MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX 3/22/10 Update
3
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Project Status –Building #1 & Building #2 Out for Bids OSC Review and Approval for Advertisement –Project Labor Agreement [PLA] has been negotiated –Additional Testing of Underground Storage Tanks [UST] complete – remediation plan formulating –DEP Review of Remediation – in Progress –Police Relocation Complete
4
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Project Schedule –Advertise for Bid issued March 19, 2010 NJ OSC approval received. –Bids Due April 16, 2010 –Anticipated Notice To Proceed (NTP) – End of April or Early May 2010 –Anticipated Project Completion November 2011
5
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Schedule Issues –DEP Review of Remedial Work Expanded Work Area –Site Remediation Garage – Detention Pond UST removal adjacent to Building #1
6
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Budget –Total Budget $15 Million Pro-active Approach To Mitigate Budget Issues –Value Engineering – Workshop conducted (3/5/10) »Identified savings and ‘bid alternates’ with out sacrificing the project program –Inclusion of Alternates – Options for consideration Meetings on – going for ‘alternate’ funding sources –Seeking Energy Cost Rebates –Stimulus Funds Sought
7
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Budget Concerns –Unbudgeted/Under-budgeted Costs Contaminated Soil Remediation Storm Water Management Police Relocation Building Utility Separation Renovation Challenges
8
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX Next Steps: Await Bid Openning on April 16, 2010 Track Contaminated Soil Remediation Plan Cost and Schedule Impact to be evaluated Furniture Procurement State Contract – Meeting 3/24/10
9
MOORESTOWN TOWNSHIP MUNICIPAL COMPLEX QUESTIONS