Download presentation
Presentation is loading. Please wait.
Published byJonas Paul Modified over 9 years ago
1
Cost valuation reconciliation
2
When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes two weeks to complete Discussed at Monthly CVR meeting © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2
3
Fundamental principle Prudence Match expenditure with income Uses the application for payment and the architects certificate to substantiate the valuation/Net sales value of the works © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3
4
Documentation used External valuation – Identification of: Overmeasure Undermeasure Variations in dispute Claims in dispute Materials on site Undercertification © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4
5
Information flows © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 5
6
Documentation (contd.) Overmeasure schedule Undermeasure schedule Subcontractor liability build-up Architects/Engineers certificates Contra charge invoices © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6
7
Definitions Overmeasure – Claimed-Unpaid – Claimed-Paid Definition-“Application for monies in advance of their eligibility” Undermeasure Definition-“Work completed that costs have been incurred for but haven’t been included in the application for payment” – Measured works – Variations Work in Progress Definition-“Work that has been carried out in the period between the cost cut-off date and the valuation date” © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7
8
Basic principle Net sales value uses the application for payment as the baseline Application adjusted as follows: – Overmeasure – Deducted – Undermeasure - Added – Materials on site - Deleted © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8
9
Basic principle Net sales value uses the application for payment as the baseline Application adjusted as follows: – Overmeasure – Deducted – Undermeasure - Added – Materials on site - Deleted © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9
10
Documentation supporting the CVR Internal valuation broken down into a set of allowances Overmeasure schedule Undermeasure schedule Cost statement Subcontractor liabilities Buying reconciliation Materials reconciliation Cost to complete exercise Estimated final account/profit margin Architects/Engineers certificate Narrative explaining variances © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 10
11
Cost statement © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 11
12
Adjustments for work in progress © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 12
13
When to report a loss? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 13
14
Internal and external bills © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 14
15
Adjustments © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 15
16
Simplified CVR pro forma © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 16
17
A more complex example 17
18
Discussions at CVR meeting Profit release Cash flow Turnover Items in dispute – Variations – Claims Items for management action © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 18
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.