement Strategy Update 3/18/201310
11
MapGuide Retirement Strategy Update Implementation Funding BCCTSC authorized $60,000 funding for MapGuide Replacement implementation services. 3/18/201311
12
MapGuide Retirement Strategy Solution Design 3/18/201312
13
Q1 Release Update Go Live Date Moved from 4/1 to 4/15 Precipitated by resource constraints Reviewed with eGIS SC on 4/4 Print function deferred temporarily from Know Your Zone 3/18/201313
14
Q1 Release Update - Dashboard 3/18/201314 RELEASE PROJECT:2013-Q1R493952 WG CANDIDATES IDENTIFIEDDONE12/20/2012ATP = Approval To Proceed EFFORT ESTIMATES VS. AVAILABILITYDONE1/7/2013BTS = Business Technology Services WG RECOMMENDATIONDONE1/8/2013UAT = User Acceptance Test BTS ATP GATE 1DONE1/15/2013WG = eGIS Working Group STEERING COMMITTEE APPROVALDONE1/10/2013 REQUIREMENTS /DESIGN PEER REVIEWDONE1/23/2013 BUILD PEER REVIEW TEST / IMPLEMENTATION PEER REVIEW BTS ATP GATE 5 GO-LIVE 4/15/2013Revised Target LESSONS LEARNED SUB-PROJECTS: REQUEST TICKET REQUIREMENTS COMPLETE DEV / CONFIG COMPLETEUAT COMPLETEIN PRODUCTION #60 Legacy MapGuide Retirement (requirements gathering and solution design) R426456DONE N/A #61, #61a, #61b Emergency Management MapGuide retirement - Hurricane Evacuation Lookup (Know Your Zone) R485592DONE #62 Justice CCMS Project Request - Subpoena/Warrants GIS Interface - Prototype Only R485593DONE N/A #58Public Safety Services (PSS) DEV environmentR485595DONE #9aParcel ViewerR475617DONE #57ArcGIS On-Line - Research OnlyR485597DONE #25Community Map - Initial Set-Up OnlyR485598N/A #27Configuration Manual - Final BTS ReviewN/A DELAYED
15
ArcGIS Online (AGO) Schedule 3/18/201315 Data Migration (Wave 1) Schedule Other Esri Training – Working instructor schedule availability with Esri (Heather) Migrate DEI Data (Wave2) – Schedule pending contract negotiation with Esri partner / vendor (Jason) Migrate EAM-GIS Data – Schedule TBD (EAM Project)
16
Training and Communication Preliminary Survey Results Preliminary Training Plan Draft Newsletter, Approve at 4/2 Working Group Meeting 3/18/201316
17
Next Steps Distribute Requirements Detail to Working Group For MapGuide Retirement Solution Design, by 3/22 Final Recommendation for MapGuide Retirement Solution Design Critical input to contract negotiation with Esri partner / vendor Working Group Meeting on 4/2 3/18/201317
18
Q2-Q3 Work Program Two Major Components Esri Partner for MapGuide Retirement Contract Negotiations, Mid April TARGET Kickoff Workshop, Mid April TARGET Detailed Schedule To Be Completed Other Q2/Q3 Candidates e.g., EAM-GIS Workshops 3/18/201318
19
Q2-Q3 Work Program – What will BTS Technical Resources Do? Technical oversight (solution architecture and compliance) Support Partner with access to eGIS resources such as test databases, and other technical tasks, etc. Integrate Partner configured solutions into eGIS infrastructure Coordination of UAT and Peer Reviews Execution of production rollout Other Candidates for Q2/Q3 (outside of vendor scope) 3/18/201319
20
Eligible Agency Agreement Review 3/18/201320
21
Open Discussion 3/18/201321