Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.

Similar presentations


Presentation on theme: "Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update."— Presentation transcript:

1 Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update -- New module design progress -- Updates to System drawings -- Testing activities

2 Project Status 15 weeks until the end of FY08 Identified FY09 PED activities are defined for the ‘Test Stand’: FADC250 – -- Nine modules fully assembled and all required modifications have been added -- 8 channel 12 bit version delivered to IU. -- Test crate and CPU that is on loan to G. Vissar at IUCF has been moved to IU -- LabView test routines have been completed to fully test each FADC250 -- The LabView test programs will provide a nice platform for troubleshooting and repair -- CODA driver has been completed and is in use for testing with the Trigger Interface -- Development to download firmware through VME has started (Hai) Trigger Interface – -- 4 modules fully assembled and functional -- Successful synchronization of trigger and latency adjustment for 150m and 50m fiber -- Plans underway to test multiple FADC250 modules in two VXS crates - Trigger rate performance testing for FADC250 - Does FADC250 pipeline trigger readout meet specifications? - Data throughput testing -- Test stand software – Ben has created very useful routines to configure and display readout data.

3 Signal Distribution module – -- Functional specifications completed for May Review -- Schematics are behind ‘schedule’ - New circuits to regulate power to the module - FPGA has been selected -- Must begin component placement and routing by July Crate Trigger Processor – -- Functional specification has been completed for May Review -- Schematics are complete -- Significant progress with placement of components and routing of circuit board -- CNU Student working with Hai on interface firmware for CTP to TI communication SubSystem Processor – Global Trigger Processor – Trigger Supervisor – -- Functional specification document completed for May Review -- Design activities scheduled for FY09 Project Status

4 CTP Circuit Board Place & Route 2 Gigabit ‘Lanes’ from each FADC250

5 More updates,, Detailed System Drawings – -- Started converting the logical drawings to detailed rack drawings - Include ALL equipment ‘chassis’ - Drawings for each platform have been started -- Work closely with Mechanical Engineering to identify best cable routing method for each sub-system (platform) Tagger Area: Instrumentation Racks Crates and other equipment chassis shown. Need to add details to show AC mains panel assignments & Network hardware.

6 Testing updates,, Many tests are planned for multiple FADC250 boards in a crate Must test token passing scheme, and measure any noise and jitter effects with up to 8 FADC in a crate. Two crate trigger latency tests have been performed, and we have the fiber optic patch panels that will be used in the final installation. The test stand is a very good platform to simulate the final configuration in the Hall and to measure total system effects on clock jitter and other critical timing parameters Data display and GUIs to configure the test station have been developed by Ben.