Presentation is loading. Please wait.

Presentation is loading. Please wait.

Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering.

Similar presentations


Presentation on theme: "Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering."— Presentation transcript:

1 Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering - Update -- Level 1 Trigger drawings/documentation The simple view Overall system diagrams: Front End crate configuration Network diagrams Fiber optic distribution -- Module specification documents FADC250 FADC125 F1TDC Crate Trigger Processor (CTP) Signal Distribution (SD) Trigger Interface (TI) SubSystem Processor (SSP) Global Trigger Processor (GTP) Trigger Supervisor (TS) Trigger Distributor (TD)

2 Front End Electronics & Level 1 Trigger Modules - (~400) FADC250 - (<40) Crate Trigger Processor - (~80) Trigger Interface - (~80) Signal Distribution Detector Signals Fiber Optic Clock/Trigger Distribution Crate Trigger Processor Fiber Optic Distribution (8) (2) (12) (# Boards) - (~140) F1TDC Clock (1) Cuevas Updated 28MARCH08 ** Standard VXS Crate Implement GTP on two Switch Slots

3 More updates,, 26 weeks until the end of FY08 Identified FY09 PED activities have started: FADC250 – Initial batch of 5 modules have been tested (We will have 9 units by end of April) 4 more prototype modules are out for assembly Front panels; heat sink fabrication Firmware has been completed! Fully tested on 3 of 5 modules. (Initial units) Test new modules after they are fully assembled in the ‘test stand’. Two new Wiener 20 Slot VXS crates – (Abhishek, Ben, Hai, Chris, Jeff) Received and measurements of slot to slot skew have been recorded. Need to complete power supply ripple testing etc. Trigger Interface – ( Ed, Ben, Jeff ) Schematic complete. Draft specification distributed. Final layout and check is in progress Board quotation received and parts have been ordered Signal Distribution module – Abhishek, et al Draft specification updated from meeting discussions. Need to distribute for comments Components selected and schematics have been started Details of programming this module are evolving

4 More updates,, F1TDC Version 2 – Create new specifications and functional requirement document (Fernando, Ed) This activity will start later in the year Crate Trigger Processor – Design and prototype circuit board for full crate (Hai, Jeff, Ben, Chris) Specification has been generated and distributed Xilinx Virtex 5 parts have been ordered. Other parts will need to be ordered soon. Schematics are complete and are being checked. Layout to begin after Trigger Interface is complete Simulation of FX20 to LX50T (Virtex 4 to Virtex 5) Gigabit Transceivers has been started Microcontroller development tools ordered and will begin design soon SubSystem Processor – (Ben) Initial specification was named ESP and the function descriptions of this module have not changed Document needs to be ‘formatted’ for review, and key functions presented at the May review. Global Trigger Processor – Dave Doughty, et al NEED Draft specification and functional description document Good information gathered at recent Trigger Workshop Trigger Supervisor – (Ed) NEED Draft specification and functional description document Trigger Distributor(s) – (Ed, Ben) Description discussed at Trigger Workshop Draft specification and functional description needed

5 More updates,, Detailed System Drawings – Updated regularly (Chris, Mark) Level of detail is progressing well Fiber optic hardware specified and budgetary estimates requested Start converting the logical drawings to detailed rack drawings Items that need more work and details: (Probably more ) 1.FADC250 Level 1 trigger processing functions Energy Sum function complete Hit Bit processing functions – needs documentation ( Tagger ) Track Count processing function - needs documentation (TOF, SC ) 2.Level 1 Trigger Timing Diagram The latency and propagation delays for transferring the L1 digital data from board to board, crate to crate, processing, and then distributing the Trigger for readout have been displayed before, but I think we need the specific details listed to convince ourselves before releasing documents to the reviewers. 3.Cost and schedule updates

6 System Engineering Hall D Drawing and Document Numbers DescriptionDrawing Number Trigger System – Top LevelD00000-16-08-0000 Level 1 Crate Trigger Processor – Fiber Distribution -16-08-0001 Trigger_Link and Clock Distribution – Fiber Optic -16-08-0002 Specifications & Functional Description FADC-250 Module -16-08-S000 Crate Trigger Processor -16-08-S001 Trigger Interface Module -16-08-S002 Signal Distribution Module -16-08-S003 Sub_System Processor Module -16-08-S004 Global Trigger Processor Module -16-08-S005 Trigger Supervisor Module -16-08-S006 Trigger Distributor Module -16-08-S007 VXS Crate Specification (JLAB Requirements) -16-08-S010

7 System Engineering Hall D Drawing and Document Numbers continued,, DescriptionDrawing Number Readout Controller Network – Top LevelD00000-16-09-0000 High Speed DAQ Subnet– Fiber Distribution -16-09-0001 Slow Controls Subnet -- Ethernet -16-09-0002 Terminal Server Connections -16-09-0003 Specifications & Functional Description Perfect place to store vendor specifications and manuals for network gear and other commercial equipment -16-09-SNNN

8 Questions? Discussion?

9

10 VXS Crate with: (16) FADC-250 (1)Sum Board (1) Clock/Trig/Sync Cpu not shown 36” Deep 19” Standard JLAB Rack Fan Tray/Crate control Examples of physical rack layout drawings ALL equipment must be shown to identify rack space issues (i.e. Network gear, patch panels, splitter panels, etc.) Airflow/Cooling issues will need to be identified and resolved

11 z 16 channel 250 Msps Flash ADCEnergy Sum Module VXS High Speed Serial Backplane Latest Designs


Download ppt "Hall D Online Meeting 28 March 2008 Fast Electronics R. Chris Cuevas Group Leader Jefferson Lab Experimental Nuclear Physics Division System Engineering."

Similar presentations


Ads by Google