1
January 26, 2012 Las Vegas, Nevada
2
Facts: The Colorado River… is more than 1450 miles long drains 246,000 sq-miles (1/12 of the continental US) has an annual flow of about 16 M acre-feet had an annual salt load of approximately 9 million tons Facts: The Colorado River supplies… drinking water to more than 30 million people in the US irrigation water to nearly 4 million acres Facts: The Colorado River Basin Salinity Program… multiple federal agencies (Reclamation, NRCS and BLM) 7 states hundreds of local agencies, organizations and companies thousands of individual producers Facts: The Colorado River Basin Salinity Control Program… existed for more than 35 years approximately $555 M spent ($384 M in appropriations and $171 M in cost share) plus potentially maybe $50- $80M from Program participants Facts/Results: The Colorado River Basin Salinity Control Program… reduced the annual salt load by about 1.2M tons reduced the concentration at Imperial Dam by 90-100 mg/L reduced quantified damages by several hundred million $/yr $50/ton
3
Early 1970’s Salinity Control Program Genesis
4
Early 1970’s Salinity of the Colorado River was rising Significant concerns by Mexico States were concerned about the implications of the Clean Water Act Salinity Control Program Genesis
5
1973 – created the Colorado River Basin Salinity Control Forum (Forum) 1974 – passed the Colorado River Basin Salinity Control Act (Act) 1975 – adopted salinity standards for the Colorado River Salinity Control Program Genesis
6
Standard (1975) Established the numeric criteria. Initiated a Plan of Implementation. 879 mg/L 747 mg/L 723 mg/L
7
Funded at about $26 M per year $10.8 M – Reclamation $6.9 M – NRCS $0.8 M – BLM $7.9 M – cost share Had put in place measures which would remove approximately 775,000 tons per year 388,000 tons per year – Reclamation 324,000 tons per year – NRCS 63,000 tons per year – BLM Salinity Control Program 2001
8
Funded at about $40 M per year $ 8.1 M – Reclamation $19.7 M – NRCS $ 0.7 M – BLM $ 11.9 M – cost share Had put in place measures which would remove approximately 1,218,000 tons per year 546,000 tons per year – Reclamation 572,000 tons per year – NRCS 100,000 tons per year – BLM Salinity Control Program 2011
10
2011 Review Reviewed the numeric criteria and determined to not change it. Identified a Plan of Implementation.
11
2011 Review There are currently measures in place to control 1.2 million tons per year. This equates to about 90-100 mg/L lower TDS at Imperial Dam.
12
2011 Review Modeling by Reclamation shows that without additional salinity control the TDS at Imperial will increase on average by 100 mg/L by 2030. The Plan of Implementation is to control an additional 644,000 tons by 2030 which will reduce this projected increase by about 50 mg/L.
13
2011 Review Table 3 Plan of Implementation Funding SourceTons/Year RECLAMATION (Basinwide Program)258,000 USDA NRCS (EQIP)186,000 BLM10,000 BASIN STATES PROGRAM (Cost Share)190,000 Basinwide Program110,000 EQIP Related80,000 TOTAL644,000
14
Reclamation’s Basinwide Program 2010 Funding Opportunity Announcement More than $100 million dollars of proposals Selected 11 projects Will control about 39,000 tons of salt annually Cost of about $35 million dollars $20 million from appropriations $15 million from cost-share Will be implemented over the next three to five years Will open up opportunities for on-farm work
15
Reclamation’s Basinwide Program
16
NRCS – EQIP Salinity Control In 2011 had about $19 million in funding of which about $12 million was obligated in EQIP contracts as follows: State Number of Contracts Salinity Control (tons) Contract Amount ($) Colorado1054,100 tons$5.2M Utah1506,200 tons$6.6M Wyoming20600 tons$145,000
17
NRCS – EQIP Salinity Control ?
18
2012 Farm Bill Since 1996 on-farm salinity control efforts have been funded through NRCS’s Environmental Quality Improvement Program (EQIP) which was last authorized in the 2008 Farm Bill The Colorado River Salinity Control Program is a small piece of EQIP which is a very small piece of the Farm Bill Authority under the 2008 Farm Bill expires on September 30, 2012 2012 Farm Bill?
19
Summary
20
Have put measures in place that reduce the salt load by 1.2 M tons per year or a concentration of 90-100 mg/L However, salinity levels are projected to increase by 100 mg/L by 2030 without continuation of the program In order to offset that increase by 50 mg/L we need greater funding under Reclamation’s Basinwide Program and continuation of NRCS’s EQIP with current funding levels, and This is the Greatest water quality improvement effort in the history of the world!