Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. November 5, 2007 Prepared.

Similar presentations


Presentation on theme: "Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. November 5, 2007 Prepared."— Presentation transcript:

1 Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. November 5, 2007 Prepared by:

2 Pool Phase “Ross House Pool” The new pool shell has been installed. Masonry has begun on the exterior walls of the seating area and filtration room additions. Brentwood UFSD

3 Phase IA Fire Alarm Upgrades Brentwood UFSD Fire Alarm upgrades are on schedule and will continue into the Fall.

4 Phase IA Exterior Door Replacement and Bleacher Replacements Brentwood UFSD The exterior doors that are scheduled to be replaced have been ordered and are being manufactured. This work will take place in late Fall of 2007 off hours while school is not in session. The new gymnasium bleachers are being installed and should be completed by November 19, 2007.

5 Phase IA Exterior Door Replacement and Bleacher Replacements (cont’d) Brentwood UFSD New gymnasium bleachers at the Ross Center.

6 Phase II - North Elem. School - Ross Center - Northeast Elem. School - Oak Park Elem. School - North Middle School - E. Kindergarten Center - Twin Pines Elem. School - West Middle School Brentwood UFSD The following buildings are associated with Phase II.

7 Phase II (cont’d) Brentwood UFSD The scope of work in Phase II will include: Window replacements Electrical, HVAC system, Plumbing upgrades Fuel tank replacements Exterior bleachers and Site work Exterior door replacements Locker room renovations Space expansion at selected buildings Phase II is currently in the Planning/Design phase. Drawings are scheduled to be submitted to S.E.D. in November, 2007.

8 Phase III Brentwood UFSD Phase III includes work at all schools. The scope of work is limited to district-wide Technology and Security upgrades. The drawings for Phase III were submitted to S.E.D. in September, 2007.

9 Phase IV - Pine Park Elem. School- South Middle School - Freshman Center- East Middle School - Ross Center- Southeast Elem. School - Sonderling Center- Laurel Park School - Loretta Park School- Southwest Elementary - Hemlock Park School Brentwood UFSD The following buildings are associated with Phase IV.

10 Phase IV (continued) Brentwood UFSD The scope of work in Phase IV will include: Window replacements Electrical, HVAC system, Plumbing upgrades Fuel tank replacements Exterior bleachers, Tennis courts, and Site work Locker room renovations Misc. exterior door replacements Misc. flooring replacements Auditorium renovations Roofing replacement Space expansion at selected buildings. Phase IV is currently in the Planning/Design phase.

11 Computer Update New computers will be installed at Southwest by November 15. The computers at Laurel Park and North Elementary will be installed before the end of the year. Brentwood UFSD