Charles I. Obichang Director, Bur. of Aviation Palau International Airport Min. of P. I. I. C.
2
ONGOING PROJECTS SECONDARY APRON MASTER PLAN: 1. PHASE II: - Obstruction Chart - Airport Layout Plan 2. WILDLIFE MANAGEMENT PLAN -Under final review by FAA and PIA 3. WATER RESCUE PLAN 4. FACILITY MAINTENANCE PLAN 5. SAFETY MANAGEMENT PLAN
3
Secondary Apron Project
4
Phase I.Complete Phase II Stage IA Total Progress of Phase II Stage IA77%
5
PRIMARY APRON AND HARDSTAND (S) OUTLYING STATE RUNWAYS PELELIU STATE ANGAUR STATE PENDING PROJECTS
6
Palau Airport Solar System 225 KW October 2011
12
Airlines 1.United 2.Delta 3.Korean Air 4.JAL 5.Asiana 6.China 7.Trans Asia 8.Palau Airways – Commence Operation on April 11, 2012. 9.Fly Guam