Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab
2
Silicon Meeting July 10, 2003 20cm Gang Production Status Tooling for 20cm Gang production u Prototype fixtures (2 sets) available for use now u First production batch (3 sets) received, QCed, Ni/Teflon coated s Being assembled by Lab B staff now u Final production batch (5 sets) in fabrication at MSU s Expect delivery this month, ready for use ~4-6 weeks later Storage Boxes u Gangs will be stored in L2-5 module burn-in boxes u We have 25 boxes assembled at Fermilab u Remaining 300 boxes being fabricated by Brown s Parts are fabricated and procured s Assembly process at Brown is being debugged now s Expect all boxes to be available by September Procedures and QA/QC u Assembly procedures written and tested u Additional technical staff needs to be trained (scheduled to start 9/9) s Training in operation of Zeiss 500’s as well as sensor handling and gluing u OGP program written to inspect gangs u Need to verify that database is ready for gang production entries
3
Silicon Meeting July 10, 2003 L1-L5 Module Tooling Overview 5 flavors of fixture, all very similar u L1 (160mm finished module length) u 20cm gang & 10-10A, 10-10S (200mm modules) u 20-20A, 20-20S (400mm modules) Alignment and Gluing Precision alignment of sensor to sensor <5 Alignment of hybrid to sensors to ~50 Module flipping u Backside HV connection from hybrid u Kapton HV insulation to isolate sensor from structure (L1) u Ground contact from hybrid for support structure (L1) Wirebonding u Axial and stereo can be bonded on same fixtures (3 types) Reasonably flat (~50 ) vacuum chucks 160, 200 & 400mm long All tooling used successfully with electrical prototype modules
4
Silicon Meeting July 10, 2003 L2-5 Module Fixture Status Four fixtures used in module production u Hybrid alignment fixture: aligns hybrid to handle for next tool u Assembly fixture: aligns sensors (or gangs) and hybrid u Bonding fixture: used for module transfer and wire bonding u Flip fixture: used for making back-side HV connection Prototype fixtures fabricated long ago u Initial prototypes worked very well u Small modifications implemented to ease module transfers s Second prototypes of these parts have been made and tested u Written procedures and CMM programs developed and tested Production fixtures u 10-10 axial fixtures are the 20cm gang fixtures u 10-10 stereo require swapping one part on 20cm gang fixtures u 20-20 axial and stereo are identical except one part u Production scheduled to start 2/4/04 s “Finalize design” dependent on final hybrid sign-off (11/03) s Probably possible to do production earlier –Mechanical aspects of hybrids should be stable earlier –Hybrid alignment tools are only ones awaiting approval of fabrication drawings
5
Silicon Meeting July 10, 2003 20-20 Axial Module Fixture
6
Silicon Meeting July 10, 2003 Status of L2-5 Electrical Modules We have produced a total of 7 electrical modules u 10-10 Axial #7, Amitron hybrid, Irradiated sensors (not for stave) u 10-10 Axial #103, OK for stave u 10-10 Stereo #1, OK for stave u 20-20 Axial #8, Amitron hybrid, Electrical test module (not for stave) u 20-20 Axial #108, 9 working chips, OK for first stave but not ideal u 20-20 Stereo #2, Chips 1,2 bad, needs debugging u 20-20 Stereo #12, Chips 6-10 re-bonded & poor hybrid alignment Additional modules to be produced for electrical staves u Two modules need replacement in order to build 1 st stave s Waiting for ~10 sensors to build new 20-20 modules u Need full compliment of electrical modules for 2 nd stave s Need an additional ~20 sensors for this
7
Silicon Meeting July 10, 2003 QA of L2-5 Electrical Modules Electrical QA/QC (Cecilia) u Burn-in s Hybrid burn-in is up and running –Need to write procedures and train personnel s Module burn-in is almost there –Need to confirm cooling system operation –Need to complete software for running HV –Need to write procedures and train personnel s Personnel should be integrated to augment Gustavo’s efforts now u Debugging is essentially non-existent still u Need to define grading scheme for hybrids and modules (done?) u Need to define interface from QA/QC to database (done?) Mechanical QA/QC (Jim) u Some OGP programs written u Need to certify programs for all module types u Need to write procedures, including file naming conventions etc. u Need to write scripts to prepare OGP output files for database
8
Silicon Meeting July 10, 2003 Fabrication of mechanical and electrical preproduction staves Mechanical stave prototype u Modules on stave core 12/18/02, used for cooling studies u C-channels attached in June, 2003 Mechanical stave pre-production u Scheduled for completion 6/13/03 u Assembled in June/July with extensive QC (done 7/3/03) u Written assembly procedures followed throughout Electrical grade pre-production staves u Assembly scheduled for 6/16-7/14 (schedule says 2 staves) s One core and set of C-channels are available –Additional cores will be available, using revised tooling, 8/1 –Additional C-channels will be available by 8/1 also u Module assembly and burn-in are delaying assembly now s Need minimum of 30 sensors to complete this task per schedule u Written procedures fleshed out with mechanical staves s Mechanical QC of modules on staves needs to be added to procedures u C-channel grounding out to Junction Cards needs to be finalized