2005/06 Procurement Analysis Dick Leitch 8 th November 2006
2
Agenda PO Volume growth 2005/06 numbers Invoice/PO Comparison Electronic procurement
3
0 5000 10000 15000 20000 2002/032003/042004/052005/06 Year No of POs 10302 12052 17733 19159 PO Volume Growth
4
POs by Supplier – Top 20
5
POs by Buyer – Top 20
6
Invoice/PO Comparison
7
PO Volume – 19,159 Invoice Volume – 76,091 PO Value – £7,075,243 Invoice Value – £79,097,563
8
Electronic Procurement Tender via OJEU 12 July 2005 Closing date 31 August 2005 22 downloaded documents 15 completed PQQ 6 invited to submit full ITT 4 invited for full evaluation
9
Schema
10
The result ………….
11
Potential Savings ProcHE savings measured at £44/PO Equals approx £775,000 on current PO volumes Buying by Category rather than by Supplier will reduce “maverick” buying Overall savings will be considerably higher
12
Thank you very much Any questions?