PPM Work Plan and MS Project Schedule Synchronization Procedures Draft for Review & Discussion June 2014 Best viewed in Slide Show mode using Presenter View for Discussion Points in Notes section
2
Configuration & Set-up Need Admin Support to Load Microsoft Visual Studio and the MSP Plug-in Page 26/13/14 Draft The MSP Plug-in loaded from PPM at Open > Administration > Download Microsoft Project Plug-in Validation for PPM v9.1, IE 9.0, MSP 2010 and current AIG server PPM MSP plug-in
3
MSP Plug-in in Microsoft Application Page 36/13/14 Draft Synchronization controlled from MSP
4
PPM Project Type Settings Page 46/13/14 Draft Can Only Synchronize with a Project that has no Work Plan Tab may be blocked to PM Mode to Control is Shared Match on Full name Transfer % Complete & Actual Dates PPM Project Set-up
5
Send the MSP Schedule to PPM Page 56/13/14 Draft Send from MSP Schedule Identify Server (Once) Log in to PPM Submit the Schedule
6
Select the Project in PPM Page 66/13/14 Draft All Projects with no Work Plan
7
Map Unmatched Resources Page 76/13/14 Draft Non Project Participants or Spelling Select the MSP Resource & Map All PPM Project Participants Listed Select the appropriate PPM Match No Changes Necessary Select from All Resources that you manage in PPM through Search
8
Complete Initial Linkage and MSP Send Page 86/13/14 Draft Include Actuals (to PPM) pop-up - No. Offer to Remove Association pop-up - blank MSP Schedule now in PPM Work Plan
9
Time Entry In PPM Page 96/13/14 Draft Select Assigned Tasks Time Sheet Policy Compliance Save the Time Sheet Will be sent on Next Retrieval
10
Retrieve Actuals from PPM Page 106/13/14 Draft From Add-Ins tab Retrieve Actuals Log Into PPM Server Transfer Data Review - Continue Done – Impact Highlighted