Project Status Update Mark Petree 11-16-2010
2
LCLS Self Seeding Status: Management put it on hold. – Preliminary conceptual design completed – Interference with LCLS II cited.
3
Cable Stabilization New system ready for installation Dec. 1 st – Spare system ready – Documentation nearing completion
4
Beam Arrival Time Monitor Upgrade chassis are being constructed – All parts available – Power supplies configured – Documentation in progress
5
Bunch Length Measurement Working on VHDL code to download into a evaluation kit w/Spartan-6 FPGA – Plan to develop code to provide timing for Pyreos IR Line sensor array. – Plan to develop PCB to install in LCLS II
6
THz Laser Timing ROD scheduled to install timing cables to laser table from existing Phase Cavity system. – Cables are being constructed – Installation for Jan 19 th ROD
7
B685 Lab AC Wiring Upgrade Safety inspection revealed non-conforming AC wiring in the racks, and grounding issues. – Electrical safety inspection today – Electrical recommendations inspection scheduled – Lab interruptions expected