Presentation is loading. Please wait.

Presentation is loading. Please wait.

Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.

Similar presentations


Presentation on theme: "Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay."— Presentation transcript:

1 Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay

2 Summary Introduction Design Status Conclusion 27/02/20132

3 3

4 Introduction Vertical cryostat “Claudet bath” principle Few cryogenic connections Installed in a pit Support structure in the pit 4 parts Vacuum vessel Helium vessel Thermal shield Insert Magnet hanging from lambda plate 27/02/20134

5 Integration on ground level Jumper to valve box Exhaust line DN 300 In a trench Release outside of SM18 Current leads 20 kA for main magnet 10 kA for insert Instrumentation Magnet Helium vessel Level gauge Heaters Temperature sensor 27/02/20135

6 Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 627/02/2013

7 Cooling from 300 K to 80 K 727/02/2013 Pre cooling valve box Courtesy M. Bajko

8 Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 827/02/2013

9 Cooling from 80 K to 4.2 K 927/02/2013 Courtesy M. Bajko

10 Magnet cooling 3 Phases 300 K – 80 K 8 hours Cold gaseous helium 80 K – 4.2 K 8 hours Liquid helium (1 bar) 4.2 K – 1.8 K 36 hours (1.5 days) Heat exchanger in cryostat 1027/02/2013

11 Cooling from 4.2 K to 1.8 K 1127/02/2013 Heat in-leak estimation at 1.9K Qnom=25W, Qdyn=40W, Qc-d=100W LHe/LHe heat exchanger, 1.9K Cooling power 100W, dT ≈30mK during cool down and dT≈10mK @ nominal condition Pumping Filling LHe/GHe heat exchanger 1.9K Cooling power up to 150W at 2K Courtesy M. Bajko

12 27/02/201312

13 Vacuum vessel Dimensions 4.6 m height 2.3 m diameter 4.8 tons Stainless steel (304L) Conical cover Limit deformations due to magnet weight 3 supports  Isostatic Static vacuum Protection using burst disk 27/02/201313

14 Helium vessel Max pressure : 5 bar Stainless steel (316 L, 316 LN) Welded to conical cover Neck thermalisation to limit heat in-leak Magnet support by lambda plate seat Heat exchanger for magnet cooling to 1.8 K 27/02/201314 1.9K 4.2K 300K

15 Helium vessel Jumper Regroup all cryogenic lines Connection to valve box Fixed point Cryogenic lines Block lines movement G10 plate + Collars 1527/02/2013

16 Helium vessel Neck thermalisation Copper profile Brazed to neck (stainless steel) Part of thermal shield cryogenic line 1627/02/2013 Neck Brazing Copper profile

17 Helium vessel Heat exchanger Copper tube brazed to stainless steel tube U shaped and welded to flange (30 x) Saturated helium (18 mbar – 1.8 K) in the tubes Cool-down pressurized helium (magnet) by conduction through copper Cooling power ≈ 100 W @ 1.9K (1.5 day Cool-Down) 1727/02/2013

18 Helium vessel Heat exchanger prototype 1827/02/2013

19 Thermal shield Actively cooled Supported from top cover Stainless steel structure Support shield Rigidity of the assembly Copper Sheet to form shield Pipe brazed on sheets for cooling 27/02/201319

20 Insert (concept) Top plate Current leads Instrumentation Radiative screens Lambda plate Quench valve (DN150) Splices Instrumentation Mechanical support Lambda plate to top plate Magnet (15 tons) to lambda plate 27/02/201320

21 27/02/201321

22 Vacuum vessel Design : Finished Construction : In progress First production meeting : 14 th February 2013 Delivery : June 2013 27/02/201322

23 Helium vessel Design : Almost finished Call for tender : March 2013 Order : Summer 2013 Delivery : 6-7 months after order (Early 2014) 27/02/201323

24 Thermal shield and Insert Thermal Shield Design in progress Construction in the shadow of helium vessel Order expected for summer 2013 Insert Design in progress Construction at CERN 27/02/201324

25 27/02/201325

26 Conclusion Design almost finished Construction in progress All components at CERN early 2014 Assembly phase to be planned Assembly of the cryostat Connection to other components 27/02/201326

27 Acknowledgment M. Bajko (TE-TF) V. Benda (TE-CRG) G. De Rijk (TE) C. Giloux (TE-TF) P. Minginette (EN-MME) V. Parma (TE-MSC) P. Perret (EN-MME) P. Viret (TE-TF) CERN TE-MSC-CMI Section 27/02/201327

28 27/02/201328

29


Download ppt "Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay."

Similar presentations


Ads by Google