A PLAN TO BUILD AN ELEVATOR October 15, 2008 2006 Long-Range Plan –Office-size Elevator –New Fireproof Stairs –Handicap-Accessible Restrooms –Large Multi-purpose Fellowship Hall 2008 Memorial Elevator –Office-size Elevator (4’x6’ – six people or wheelchair plus two or three people)
3
FIRST PRELIMINARY PLAN January 2005 LARGE FOOTPRINT LONG SETBACK FROM DRIVEWAY CASKET-SIZED ELEVATOR SIX LARGE HANDICAP RESTROOMS NEW FIREPROOF STAIRWELL EXPENSIVE
4
SURVEY OF BUILDING NEEDS August 2005 SMALLER ELEVATOR LESS RESTROOMS CAPACITY WEATHER PROTECTED ENTRANCE FUTURE NEW MULTI-PURPOSE HALL FUTURE NEW KITCHEN RENOVATE OLD FELLOWSHIP HALL
5
LONG-RANGE PLAN April 6, 2006 SMALLER ELEVATOR IMPROVED STAIRS LESS RESTROOMS CAPACITY WEATHER PROTECTED ENTRANCE LARGER MULTI-PURPOSE ROOM FEWER $$$
6
FIRST FLOOR ALL PHASES COMPLETED
7
FIRST FLOOR PHASE 1 - ALTERNATE
13
BASEMENT
14
SECOND FLOOR
15
A PLAN TO BUILD AN ELEVATOR October 15, 2008 2008 Memorial Elevator –$150,050 + $3,700 = $153,750 Elevator Fund –About $130,000 Shortfall (today) –$23,750 Pledges –$12,200 Need $11,550 more
16
Additional Options Canopy over Handicap Entrance - $2,200 Hardtop Driveway - $3,750 Face brick on East side - $2,000 One handicap restroom - $27,000 Inside double doors - $1,000 per pair
17
MANAGEMENT Elevator Building Committee –Mary Broy Treasurer –Jeff Fanning Associate Project Manager –Rose Staples Assistant Treasurer –Dick Hill Chairman & Project Manager – open Safety and Security Officer