Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Virgo Commissioning progress ILIAS, Nov 13 th 2006 Matteo Barsuglia on behalf of the Commissioning Team.

Similar presentations


Presentation on theme: "1 Virgo Commissioning progress ILIAS, Nov 13 th 2006 Matteo Barsuglia on behalf of the Commissioning Team."— Presentation transcript:

1 1 Virgo Commissioning progress ILIAS, Nov 13 th 2006 Matteo Barsuglia on behalf of the Commissioning Team

2 2 Outline  July-August  Main problem: thermal lensing  Main activities:  Lock acquisition improvements & automatic alignment  Noise hunting: recover good sensitivity after the shutdown  Thermal lensing  Data takings: WSR-1 (Sept 8 th -11 th )  Upgrades (September-October)  Faraday isolation optimization  Acoustic isolation laser laboratory  Matching improvements  Actuators noise reduction  Detection Brewster replacement  Frequency noise  see Matt’s talk  WSR-5 (last week-end)  Future steps

3 3 Thermal lensing 20 min Still the main concern (Lock acquisition long and more difficult / Noise couplings?)  Why?  Absorption in the input mirrors seems to be part of the problem (x4-x10 with respect to the design)  Also thermal lensing in the Faraday?  Dynamics of the fields inside the interferometer not understood  Simulation ongoing (Finesse, darkF, Matlab)  Diagnostics through optical spectrum analyzer  Phase camera in a few months  Thermal compensation in > 1 year

4 4 Thermal lensing: last week results/1

5 5 Thermal sensing: last week results/2 20 min 6.7 W input: old matching

6 6 Thermal sensing: last week results/2 20 min 100 sec 6.7 W input 6.7 W input: old matching Matching activity Stored power increase ~ 10%

7 7 Thermal sensing: last week results/2 20 min 100 sec 6.7 W input 5.4 W input 6.7 W input: old matching Matching activity Stored power increase ~ 10% Laser power reduction (19%)

8 8 Thermal sensing: last week results/2 20 min 100 sec 6.7 W input 5.4 W input 5 W input 6.7 W input: old matching Matching activity Stored power increase ~ 10% Laser power reduction (19%) Laser power reduction (25%) Stored power reduction ~ 10%

9 9 Automatic alignment  14 d.o.f. controlled  8 with high gain (~3 Hz), 6 with low gain (~10 mHz)  Power recycling automatic alignment critical during lock acquisition  8 wavefront signals, 6 DC signals (common end mirrors, NI, WI)  Future steps: better filtering, enlarge BW, find demodulated signal for common end

10 10 WSR-1 sensitivity C7 WSR-1

11 11 WSR-1 noise budget

12 12 Faraday isolation optimization  Faraday isolation ~ 100, expected 10,000  Small key Allen found attached to the rotator  isolation 10,000 in air  In vacuum isolation ~ 1000  Remote adjustment planned  Some signals improved – no clear improvements in the sensitivity Power recycling alignment

13 13 Brewster detection replacement Detection Brewster window  B1 sensitive to detection Brewster vibrations  Wrong Brewster – too small (80 mm instead 110 mm)  New window installed in October  New tests on going

14 14 Acoustic enclosure laser lab to the vacuum chamber

15 15 Acoustic enclosure laser lab  Actenuation 3-4 for both benches  Less than expected  try to find shortcuts  Problems with turbulent air flux  Temporary solved using apertures (final solution: silenced door)

16 16 Clapping tests detection lab  Actions planned for detection bench and end benches

17 17 Noise at high frequency  Oscillator phase noise OK  Shot noise  Almost at the measured value  Difference with design  Stored power 300 W (500W design)  T_OMC = 0.8 (1 design)  Calibration: ~ 40% uncertainty  Frequency noise  See Matt’s talk

18 18 Control noises

19 19 Power recycling noise  BW ~ 40 Hz, cut-off 200 Hz  Power recycling coupling changes by factor 10  Mechanism not understood Actions:  Understand the coupling mechanism  Switch to B2  Understand the noise of the error signal (B2_3f_ACp)

20 20 B2_3f error signal / switch to B2  B2_3f limited by read-out noise from ~ 50-100 Hz  ~50 mW when ITF locked ~70 mW during lock acquisition - max power  B2_3f signals strongly depressed by the use of the 3 rd harmonics demodulation  B2 gives a better SNR (1 st harmonic demodulation)  Switch already tried but never worked for long time periods

21 21 Actuators noise DAC DSP CoilDriver G EmphasisDeEmphasis

22 22 Detection bench noise/2 C7  Transfer function zBench  ITF output  Several structures already present in the ITF output excited

23 23 Detection bench noise C7 Actuators noise

24 24 WSR-5 sensitivity C7

25 25 Sensitivity to weather conditions Red curve: 2.7 Mpc -(wind+sea) Red curve = 2.7 Mpc-(wind+sea)

26 26 Suspension improvements LVDT ACC + NINE WE WI BS PR 3f I f I,Q CARM MICH PRCL f I DARM Use 4 locking signals for the position control of 4 mirrors in the beam direction GOALS: 1.reduce use of noisy sensors 2.do not use ACC where tilt dominates with no reinjection of seismic noise

27 27 Future steps  Noise hunting  B2 switch – power recycling control noise improvements  Detection bench actuators noise reduction  Diffused light mitigation  Detection bench  External injection bench  Mirror centering/coils balancing  Suspension control improvements  Global inverted pendulum suspension control  Vertical inertial damping  New SSFS (common mode servo) board  Acoustic isolation detection laboratory and end benches  Continue WSR program (data taking each ~3 weeks)  Long run (a few months) before end of S5


Download ppt "1 Virgo Commissioning progress ILIAS, Nov 13 th 2006 Matteo Barsuglia on behalf of the Commissioning Team."

Similar presentations


Ads by Google