Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project
3
EXIT 5 AUGUSTA METRO AREA
4
EXIT 5 AUGUSTA NORTH AUGUSTA
5
Palmetto Parkway Park & Ride Site EXIT 5
6
October 2009
7
Issues Air quality Demand SCDOT to design and construct City to maintain Sustainable Design: stormwater, energy, landscaping Security Image Maintenance cost
8
Main JANUARY 2010
9
Chronology August 2009 Project conceived October 2009 User meeting held January 2010 Sketch design complete June 2010 ARTS funding approved January 2011 Design contract advertised April 2011 URS selected for design October 2011 URS design contract approved October 2012 Preliminary plans at 95%
10
December 2011
11
October 2012
12
Cost Estimates January 2010$ 800,000 June 2010$ 1,000,000 October 2012$ 1,473,305
13
North Augusta Park and Ride Project QUESTIONS