Quilt Optical Fiber Workshop Boulder Research and Administrative Network (BRAN) Experiences/Lessons Learned By Jim Van Dyke
2
6/22/04 - 2 BRAN Introduction Four Partners: NCAR/UCAR, City of Boulder, NOAA/NIST, CU at Boulder Boulder metro installation to connect partner sites A 96 strand SMF-28 fiber from end to end Nodes are spliced and pigtailed
3
6/22/04 - 3
4
6/22/04 - 4 Development Initiated by technical side, not management side Four partners mean: cooperation, politics, serving special interests Management and technical folks had to work together to develop project RFP process with detailed specifications
5
6/22/04 - 5 Specifications Identify lead party to develop and champion specifications Do not compromise quality Document and confirm the details Have other parties review specs and proposals
6
6/22/04 - 6 Construction Electrical contractor won the bid with a communications subcontractor The contractor underestimated the complexity/cost of the installation – it is called “Boulder” for a reason –Hit countless big rocks –Hit at least 2 water mains –Locates/paths under busy intersections difficult –Working with railroad RoWs difficult
7
6/22/04 - 7 Prepare for Setbacks
8
6/22/04 - 8 Installation Assign lead party to manage installation Spend time with the contractor/installer up front Verify quality of fiber installers/splicers prior to installation
9
6/22/04 - 9 Acceptance Criteria Quality components Bend radius Pulling tension Splice quality Connector quality 100% fiber strand verification Make sure your expectations are clear up front –Verify quality early and often
10
6/22/04 - 10 Connector Faces
11
6/22/04 - 11
12
6/22/04 - 12 Phased implementation Specifications should allow turning up links in the path without having the entire project done
13
6/22/04 - 13 Maintenance: Do you maintain or outsource? Coordinate outsource management –Locator –Manhole verification - annuallyManhole verification –Repair We maintain –Emergency parts –Contingency fund
14
6/22/04 - 14 Maintenance – annual manhole verification
15
6/22/04 - 15
16
6/22/04 - 16 Expansion Collocated at local PoPs Have a common bundle of fiber go to every new node/spur and be terminated for route testing
17
6/22/04 - 17 Questions?