Download presentation
Presentation is loading. Please wait.
Published byProsper Patrick Modified over 8 years ago
1
Calculating Project Schedule Risk Using Monte Carlo Simulation Curt Blair, PMP
2
Project Schedule Risk The Problem Projected completion dates are estimates, not “hard” facts Projected completion dates are estimates, not “hard” facts These estimates often only represent a median scenario – 50% probability These estimates often only represent a median scenario – 50% probability Parallel paths (concurrent development) decrease estimate quality Parallel paths (concurrent development) decrease estimate quality A single completion date estimate does not reflect component risk factors A single completion date estimate does not reflect component risk factors
3
Project Schedule Risk One Solution Monte Carlo simulation provides a more complete picture of the risk Monte Carlo simulation provides a more complete picture of the risk Uses Optimistic, Pessimistic and Most likely WBS task durations Uses Optimistic, Pessimistic and Most likely WBS task durations Provides a range of completion dates each with an associated probability Provides a range of completion dates each with an associated probability
4
Project Schedule Risk Advantages Gives stakeholders a better “feel” for the schedule risk Gives stakeholders a better “feel” for the schedule risk Reflects contribution of individual high risk tasks on near-critical paths Reflects contribution of individual high risk tasks on near-critical paths Allows the Project Manager to demonstrate relative schedule risk of alternate scenarios Allows the Project Manager to demonstrate relative schedule risk of alternate scenarios
5
Project Schedule Risk Tools Excel spreadsheet Excel spreadsheet Add-ins for Microsoft Project Add-ins for Microsoft Project – @Risk – Risk+ Example Example
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.