Maciej Ostręga Michal Zimny IBL CO 2 cooling progress meeting 14.01.2014
2
Pressure supply pipes already connected to all valves Power supply for plants connected to power distribution box Electrical connection for communication between plants – will have been tested when plant B commissioning will be finished Plant A I/O commissioning Digital input Feedback from PV108 liquid line bypass valve (valve is still not connected) MV106 filling valve open status (cable not connected to valve – no feedback in PVSS) MV110 liquid line bypass valve ( valve has to be changed – existing valve has only one feedback status) MV054,MV056,MV058 service line valves close status ( end-switch was broken ! No feedback to PLC) Digital output Communication with DSS
3
IBL CO 2 cooling progress meeting 14.01.2014 Plant A I/O commissioning Analog input Pump head membrane pressure PT101, PT102, PT103 sensors still not connected Accumulator level transmitter LT142 J.box and vacuum system inputs will have been tested after installation Analog input real Bug in PTsat and TTsat table found by Maciek Alarms Manual valves end-switchs and position verification alarms J.box and vacuum system alarms will have been tested after installation Communication with DSS All alarm groups Pump LP101 alarms Alarms for some of the heaters has to be finished
4
IBL CO 2 cooling progress meeting 14.01.2014 General comments Circuit breaker (8Q3) in plant B control cabinet has to be changed Missing protection for high voltage on terminal in Accumulator Pneumatic valve PV108 save mode should be open Time delay for all alarms changed to 0.0 s Valve EV208 is Normally Open! Added function in PLC program for PHOENIX TC card (wire break detection) Compressor GP250 ramping time speed was increased (during stop) All necessarily modification are immediately updated in PLC program and SCADA application You can find more detailed report on DFS: \\cern.ch\dfs\Departments\PH\Groups\DT\PO\Cooling activities\PROJECTS\ATLAS_IBL\COMMISSIONING Current file version: IOCommissioning_IBL_A.v3.xlsx
5
IBL CO 2 cooling progress meeting 14.01.2014 We have 2 weeks of delay, because of communication problems which was related to bug in Schneider firmware !!!
6
IBL CO 2 cooling progress meeting 14.01.2014