INSPECTION AND RECORDS Abstract from LWR Manual
2
SHEDULE OF INSPECTION OF LWR / CWR By SE / SSE Every fortnight during the two coldest and two hottest months of the year at about minimum and maximum temperatures alternately by SSE and SE / JE Alternately once in two months during other months of the year
3
RECORDS Record of LWR/CWR, as per the proforma laid down, shall be maintained by SSE in a permanent register called the sectional LWR/CWR Register. The SSE shall be responsible for keeping this register up-to-date. Annexure – XIAnnexure – XII Annexure – XIII AAnnexure – XII B
4
Thanks
9
Para 5.6.2 – The gap between the reference mark and tongue rail tip/stock rail corner at various rail temperatures shall not differ by more than +/- 10 mm from the theoretical range as shown in Annexure- v Para 5.6.3 - Where fishplated or SWP track is joined one side of SEJ, The gap between the reference mark and tongue rail tip/stock rail corner at various rail temperatures shall not differ by more than +/- 10 mm from the theoretical range as shown in Annexure- v
10
Reference Marks Para 5.9 – Reference marks shall be fixed at each SEJ and at the centre of LWR/CWR, on the reference pillars erected for this purpose. Additional reference marks in fixed portion and breathing length may be provided to know the behavior of LWR/CWR
11
Para 8.2.4 – When creep in fixed portion of LWR/CWR exceed 20 mm, full investigation shall be carried out and remedial measures undertaken