Incentives & Infrastructure Estimated incentives and Infrastructure cost: $87,000,000 We will have a Development Agreement with Microsoft that will also have a minimum assessment agreement requiring a minimum property valuation of $255,000,000 at the end of Phase IV
5
Project Description Four phase data center Area: 154 acres Total investment: $1,126,218,000 Total building size: 1,165,364 square feet Total employment: 84
6
Potential Infrastructure Improvements South 8 th Street (old Army Post Rd to County Line Rd) Pine Avenue to new Army Post Road
7
Potential Infrastructure Improvements Continued Pine Avenue upgrades (eastern Corporate Limits to South 8 th Street) Maffitt Road/County Line Road connection (South Veterans’ Parkway to County Line Road) County Line Road connector to Maffitt Road extension
8
Water & Sewer Water line distribution/storage upgrades Sanitary sewer line upgrades
9
Services Relocation of MidAmerican power line Fiber optic conduit/fiber line installation Public Safety Facility (to be constructed/equipped as part of TIF District at a date to be determined)
10
Schedule Review plans (Phase I only) Grading Construction of Phase 1 Open Phase 1 Future Phases