Lake Pickett South Transportation Term Sheet Orange County BCC September 15, 2015
2
Presentation Outline Background Term Sheet Overview Requested Action
3
Background July 28, 2015 Public Hearing Lake Pickett North (2015-2-A-5-2) withdrew Board vote to transmit Lake Pickett South (2015-2-A-5-1) Transportation mitigation deal points unresolved BCC directed staff to bring back term sheet for direction at a future BCC meeting
4
2015-2-P-FLUE-1 General Location
5
Background Identify preliminary impact area 1% Development Program Lake Pickett South 1,856 SFR 400 Townhomes 230,000 Commercial 7,000 Office
6
Background Identify preliminary impact area 78% 4% 5% 8% 3% 7% 55% 1% Trip Distribution Lake Pickett South 78% 63% 60%
7
Background Identify preliminary impact area Future (2030) Conditions LOS With LPN/LPS
8
Term Sheet Overview Monetary contribution to area needed transportation infrastructure – Contribution substantially greater than transportation impact fees Roads first – Trip thresholds – Caps on building permits Concurrency satisfaction
9
Term Sheet Overview Traffic studies showed proportionate share of impacts ranging from $20-35M $28.0M mitigation obligation offered by LPS – $16.0M for SR 50 – $12.0M for Chuluota Road Other transportation needs to be addressed by County
10
SR 50 Avalon Park Blvd to Chuluota Road – FDOT to complete Design and Permitting by August 2016 – No ROW needed – CST funding not in adopted 5-year WP – FDOT to refund County when funding otherwise available Term Sheet Overview
11
Chuluota Road SR 50 to Lake Pickett Road – No studies conducted – Total project cost estimated to be $14.8M – LPS funding anticipated to be available in November 2020 – RCA, DEP, and ROW to be funded by County (3.5 years to complete)
12
Term Sheet Overview Trip thresholds limit development activity based on mitigation payments and road construction Additional cap on residential building permits – 180 year 1 after SR 50 is funded – 200 per year until Chuluota Road is funded ThresholdLPS Obligation Number of Trips Released % of Total Trips Released AFund $16.0M for SR 502508.5% BSR 50 50% complete2508.5% CSR 50 100% complete67123% DFund $12.0M for Chuluota Road 1,74660%
13
Term Sheet Overview Release of trips demonstrates satisfaction of the County’s concurrency requirements Concurrency approval to be demonstrated at plat approval (not plat submittal)
14
Requested Action Board direction regarding major roadway agreement conditions for incorporation into a Road Network Agreement with Lake Pickett South. District 5