1
© The Delos Partnership 2007 page 1 Supply Chain Techniques Getting the plan executed
2
© The Delos Partnership 2007 page 2 Factory – working the plan AND/ OR What do I make next ? Kanban Work To Lists
3
© The Delos Partnership 2007 page 3 Creation of Work to List 12345678 Projected Gross Requirements 10 20 Scheduled Receipts20 Projected Available Balance 30 Planned Order Release Opn No Work Centr e Operatio n SetRun 1045Inspect0.50.10 2055Mix1.00.5 3065Pack1.00.2 Routing Work Centre Information
4
© The Delos Partnership 2007 page 4 WTL and the routing Put Away Set-up & Run Q Move Set-up & Run Q Pick 1 day Dept 10 2 days Dept 30 Opn No DeptWork Centr e Operatio n SetRunSetRunTotal Hrs Total Days 10 45Inspect0.50.10.51010.52 203055Mix1.00.5150517 Product 43768 Lot Size : 100 Calc 2 day7 days Works Order Start Date Works Order Due Date Op Due Date Op Due Date
5
© The Delos Partnership 2007 page 5 Operation Due Dates Job NumberDescriptionWorks Order Due Date Operation Due Date 3458Turn21/511/5 3462Mill19/412/4 3756Turn22/311/3 3893Mill24/512/5 Department 10 – Which job next ?
6
© The Delos Partnership 2007 page 6 CRP and the routing Put Away Set-up & Run Q Move Set-up & Run Q Move Set-up & Run Q Pick 1 day 2 days1 day Dept 30 Dept 20Dept 10 1 day2 days Put Away Set-up & Run Q Move Set-up & Run Q Pick 1 day Dept 10 2 days Dept 30 Product 43768 Lot Size : 100 2 day7 days Product 24575 Lot Size : 200 3 days5 days
7
© The Delos Partnership 2007 page 7 Priorities are set by date Product 24575 – Job 407 Put Away Set-up & Run Q Move Set-up & Run Q Move Set-up & Run Q Pick Put Away Set-up & Run Q Move Set-up & Run Q Pick Product 43678 – Job 403 Order Due Date 27 March Order Start Date 8 March Order Due Date 29 March Order Start Date 2 March Dept 10 Operation Due Date = 13 March Operation Due Date = 14 March
8
© The Delos Partnership 2007 page 8 Operation Due Dates Job NumberDescriptionWorks Order Due Date Operation Due Date 3458Turn21/511/5 3462Mill19/412/4 3756Turn22/311/3 3893Mill24/512/5 Department 10 – Which job next ?Today’s date 15/3
9
© The Delos Partnership 2007 page 9 Work To List Order No.Part No.Descriptio n QuantityOp’n Number Op’n Start Date Op’n Due Date Order Due Date Set up Time Run TimeNext/Prev WC Status 40724575Barrel201010/312/324/510.07.520Q 40343678Cap401009/0313/327/50.02.030R 40947823Cap20 14/316/323/410.08.030S 41132672Top103014/318/321/48.010.060Q Order No.Part No.Descriptio n QuantityOp’n Number Op’n Start Date Op’n Due Date Order Due Date Set up Time Run TimeNext?prev WC Status 42025763Body30 10/313/323/43.05.040R 42534732Barrel20 11/314/322/45.010.020R 43032567Top254013/315/327/42.07.020Q 44047823Cap400514/317/304/045.07.020Q Work Centre Number 10 Description : Turning Date : 12/3 Jobs Currently at Work Centre Jobs Coming to this Work Centre
10
© The Delos Partnership 2007 page 10 Work to List Must show today’s date No past due orders Requires communication Requires Feedback from shop-floor to planner Shows which job to work on next Operation due date is the priority
11
© The Delos Partnership 2007 page 11 Kanban Means “visible signal” Replaces need for Work to List Replaced by Card Empty square Tennis Ball Empty package
12
© The Delos Partnership 2007 page 12 Kanban in Operation Operation 10Operation 20
13
© The Delos Partnership 2007 page 13 Kanban Visible instruction to make or move Highlights problems Requires line balance Requires Andon – traffic light operation Operator responsible for own quality Must not pass on known defects Small batch quantity required
14
© The Delos Partnership 2007 page 14 Kanban Works to keep the “Kanban” full When full must stop Do not build extra Result is less WIP Improved Quality Shorter Lead times
15
© The Delos Partnership 2007 page 15 Kanban vs WTL Visible feedback Signal driven not date driven Both require feedback Good Quality helps both Problem solving tools should support both WTL needs MRP and CRP; Kanban needs SOP and RCCP
16
© The Delos Partnership 2007 page 16 Creation of Vendor Schedule 12345678 Projected Gross Requirements 10 20 Scheduled Receipts20 Projected Available Balance 30 Planned Order Release Supplier Schedule Part Number : 14356 D escription : Red Pen Line Part Number DescriptionQtyScrap PerFactor 1043768Pen Barrel10.0 2076452Finished Nib10.0 3089563Cap10.0 Bills of Material Planning Data Lead Times Order Quantities Safety Stock
17
© The Delos Partnership 2007 page 17 Vendor Schedule Part No. 1/78/715/722/729/75/812/819/826/8SeptOct12 m Tota l 2346720 80 960 2456610 3060 1040 354673570 35 140 1680 1437620 40 1601801920 2543610 4080620 Supplier : ACME Grinding Equipment Limited OrdersPay for materialsVisibility Orders :PartQtyDue 14532623467201/7
18
© The Delos Partnership 2007 page 18 Vendor Scheduler Manages Exception messages Reviews and manages performance Operates MRP for their items Releases vendor schedule Point of contact for suppliers
19
© The Delos Partnership 2007 page 19 Discussion Areas Fast Tech Score Cards Forecasts Dell Value Chain
20
© The Delos Partnership 2007 page 20 Supplier Community Web Site View and Download Build Sequence
21
© The Delos Partnership 2007 page 21 Supplier Community Web Site View and Download Contract Orders
22
© The Delos Partnership 2007 page 22 Vendor Scheduling Vendor Scheduling Customer Supplier Buying and Scheduling Buying Short/ Medium Term Short/ Medium Term Long Term Long Term
23
© The Delos Partnership 2007 page 23 Execution - Prerequisites In order for Manufacturing and suppliers to achieve the schedule we need A Valid plan, balanced with respect to capacity and materials Correct planning data Effective Demand Management Proper Time Fence Policies Accurate planning data A commitment to the schedule Communication when things are wrong [ADR = Advise of Delay Report] All dates in the system in the future for unreleased planned orders, and due dates in the future for released orders A supporting framework of Integrated Enterprise Leadership