Download presentation
Published byCharles Dominick Miller Modified over 9 years ago
1
Dave McGinnis Chief Engineer – Accelerator Division
The ESS Linac Dave McGinnis Chief Engineer – Accelerator Division 15 October 2014
2
The ESS Linac The European Spallation Source (ESS) will house the most powerful proton linac ever built. Average beam power of 5 MW. Peak beam power of 125 MW Acceleration to 2 GeV Peak proton beam current of 62.5 mA Pulse length of 2.86 ms at a rate of 14 Hz (4% duty factor) 97% of the acceleration is provided by superconducting cavities. The linac will require over 150 individual high power RF sources with 80% of the RF power sources requiring over 1.1 MW of peak RF power We expect to spend over 200 M€ on the RF system alone
3
ESS Schedule Full funding and ground-break in Fall 2014
1.25 MW of proton beam power by 2019 5 MW of proton beam power by 2022
4
Neutron Spallation Sources
Traditional neutron sources are reactor based Neutron flux is limited by reactor cooling Neutron energy spectrum is measured by time of flight using neutron choppers Chopping throws away neutrons and limits neutron brightness Spallation sources consist of a: pulsed accelerator that shoots protons into: a metal target to produce the neutrons The pulsed nature of the accelerator makes the neutron brightness much higher for a spallation source for the same average neutron flux as a reactor The accelerator complex of atypical spallation sources consist of a: Linac to accelerator the protons A storage ring to compress the linac beam pulse Linac Target and Instruments Storage Ring
5
What is Different About ESS?
The average proton beam power will be 5 MW Average neutron flux is proportional to average beam power 5 MW is five times greater than SNS beam power The total proton energy per pulse will be 360 kJ Beam brightness (neutrons per pulse) is proportional to total proton energy per pulse 360 kJ is over 20 times greater than SNS total proton energy per pulse
6
Short Pulse Neutron Spallation Sources
The neutrons are cooled by a moderator downstream of the target The time constant of the moderation process is about 100 ms Proton beam pulses shorter than 100 us serve only to stress the metal target and limit the beam power Typical short pulse spallation sources have storage ring circumferences ~300 meters which produce 1 ms beam pulses To build a storage ring with a 100 ms pulse would require a ring 30 km in circumference The target stress from the short beam pulse places a limit on: proton beam power and ultimately neutron flux and brightness The proton beam power of SNS (Oak Ridge Tennessee, USA) is limited to 1MW (17 MW peak)
7
Long Pulse Concept 360 kJ packed into a short pulse of 1 ms (360 GW peak) would destroy a target ESS will not use a compressor ring The linac will send the beam directly to the target over a period of 3 ms at a rate of 14 Hz. Peak beam power on the target is less than 125 MW The tradeoff is that ESS will Have longer neutron guides between experiments and the target Require a neutron choppers for precision energy measurements
8
The Long Pulse Concept Advantage - No compressor ring required
No space charge tune shift so peak beam current can be supplied at almost any energy Relaxed constraints on beam emittance This is especially true if the beam expansion system for the target is based on raster scanning of the beam on the target. No H- and associated intra-beam stripping losses Permits the implementation of target raster scanning Disadvantage - Experiment requirements “imprint” Linac pulse structure Duty factor is large for a copper linac Duty factor is small for a superconducting linac
9
ESS Linac Evolution
10
Cost Targets Although the 2008 design with 150 mA of beam current has higher technical risk, it has an inherently lower construction cost than the October 2012 baseline. Large fraction of the 2008 linac consists of normal conducting structures which are significantly less expensive to build than superconducting structures Lower energy (but higher beam current) requires a significantly shorter linac with less accelerating structures However the current cost targets are based on the 2008 design even though the October 2012 design: Has many more superconducting structures But provides less technical risk The only way to close the gap between the cost estimate and cost target is to modify the October 2012 baseline by adding technical risk or increasing the cost target
11
Cost Reduction Strategy
Keep constant 𝑃 𝑏 = 𝑃 𝑏𝑝𝑘 𝐷= 𝑃 𝑏𝑝𝑘 𝑓 𝑟 𝜏 𝑝 Reduce 𝑃 𝑏𝑝𝑘 = 𝐼 𝑏 𝐸 𝑝𝑘 𝑛=1 𝑁 𝑀 𝑐𝑒𝑙𝑙 𝐸 𝑎𝑐𝑐 𝑇 𝐸 𝑝𝑘 𝛽 𝑔 𝜆 2 cos 𝜙 𝑠 𝑛 + ℰ 𝐹𝐸 𝑞 The cost of the elliptical cryomodules and associated RF systems are the largest cost driver in the ESS Linac Reducing the number of superconducting cavities will have the largest impact on cost and design contingency each cavity that is removed from the design not only removes the cost of the cavity but also removes the need (and cost) for the RF power sources that feed the cavity. Therefore, the design contingency strategy will hold the average beam power constant while looking for avenues to minimize the number of superconducting cavities.
12
Cost Reduction Strategies
Keep constant 𝑃 = 𝑃 𝑝𝑘 𝐷= 𝑃 𝑝𝑘 𝑓 𝑟 𝜏 𝑝 Reduce 𝑃 𝑝𝑘 = 𝐼 𝑏 𝐸 𝑝𝑘 𝑛=1 𝑁 𝑀 𝑐𝑒𝑙𝑙 𝐸 𝑎𝑐𝑐 𝑇 𝐸 𝑝𝑘 𝛽 𝑔 𝜆 2 𝑛 + ℰ 𝐹𝐸 𝑞 Increase duty factor, D peak surface field, Epk peak beam current, Ib average value of EaccT sum by adjusting the power profile ratio of EaccT/Epk by appropriate choice of bg energy of the front end linac, EFE
13
Increasing The Duty Factor
The choice of a superconducting linac becomes obvious as the duty factor increases. From an accelerator design point of view, increasing the duty factor has the least impact on the configuration of the accelerator. As the duty factor is increased by either increasing the pulse length or the repetition rate, the final energy of the linac can be decreased and still provide the same average beam power. However, increasing the duty factor will reduce the peak neutron flux
14
New Baseline New Baseline Headline Parameters
5 MW Linac 2.0 GeV Energy (30 elliptical cryomodules) 62.5 mA beam current 4% duty factor (2.86 mS pulse length, 14 Hz) First beam by 2019 (1.0 MW at 570 MeV) The new baseline was achieved by: Increasing beam current by 25% Increasing Peak Surface Field by 12% Setting High Beta bg to 0.86 Adopting maximum voltage profile Adopting a uniform lattice cell length in the elliptical section to permit design flexibility schedule flexibility.
15
Lattice Cell Length For the October 2012 baseline design, the cell length along the linac changes substantially. 4.18 meters in the spokes, 7.12 meters in the medium beta section with one cryomodule per cell 15.19 meters in the high beta section with two cryomodules per cell. For a maximized voltage profile, a high beta bg=0.86, and an Ib=62mA, over half the medium beta cryomodules are eliminated the beginning of the high beta region is now 520 MeV At this energy, the current long high beta cells is too weak at to provide the desired phase advance per cell of 87 degrees with reasonable gradients in the quadrupoles. Thus a fourth type of cell with one high beta cryomodule per cell would be needed in this region.
16
Uniform Lattice Cell Length
A tunnel design with many different cell lengths is very undesirable with the perspective of considering: design contingency future upgrades. In the future, it might be advantageous to interchange spoke cryomodules with medium beta cryomodules. medium beta cryomodules with high beta cryomodules. At the added expense of a longer linac, the new baseline has: Spoke cell Length = 0.5 x Medium beta cell length Medium beta cell length = High beta cell length A uniform cell length provides the possibility that the medium and high beta cryomodules could be interchangeable and possibly identical. 6 cell medium beta cavities that would be close to the same length of the high beta cavities. This would reduce the prototyping schedule (and cost) significantly because only one type cryomodule prototype would need to be constructed. Also a 6 cell medium beta cryomodule requires one less high beta cryomodule to achieve 5 MW of beam power
17
6 Cell Medium Beta Cavities
For a uniform lattice cell length, the current 5 cell medium beta cavities need a drift of 0.2 meters after each cavity Might require a specialized port on the cryomodule to access the tuner package for both species of geometrical beta If 6 cell medium beta cavities (bg=0.67) are used, the extra drift is reduced to 0.06 meters One less high beta cryomodule required
18
New Baseline Layout Done by a professional: M. Eshraqi
19
New Baseline Lattice
20
Design Risk Reduced the number of elliptical cryomodules from 45 to 30
Each cryomodule + RF to power the cryomodule costs ~6.5 M€ Elimination of 15 cryomodules yields 78 M€ savings (6.5 M€ x 15 x 80% (power factor) ) By accepting large technical risk Power Couplers: Maximum coupler power is 1200 kW Went from 850 kW/coupler to 1100 kW/coupler Reduced our design margin by 70% Cavity Peak Surface Field Maximum surface field is 50 MV/meter Went from 40 MV/meter to 45 MV/meter Reduced our design margin by 50%
21
Design Contingency ESS uses the Long Pulse concept
No compressor ring is required Peak beam current can be supplied at almost any energy If we fail to meet our goals on: Beam current Cavity gradient Power coupler power The accelerator complex will still function but at a reduced beam power With the exception of reduced gradient on the spokes (energy acceptance in medium betas) We can buy back the beam power in the future by adding high beta cryomodules to the end of the linac As long as the additional space is reserved. We proposed to mitigate these risks by reserving the tunnel space for 15 cryomodules (127.5 meters) as “design contingency”.
22
Conventional Facility Costs
The approximate costs for conventional facilities are: Tunnel: 22,900 €/m (3270 k€ / m2) including berm, auxiliary costs Gallery: 46,200 €/m (2800 k€ / m2) The cost of accelerator equipment is: 6.5 M€ / cryomodule which includes the RF power Average cost of superconducting RF accelerator equipment is: 790,000 €/m 35x more expensive than tunnel cost 11.4x more expensive than total CF cost Average beam power cost for the accelerator equipment in a cryomodule cell is 18kW / M€. The cost of the 127 meter contingency space without stubs and gallery is 2.9 M€ Equivalent to the cost of accelerator equipment needed to supply MW of average beam power (1% of 5 MW)
23
Linac Design Choices User facilities demand high availability (>95%) ESS will limit the peak beam current below 65 mA Linac Energy > 2 GeV to accomplish 125 MW peak power. The linac will be mostly (>97%) superconducting Front end frequency is 352 MHz (CERN Standard) High energy section is at 704 MHz
24
Front End Section The RFQ and DTL will be similar to the CERN Linac 4 design. The RFQ will be 4.5 meters long and reach an energy of 3.6 MeV The DTL Will consist of five tanks Each tank ~7.5 meters in length Final energy will be 88 MeV Six klystrons at 352 MHz with a maximum saturated power of 2.8 MW and a duty factor of 4% are required for the Front End
25
Spoke Cavities ESS will transition to superconducting cavities at 88 MeV ESS will be the first accelerator to use 352 MHz double spoke cavity resonators Twenty-eight cavities with an accelerating gradient of 9 MV/m are required. Each cavity will operate at a nominal peak power of 320 kW What type of power source to choose? Tetrode Klystron IOT Solid State
26
Elliptical Cavities Universal Cryomodule Medium Beta bg = 0.67
Cryomodules are expensive and difficult to fabricate Pick cavity bg and number of cells Optimize power transfer Optimize length Power in couplers is limited to 1200 MW (peak) Medium Beta bg = 0.67 6 cell cavities Cavity length = 0.86 m 32 cavities packaged in 8 cryomodules Maximum peak RF power = 800kW High Beta bg = = 0. 86 5 cell cavities Cavity length = 0.92 m 88 cavities packaged in 22 cryomodules Maximum peak RF power = 1100kW
27
Lorentz De-tuning Because of the enormous gradients in superconducting cavities, the radiation pressure deforms the cavities We expect over 400 Hz of detuning in the ESS cavities. Unloaded cavity bandwidth = 0.07 Hz Loaded cavity bandwidth = 1 kHz The mechanical time constant of the cavities is about 1 ms compared to the pulse length of 3 ms Static pre-detuning as done in SNS will not be sufficient Dynamic de-tuning compensation using piezo-electric tuners is a must! Or else pay for the extra RF power required
28
Cavity Power Configuration
Because of fabrication techniques, superconducting cavity strings are usually much shorter (< 1 m) than copper cavity strings (> 5m). The Lorentz de-tuning coefficient varies from cavity to cavity Therefore, each superconducting cavity has its own RF power source
29
Transit Time Factor For proton linacs using copper RF cavities
the cavity cell structure is tuned to match the changing proton velocity as it accelerates. The power profile is usually flat Because of high fabrication costs and difficulty, The cell structure of superconducting cavities is tuned for only one beam velocity. Multiple families of cell velocities are chosen. ESS cell velocities: Spoke: bg = 0.5 Medium beta: bg = 0.67 High beta: bg = = 0. 86 There is a limit on the surface field in a SCRF cavity (ESS 45 MV/m) Since, the particle velocity does not match the geometrical velocity for the entire acceleration range, The power profile is not flat
30
ESS Linac Cavity Power Profile
High Beta Medium Beta Spoke Transitions
31
ESS Linac RF System
32
Spoke linac (352 MHz) RF System Layout
26 Double Spoke cavities Power range kW Combination of two tetrodes Other options: Solid State Amplifiers Large power supply (330 kVA) to supply 8 stations (16 tetrodes)
33
Elliptical (704 MHz) RF System Layout
One cavity per klystron 4 klystrons per modulator 16 klystrons per tunnel penetration Tunnel
34
Elliptical (704 MHz) RF System Layout
Klystrons Modulator Racks and Controls WR1150 Distribution 4.5 Cells of 8 klystrons for Medium Beta 10,5 Cells of 8 klystrons (IOTs) for High Beta
35
Summary
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.