Greg Kelley, Assistant Deputy Director Los Angeles County Department of Public Works SOUTHERN CALIFORNIA SUSTAINABLE PAVEMENT PRESERVATION ROUND TABLE COUNTY OF LOS ANGELES FEBRUARY 10, 2015
2
Job Order Contract (JOC) is a flexible, cost- effective unit price contracting method used extensively by Los Angeles County Department Public Works to complete maintenance, repair, and refurbishment of County infrastructure and facilities. LA County DPW awarded its first JOC in 1996.
3
Competitively bid. Awarded to the lowest bidders. Based on fixed unit costs. Adjustment Factor for the unit costs. $4.3 million maximum contract amount. Contract is valid for one year. Accordance to State Public Contracting Code.
4
All items are fixed and pre-priced. The Adjustment Factor is competitively bid. Accelerate project delivery. Reduce administrative costs. Reduce PE and CE costs. Utilize local workers to perform at least 40% of total construction worker hours.
5
JOC documents consist of 2 components: 1.Unit Price Book (UPB) 2. Special Provisions
6
A catalog of fixed pre-priced construction activities. The cost for each activity is priced by multiplying the number of units by the unit price in the UPB. The amount of each Job Order is the sum of the cost of the activities multiplied by the Adjustment Factor.
8
A set of Special Provisions includes: General Provisions Technical Provisions (Roadway, Stripping, etc.)
10
Master Construction Activity List Unit Price Books & Master Specs JOC Book Advertise for JOC Book Award JOC Book to Contractor Work Orders PE Phase Construction Phase