FUI Stakeholder Group 3rd December 2008 Congestion Management project
2
Recap National Grid and RTE are progressing the Capacity Management System project to achieve CM Guidelines compliance. Slides presented on 4 July 08 are available at: –www.nationalgrid.com/uk/Interconnectors/France/GeneralInfor/www.nationalgrid.com/uk/Interconnectors/France/GeneralInfor/
3
Progress Since 4 July SG we have: 31/7- contract awarded for CMS supplier 7/8- tender launched for Hosting / Managed service 3/10- conducted User & Regulator consultation on commercial aspects 14/10- consultation results shared with Regulators 30/10- provided IFA Users with a summary of certain Access Rules principles 30/11- software design stage completed
4
CMS Project scope CMS will handle all IFA commercial aspects, including auctions, credit management, nominations across all timescales LT, D-1, Intraday. In addition, CMS project requires National Grid / RTE to modify various internal processes, eg: –IS interfaces: Control Room IS interfaces Market operator interfaces (eg Elexon, RTE) Back office systems ETSO Vista –Documentation: IFA Access Rules Operational procedures SLAs –Processes Control room functions Back office process (credit management / invoicing).
5
Next Steps in 2009 Jan- award contract for Hosting & Managed service Jan-Feb- consult IFA Users on draft Access Rules Feb- Factory Acceptance Tests (FAT) Apr-May- Site / User Acceptance Tests (SAT / UAT) May- publish IFA Access Rules June- Availability Testing & User Training July- Go Live