Download presentation
Presentation is loading. Please wait.
Published byRalf Dickerson Modified over 8 years ago
1
- Timeslots for the EUSO-Balloon flight - The campaign organization DESIGN FLIGHT REVIEW, 04.06.2014, CNES TOULOUSE Guillaume Prévôt APC, Paris, France The EUSO-BALLOON campaign
2
2 EUSO-Balloon flight timeslots ( < 25% moon) RAV – 04.06.2014The EUSO-BALLOON campaign The baseline timeslot: August, 20 th to August, 29 th (priority to the long duration flights) Back-up end of September (priority to short flights)
3
3 EUSO-Balloon flight timeslots RAV – 04.06.2014The EUSO-BALLOON campaign The baseline timeslot: August, 20 th to August, 29 th (priority to the long duration flights) Back-up end of September (priority to short flights)
4
Campaign activities Plan 1/ Our proposition if EUSO Balloon is authorized to flight: 1.Preparation to shipment: packaging week 20 (the packaging list is ready and has been sent to Stéphane Louvel) 2.Travel to Timmins 1.Boat shipping for the gondola (from 12 June 2014) 2.Flight for PDM & DP (from 20 July 2014) 3. EUSO Balloon ready for Timmins campaign: 10 August 2014
5
Campaign activities Plan 2/ Activities Plan at Timmins: 1.Unpacking 2.Sub systems Good Health tests 3.Instrument Integration 4.Instrument Final tests 5.EUSO / Siren coupled tests 6.Final integration activities 7.EUSO Instrument available for Negative Chronology 8.Flight slot 9.Recup EUSO Instrument 10.Visual Control / Re packing Instrument 11.End
6
6 EUSO-Balloon schedule of the campaign The EUSO-BALLOON campaignRAV – 04.06.2014 Schedule of the campaign (with margins) Associated list of the arrival of each member of the team, tasks, etc.
7
Campaign Team Organization International Teams from several laboratories will participate in the campaign (~ 12 (min) 20 max persons in total – average of 12 persons max each day) to organize the activities and team campaign organization is proposed*: EUSO Balloon Project Manager: Jean EVRARD (CNES) Interface with Head of campaign EUSO Balloon PI: Peter VOM BALLMOONS (IRAP) Behalf the EUSO Balloon scientist authorize the flight EUSO Balloon Laboratories Project Manager: Guillaume PREVOT (APC) Coordinate the laboratories activities EUSO Balloon CNES Instrument Manager: Karine MERCIER (CNES) Coordinate Instrument activities (Planning management, actions) Daily meeting (in the morning) between this 4 persons to o Debriefing Campaign information o Day -1 activities synthesis o Day activities debriefing o Day+ 1 activities o Wrap up actions o Schedule * based on Project organization note EUSO-NO-0-5290-CN
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.