19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready.

Similar presentations


Presentation on theme: "19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready."— Presentation transcript:

1 19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready to go cold –Preshower smooth operation –Thermal Screen ready to operate Water systems –Castor/Totem cooling plants under construction –Filter cleaning campaign on Al demineralized circuits –Upgrade of Muon/RPC primary heat exchanger under study CMS cooling: status and plans Detector cooling project, 19 May 2009

2 19 May 09P. Tropea2 Fluorocarbon systems: what’s been done SS1 Copper piping between cooling plant and Tracker (1-23 Apr) New air purge system installation (27 Apr) Pneumatic connections (27-29 Apr) Tank and plant pressure test (28 Apr) Leak test (29 Apr-15 May) Checkout of pneumatic connections (7-8 May, EN/CV) New sensor installation and cabling (4 May) Sensor connection and checkout (14 May, EN/CV) Filling of the tank (15-18 May, EN/CV)SS2 Copper piping between cooling plant and Tracker (25 Apr- 13 May) New air purge system installation (15 May) Pneumatic connections (19 May)Pixels New cabinet insulation (13-15 May) Pipe insulation (18 May)Monitoring All sensors installed, cables pulled to PLC

3 19 May 09P. Tropea3 Fluorocarbon systems: what comes next SS1 Commissioning (EN/CV) Balancing DCS testSS2 Pneumatic connections (May 19) Tank and plant pressure test (May 19) Leak test (May 25) Checkout of pneumatic connections (EN/CV+CMS) Sensor connection and checkout (EN/CV) Filling of the tank and plant (EN/CV) Commissioning (EN/CV) Balancing DCS test Both x SS1 & SS2 Both x SS1 & SS2 : insulation and cabinet doors (in 3 weeks)Monitoring New cabinet installation Sensor connections and checkout DCS implementation

4 19 May 09P. Tropea4 Possible improvements and open issues Lack of communication/tracking of activities: 18 Mar: filling of Pixels plant: nobody recorded batch numbers and real qty of fluid put into the plant May: missing labels/electrical schemes for CMS sensors, no communication on unplugged sensors: 1 day additional work before commissioning on SS1 for EN/CV 11 May: Pixels plant stop (announced), when re-starting very low T inside detector, no alarm, panic mode btw users… Pending issues Pending issues: Piloting of manifold valves from PLC/DCS Approval of PLC requirements on EDMS 991171991171 SCY file: details and planning for DCS implementation Monitoring: planning and DCS implementation Procedure for filling cooling loops Leak-trough valves on manifolds/filters