Operations Management Operations Scheduling
Manufacturing Execution Systems Equipment Scheduling Work Centers Priority rules Johnson’s rule Backward / Forward scheduling Workforce Scheduling MBA.782.Operations.Scheduling
2
Work flow is driven by a schedule
Oper. Sched Manufacturing Execution Systems Work flow = Cash flow Work flow is driven by a schedule ____ % of time actually working; ____ % of time waiting in queues Schedule equipment and workforce MBA.782.Operations.Scheduling 3
3
Becomes exceedingly complex because....
Oper. Sched Equipment Scheduling Becomes exceedingly complex because.... Unpredictability of demand for all resources Variability of throughput times Tradeoffs among: Utilization of people and equipment vs. Work in Process vs. ability to meet promised delivery dates MBA.782.Operations.Scheduling 3
4
where a particular type of work is done.
Equip. Sched Work Centers A work center is an area in a business in which productive resources are organized and work is completed. where a particular type of work is done. Finite / infinite ____________ backward / forward _____________ machine and/or labor ___________ MBA.782.Operations.Scheduling 3
5
___________ for the resource of interest
Equip. Sched Definitions Queue time ___________ for the resource of interest Flow time = operation time + queue time time for a job to _______________ the process Lateness = ( Flow time - Due date ) + Completion time (aka, ______________ ) finish time of last job - start time of first job MBA.782.Operations.Scheduling 3
6
Meeting ____ ______ of customers or downstream operations.
Equip. Sched Schedule Performance Measures Meeting ____ ______ of customers or downstream operations. Minimizing the flow time the time a job _________ in the process Minimizing work-in-process inventory. Minimizing _____ ______ of machines or workers. Maximize machine utilization MBA.782.Operations.Scheduling 9
7
Allocating orders, equipment, and personnel.
Equip. Sched Scheduling Activities Allocating orders, equipment, and personnel. Determining the ____________ of order performance. Schedule jobs as a _________ with process stages back to back. Re-schedule every day. MBA.782.Operations.Scheduling 5
8
Used for n-Jobs on One Machine Local Priority Rules
Equip. Sched Priority Rules and Techniques Used for n-Jobs on One Machine Local Priority Rules schedule jobs according to their effect on the _____________________ workstation Global Priority Rules sequence jobs according to their effect on ____________ work requirements MBA.782.Operations.Scheduling 9
9
Suppose these four jobs arrive for processing on one machine:
Local Priority Rules First Come, First Serve (FCFS) Suppose these four jobs arrive for processing on one machine: MBA.782.Operations.Scheduling 9
10
The job with the shortest processing time is processed first
Local Priority Rules Shortest Operation Time (SOT) The job with the shortest processing time is processed first MBA.782.Operations.Scheduling 9
11
Schedule job with smallest slack first
Local Priority Rules Slack Time Remaining (STR) Schedule job with smallest slack first MBA.782.Operations.Scheduling 9
12
MBA.782.Operations.Scheduling
13
Sequence: ____ , ____ , ____ , ____
Global Priority Rules Critical Ratio (CR) Sequence: ____ , ____ , ____ , ____ MBA.782.Operations.Scheduling 9
14
Sequence: ____ , ____ , ____ , ____
Global Priority Rules. Dynamic Slack / Operation Remaining Sequence: ____ , ____ , ____ , ____ MBA.782.Operations.Scheduling 9
15
Job A Job B Job C Jobs (N = 3) Saw Drill
Oper. Sched. Johnson’s Rule Used to schedule n-jobs through 2 sequential machines Jobs (N = 3) Saw Drill Job A Job B Job C © 1995 Corel Corp. © 1995 Corel Corp. MBA.782.Operations.Scheduling
16
Once a job is scheduled, eliminate it.
Oper. Sched. Johnson’s Rule All jobs are to be listed, and the time required on each machine is shown. Select the job with the shortest activity time. If the shortest time lies with the first machine, the job is scheduled first; if with the second machine, the job is scheduled last. Once a job is scheduled, eliminate it. Apply steps 2-3 to the remaining jobs, working toward the center of the sequence. MBA.782.Operations.Scheduling
17
Jobs to be sent through a 2-machine sequence...
Oper. Sched. Johnson’s Rule Jobs to be sent through a 2-machine sequence... Job Saw Time Drill Time A 5 2 B 3 6 C 8 4 D E MBA.782.Operations.Scheduling
18
schedule the ____________ possible starting time
Oper. Sched. Forward and Backward Scheduling Forward Scheduling schedule the ____________ possible starting time due dates determined by internal scheduler Backward Scheduling determine the _____________ possible starting time for externally set due dates MBA.782.Operations.Scheduling 21
19
Oper. Sched. Forward and Backward Scheduling
MBA.782.Operations.Scheduling 21
20
Oper. Sched. Forward and Backward Scheduling
MBA.782.Operations.Scheduling 21
21
forecasted staffing levels
Oper. Sched. Workforce Scheduling in Services Need to know forecasted staffing levels specific skills needed during the time-frame work-hour constraints Consecutive days-off requirements methods exist to provide the _____ schedule Complex scheduling situations computer programs used to find ______________ schedules, given many constraints MBA.782.Operations.Scheduling 21
22
Oper. Sched. Scheduling Consecutive Days Off
Objective find the schedule that minimizes the number of five-day workers with two consecutive days off, subject to the demands of the daily staffing schedule Procedure given the total number of workers needed each day, create a schedule by adding one worker at a time MBA.782.Operations.Scheduling 21
23
Oper. Sched. Scheduling Consecutive Days Off
MBA.782.Operations.Scheduling 21
24
Concepts / Terminology Review Lecture notes Recommended Problems
Topic Title Chapter Wrap-Up Read Chapter 15 Concepts / Terminology Review Lecture notes Recommended Problems MBA.782.Operations.Scheduling
25
Principles of Work Center Scheduling
1. There is a direct equivalence between work flow and cash flow. 2. The effectiveness of any job shop should be measured by speed of flow through the shop. 3. Schedule jobs as a string, with process steps back-to-back. 4. A job once started should not be interrupted. MBA.782.Operations.Scheduling 18
26
Principles of Job Shop Scheduling (Continued)
5. Speed of flow is most efficiently achieved by focusing on bottleneck work centers and jobs. 6. Reschedule every day. 7. Obtain feedback each day on jobs that are not completed at each work center. 8. Match work center input information to what the worker can actually do. MBA.782.Operations.Scheduling 19
27
Principles of Job Shop Scheduling (Continued)
9. When seeking improvement in output, look for incompatibility between engineering design and process execution. 10. Certainty of standards, routings, and so forth is not possible in a job shop, but always work towards achieving it. MBA.782.Operations.Scheduling 20