1 1 Slide © 2005 Thomson/South-Western Chapter 10 Project Scheduling: PERT/CPM n Project Scheduling with Known Activity Times n Project Scheduling with Uncertain Activity Times n Considering Time-Cost Trade-Offs
2
2 2 Slide © 2005 Thomson/South-Western PERT/CPM n PERT Program Evaluation and Review Technique Program Evaluation and Review Technique Developed by U.S. Navy for Polaris missile project Developed by U.S. Navy for Polaris missile project Developed to handle uncertain activity times Developed to handle uncertain activity times n CPM Critical Path Method Critical Path Method Developed by Du Pont & Remington Rand Developed by Du Pont & Remington Rand Developed for industrial projects for which activity times generally were known Developed for industrial projects for which activity times generally were known n Today’s project management software packages have combined the best features of both approaches.
3
3 3 Slide © 2005 Thomson/South-Western PERT/CPM n PERT and CPM have been used to plan, schedule, and control a wide variety of projects: R&D of new products and processes R&D of new products and processes Construction of buildings and highways Construction of buildings and highways Maintenance of large and complex equipment Maintenance of large and complex equipment Design and installation of new systems Design and installation of new systems
4
4 4 Slide © 2005 Thomson/South-Western PERT/CPM n PERT/CPM is used to plan the scheduling of individual activities that make up a project. n Projects may have as many as several thousand activities. n A complicating factor in carrying out the activities is that some activities depend on the completion of other activities before they can be started.
5
5 5 Slide © 2005 Thomson/South-Western PERT/CPM n Project managers rely on PERT/CPM to help them answer questions such as: What is the total time to complete the project? What is the total time to complete the project? What are the scheduled start and finish dates for each specific activity? What are the scheduled start and finish dates for each specific activity? Which activities are critical and must be completed exactly as scheduled to keep the project on schedule? Which activities are critical and must be completed exactly as scheduled to keep the project on schedule? How long can noncritical activities be delayed before they cause an increase in the project completion time? How long can noncritical activities be delayed before they cause an increase in the project completion time?
6
6 6 Slide © 2005 Thomson/South-Western Project Network n A project network can be constructed to model the precedence of the activities. n The nodes of the network represent the activities. n The arcs of the network reflect the precedence relationships of the activities. n A critical path for the network is a path consisting of activities with zero slack.
7
7 7 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Frank’s Fine Floats is in the business of building elaborate parade floats. Frank and his crew have a new float to build and want to use PERT/CPM to help them manage the project. The table on the next slide shows the activities that comprise the project. Each activity’s estimated completion time (in days) and immediate predecessors are listed as well. Frank wants to know the total time to complete the project, which activities are critical, and the earliest and latest start and finish dates for each activity.
8
8 8 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats Immediate Completion Immediate Completion Activity Description Predecessors Time (days) Activity Description Predecessors Time (days) A Initial Paperwork --- 3 A Initial Paperwork --- 3 B Build Body A 3 B Build Body A 3 C Build Frame A 2 C Build Frame A 2 D Finish Body B 3 D Finish Body B 3 E Finish Frame C 7 E Finish Frame C 7 F Final Paperwork B,C 3 F Final Paperwork B,C 3 G Mount Body to Frame D,E 6 G Mount Body to Frame D,E 6 H Install Skirt on Frame C 2 H Install Skirt on Frame C 2
9
9 9 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats n Project Network Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E 7
10
10 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats n Earliest Start and Finish Times Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E 7 0 3 3 6 6 9 3 5 12 18 6 9 5 7 5 12
11
11 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats n Latest Start and Finish Times Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E 7 0 3 3 6 6 9 3 5 12 18 6 9 5 7 5 12 6 9 9 12 0 3 3 5 12 18 15 18 16 18 5 12
12
12 Slide © 2005 Thomson/South-Western Determining the Critical Path n Step 3: Calculate the slack time for each activity by: Slack = (Latest Start) - (Earliest Start), or Slack = (Latest Start) - (Earliest Start), or = (Latest Finish) - (Earliest Finish). = (Latest Finish) - (Earliest Finish).
13
13 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats n Activity Slack Time Activity ES EF LS LF Slack Activity ES EF LS LF Slack A 0 3 0 3 0 (critical) A 0 3 0 3 0 (critical) B 3 6 6 9 3 B 3 6 6 9 3 C 3 5 3 5 0 (critical) C 3 5 3 5 0 (critical) D 6 9 9 12 3 D 6 9 9 12 3 E 5 12 5 12 0 (critical) E 5 12 5 12 0 (critical) F 6 9 15 18 9 F 6 9 15 18 9 G 12 18 12 18 0 (critical) G 12 18 12 18 0 (critical) H 5 7 16 18 11 H 5 7 16 18 11
14
14 Slide © 2005 Thomson/South-Western n Determining the Critical Path A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. Critical Path: A – C – E – G Critical Path: A – C – E – G The project completion time equals the maximum of the activities’ earliest finish times. The project completion time equals the maximum of the activities’ earliest finish times. Project Completion Time: 18 days Project Completion Time: 18 days Example: Frank’s Fine Floats
15
15 Slide © 2005 Thomson/South-Western Example: Frank’s Fine Floats n Critical Path Start Finish B 3 D 3 A 3 C 2 G 6 F 3 H 2 E 7 0 3 3 6 6 9 3 5 12 18 6 9 5 7 5 12 6 9 9 12 0 3 3 5 12 18 15 18 16 18 5 12
16
16 Slide © 2005 Thomson/South-Western n In the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. n An activity’s mean completion time is: t = ( a + 4 m + b )/6 t = ( a + 4 m + b )/6 a = the optimistic completion time estimate a = the optimistic completion time estimate b = the pessimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate m = the most likely completion time estimate Uncertain Activity Times Variance: The measure of uncertainty. Its value largely affected by the difference between b and a (large differences reflect a high degree of uncertainty in actv. time
17
17 Slide © 2005 Thomson/South-Western n An activity’s completion time variance is: 2 = (( b - a )/6) 2 2 = (( b - a )/6) 2 a = the optimistic completion time estimate a = the optimistic completion time estimate b = the pessimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate m = the most likely completion time estimate Uncertain Activity Times
18
18 Slide © 2005 Thomson/South-Western Uncertain Activity Times n In the three-time estimate approach, the critical path is determined as if the mean times for the activities were fixed times. n The overall project completion time is assumed to have a normal distribution with mean equal to the sum of the means along the critical path and variance equal to the sum of the variances along the critical path.
19
19 Slide © 2005 Thomson/South-Western Example: ABC Associates n Consider the following project: Immed. Optimistic Most Likely Pessimistic Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 A -- 4 6 8 B -- 1 4.5 5 B -- 1 4.5 5 C A 3 3 3 C A 3 3 3 D A 4 5 6 D A 4 5 6 E A 0.5 1 1.5 E A 0.5 1 1.5 F B,C 3 4 5 F B,C 3 4 5 G B,C 1 1.5 5 G B,C 1 1.5 5 H E,F 5 6 7 H E,F 5 6 7 I E,F 2 5 8 I E,F 2 5 8 J D,H 2.5 2.75 4.5 J D,H 2.5 2.75 4.5 K G,I 3 5 7 K G,I 3 5 7
20
20 Slide © 2005 Thomson/South-Western Example: ABC Associates n Project Network 66 44 33 55 55 22 44 11 66 33 55
21
21 Slide © 2005 Thomson/South-Western Example: ABC Associates n Activity Expected Times and Variances t = ( a + 4 m + b )/6 2 = (( b - a )/6) 2 t = ( a + 4 m + b )/6 2 = (( b - a )/6) 2 Activity Expected Time Variance A 6 4/9 A 6 4/9 B 4 4/9 B 4 4/9 C 3 0 C 3 0 D 5 1/9 D 5 1/9 E 1 1/36 E 1 1/36 F 4 1/9 F 4 1/9 G 2 4/9 G 2 4/9 H 6 1/9 H 6 1/9 I 5 1 I 5 1 J 3 1/9 J 3 1/9 K 5 4/9 K 5 4/9
22
22 Slide © 2005 Thomson/South-Western Example: ABC Associates n Earliest/Latest Times and Slack Activity ES EF LS LF Slack A 0 6 0 6 0 * A 0 6 0 6 0 * B 0 4 5 9 5 B 0 4 5 9 5 C 6 9 6 9 0 * C 6 9 6 9 0 * D 6 11 15 20 9 D 6 11 15 20 9 E 6 7 12 13 6 E 6 7 12 13 6 F 9 13 9 13 0 * F 9 13 9 13 0 * G 9 11 16 18 7 G 9 11 16 18 7 H 13 19 14 20 1 H 13 19 14 20 1 I 13 18 13 18 0 * I 13 18 13 18 0 * J 19 22 20 23 1 J 19 22 20 23 1 K 18 23 18 23 0 * K 18 23 18 23 0 *
23
23 Slide © 2005 Thomson/South-Western n Determining the Critical Path A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times. Critical Path: A – C – F – I – K Critical Path: A – C – F – I – K The project completion time equals the maximum of the activities’ earliest finish times. The project completion time equals the maximum of the activities’ earliest finish times. Project Completion Time: 23 hours Project Completion Time: 23 hours Example: ABC Associates
24
24 Slide © 2005 Thomson/South-Western Example: ABC Associates n Critical Path (A-C-F-I-K) 66 44 33 55 55 22 44 11 66 33 55 0 6 9 13 13 18 9 11 9 11 16 18 13 19 14 20 19 22 20 23 18 23 6 7 6 7 12 13 6 9 0 4 5 9 6 11 6 11 15 20
25
25 Slide © 2005 Thomson/South-Western n Probability the project will be completed within 24 hrs 2 = 2 A + 2 C + 2 F + 2 H + 2 K = 4/9 + 0 + 1/9 + 1 + 4/9 = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 = 2 = 1.414 = 1.414 z = (24 - 23)/ (24-23)/1.414 =.71 z = (24 - 23)/ (24-23)/1.414 =.71 From the Standard Normal Distribution table: From the Standard Normal Distribution table: P(z <.71) =.5 +.2612 =.7612 P(z <.71) =.5 +.2612 =.7612 Example: ABC Associates Probability completed within 24 hrs = 76.12%
26
26 Slide © 2005 Thomson/South-Western 0 Z z.00.01.02.03.04.05.06.07.08.09.0.5000.5040.5080.5120.5160.5199.5239.5279.5319.5359.1.5398.5438.5478.5517.5557.5596.5636.5675.5714.5753.2.5793.5832.5871.5910.5948.5987.6026.6064.6103.6141.3.6179.6217.6255.6293.6331.6368.6406.6443.6480.6517.4.6554.6591.6628.6664.6700.6736.6772.6808.6844.6879.5.6915.6950.6985.7019.7054.7088.7123.7157.7190.7224.6.7257.7291.7324.7357.7389.7422.7454.7486.7517.7549.7.7580.7611.7642.7673.7703.7734.7764.7794.7823.7852.8.7881.7910.7939.7967.7995.8023.8051.8078.8106.8133.9.8159.8186.8212.8238.8264.8289.8315.8340.8365.8389 1.0.8413.8438.8461.8485.8508.8531.8554.8577.8599.8621 1.1.8643.8665.8686.8708.8729.8749.8770.8790.8810.8830 1.2.8849.8869.8888.8907.8925.8944.8962.8980.8997.9015 1.3.9032.9049.9066.9082.9099.9115.9131.9147.9162.9177 1.4.9192.9207.9222.9236.9251.9265.9279.9292.9306.9319 1.5.9332.9345.9357.9370.9382.9394.9406.9418.9429.9441 Areas of the cumulative standard normal distribution
27
27 Slide © 2005 Thomson/South-Western 0 Z Areas of the cumulative standard normal distribution (Continue) z.00.01.02.03.04.05.06.07.08.09 1.6.9452.9463.9474.9484.9495.9505.9515.9525.9535.9545 1.7.9554.9564.9573.9582.9591.9599.9608.9616.9625.9633 1.8.9641.9649.9656.9664.9671.9678.9686.9693.9699.9706 1.9.9713.9719.9726.9732.9738.9744.9750.9756.9761.9767 2.0.9772.9778.9783.9788.9793.9798.9803.9808.9812.9817 2.1.9821.9826.9830.9834.9838.9842.9846.9850.9854.9857 2.2.9861.9864.9868.9871.9875.9878.9881.9884.9887.9890 2.3.9893.9896.9898.9901.9904.9906.9909.9911.9913.9916 2.4.9918.9920.9922.9925.9927.9929.9931.9932.9934.9936 2.5.9938.9940.9941.9943.9945.9946.9948.9949.9951.9952 2.6.9953.9955.9956.9957.9959.9960.9961.9962.9963.9964 2.7.9965.9966.9967.9968.9969.9970.9971.9972.9973.9974 2.8.9974.9975.9976.9977.9977.9978.9979.9979.9980.9981 2.9.9981.9982.9982.9983.9984.9984.9985.9985.9986.9986 3.0.9987.9987.9987.9988.9988.9989.9989.9989.9990.9990 3.1.9990.9991.9991.9991.9991.9992.9992.9992.9993.9993 3.2.9993.9993.9994.9994.9994.9994.9994.9995.9995.9995 3.3.9995.9995.9995.9996.9996.9996.9996.9996.9996.9997 3.4.9997.9997.9997.9997.9997.9997.9997.9997.9997.9998
28
28 Slide © 2005 Thomson/South-Western EarthMover is a manufacturer of road construction equipment including pavers, rollers, and graders. The company is faced with a new project, introducing a new line of loaders. Management is concerned that the project might take longer than 26 weeks to complete without crashing some activities. Example: EarthMover, Inc.
29
29 Slide © 2005 Thomson/South-Western Immediate Completion Immediate Completion Activity Description Predecessors Time (wks) Activity Description Predecessors Time (wks) A Study Feasibility --- 6 A Study Feasibility --- 6 B Purchase Building A 4 B Purchase Building A 4 C Hire Project Leader A 3 C Hire Project Leader A 3 D Select Advertising Staff B 6 D Select Advertising Staff B 6 E Purchase Materials B 3 E Purchase Materials B 3 F Hire Manufacturing Staff B,C 10 F Hire Manufacturing Staff B,C 10 G Manufacture Prototype E,F 2 G Manufacture Prototype E,F 2 H Produce First 50 Units G 6 H Produce First 50 Units G 6 I Advertise Product D,G 8 I Advertise Product D,G 8 Example: EarthMover, Inc.
30
30 Slide © 2005 Thomson/South-Western n PERT Network Example: EarthMover, Inc. 66 44 33 1010 33 66 2266 88
31
31 Slide © 2005 Thomson/South-Western n Earliest/Latest Times Activity ES EF LS LF Slack Activity ES EF LS LF Slack A 0 6 0 6 0 * A 0 6 0 6 0 * B 6 10 6 10 0 * B 6 10 6 10 0 * C 6 9 7 10 1 C 6 9 7 10 1 D 10 16 16 22 6 D 10 16 16 22 6 E 10 13 17 20 7 E 10 13 17 20 7 F 10 20 10 20 0 * F 10 20 10 20 0 * G 20 22 20 22 0 * G 20 22 20 22 0 * H 22 28 24 30 2 H 22 28 24 30 2 I 22 30 22 30 0 * I 22 30 22 30 0 * Example: EarthMover, Inc.
32
32 Slide © 2005 Thomson/South-Western Example: EarthMover, Inc. n Critical Activities 66 44 33 1010 33 66 2266 88 0 6 10 20 10 20 20 22 10 16 16 22 22 30 22 28 24 30 6 9 6 9 7 10 7 10 10 13 17 20 6 10 6 10
33
33 Slide © 2005 Thomson/South-Western Example: EarthMover, Inc. n Crashing The completion time for this project using normal times is 30 weeks. Which activities should be crashed, and by how many weeks, in order for the project to be completed in 26 weeks?
34
34 Slide © 2005 Thomson/South-Western Crashing Activity Times n In the Critical Path Method (CPM) approach to project scheduling, it is assumed that the normal time to complete an activity, t j, which can be met at a normal cost, c j, can be crashed to a reduced time, t j ’, under maximum crashing for an increased cost, c j ’. n Using CPM, activity j 's maximum time reduction, M j, may be calculated by: M j = t j - t j '. It is assumed that its cost per unit reduction, K j, is linear and can be calculated by: K j = ( c j ' - c j )/ M j.
35
35 Slide © 2005 Thomson/South-Western Example: EarthMover, Inc. Normal Crash Normal Crash Activity Time Cost Time Cost Activity Time Cost Time Cost A) Study Feasibility 6 $ 80,000 5 $100,000 B) Purchase Building 4 100,000 4 100,000 C) Hire Project Leader 3 50,000 2 100,000 D) Select Advertising Staff 6 150,000 3 300,000 E) Purchase Materials 3 180,000 2 250,000 F) Hire Manufacturing Staff 10 300,000 7 480,000 G) Manufacture Prototype 2 100,000 2 100,000 H) Produce First 50 Units 6 450,000 5 800,000 I) Advertising Product 8 350,000 4 650,000 I) Advertising Product 8 350,000 4 650,000 n Normal Costs and Crash Costs
36
36 Slide © 2005 Thomson/South-Western Min 20 Y A + 50 Y C + 50 Y D + 70 Y E + 60 Y F + 350 Y H + 75 Y I s.t. Y A 0 + (6 - Y I ) X G > X F + (2 - Y G ) s.t. Y A 0 + (6 - Y I ) X G > X F + (2 - Y G ) Y C X A + (4 - Y B ) X H > X G + (6 - Y H ) Y C X A + (4 - Y B ) X H > X G + (6 - Y H ) Y D X A + (3 - Y C ) X I > X D + (8 - Y I ) Y D X A + (3 - Y C ) X I > X D + (8 - Y I ) Y E X B + (6 - Y D ) X I > X G + (8 - Y I ) Y E X B + (6 - Y D ) X I > X G + (8 - Y I ) Y F X B + (3 - Y E ) X H X B + (3 - Y E ) X H < 26 Y H X B + (10 - Y F ) X I X B + (10 - Y F ) X I < 26 Y I X C + (10 - Y F ) Y I X C + (10 - Y F ) X G > X E + (2 - Y G ) X i, Y j > 0 for all i X G > X E + (2 - Y G ) X i, Y j > 0 for all i Example: EarthMover, Inc. n Linear Program for Minimum-Cost Crashing Let: X i = earliest finish time for activity i Y i = the amount of time activity i is crashed
37
37 Slide © 2005 Thomson/South-Western End of Chapter 10