1
US Army Corps of Engineers BUILDING STRONG ® Model Certification Jodi Staebell Operational Director, Ecosystem Restoration Planning Center of Expertise Rock Island, IL August 7, 2009
2
BUILDING STRONG ® Model Certification Process to review, improve, validate analytical tools and models Toolbox - Ensure high quality methods and tools available to enable informed decisions Technical quality ► Theory ► Computational correctness System Quality Usability
3
BUILDING STRONG ® Information Quality Act (PL106-544) OMB Information Quality Bulletin for Peer Review Report of the Planning Models Improvement Task Force Engineer Circular 1105-2-407 Updated EC under development Protocols for Certification of Planning Models HQ Memo Policy Guidance on Certification of Ecosystem Output Models, Aug 08 Model Certification References
4
BUILDING STRONG ® Definition - any model or analytical tool used to ► Define problems and opportunities ► Formulate alternatives ► Evaluate effects ► Support decision-making Planning models, not engineering models Review is cost-shared In-house or contracted Model Certification Basics
5
BUILDING STRONG ® Stages of Model Development Requirements stage Development stage External Testing Implementation Model categories Corporate Regional/local Commercial off-the-shelf Models developed by others Model Basics
6
BUILDING STRONG ® Provided by model proponent Documentation includes ► Background ► Theory, assumptions, analytical requirements, formulas ► Software/hardware, testing/validation process, ► Availability of input data, usefulness to support project analysis, tech support, training Software/spreadsheets also provided Model Documentation
7
BUILDING STRONG ® Planner/Formulator Functional Field Expert(s) (internal and/or external) Software programmer/spreadsheet auditor Model Review Team
8
BUILDING STRONG ® Ecosystem Output Models Flowchart to Determine Level of Review IEPR required? Single use of multiple use model? Detailed model review is required. Yes Goal to recommend model for certification/ approval for use on future projects Goal to approve application of model on specific project Multiple Use Single Use Model Review $60-120k 7-10 months Single use or multiple use model? No Single Use ATR Team staffed and charged to conduct model review, supplement ATR team with outside experts, as appropriate Detailed model review is required. Multiple Use Model certified/ approved for use? No Yes ATR Team reviews model application Approved models include IWR Planning Suite and USFWS Published HSI ModelsUSFWS Published HSI Models
9
BUILDING STRONG ® Develop Model Certification Plan Assemble Review Team (In-house/Contract) Charge to Reviewers Kick-off Meeting Conduct Review Draft Model Review Report Meeting to discuss findings Final Model Review Report Revise model, as needed (lather, rinse, repeat!) PCX recommend that HQ certify model Model Certification Process
10
BUILDING STRONG ® District request PCX Model Review Model Review Process PCX assign Model Review Manager Model Review Plan approved by HQ Model Review Contract Executed Model Review Conducted Final Review Report submitted Model Review Plan Scope/Cost/Schedule/Method Scope of Work Independent Government Estimate Contractor Cost proposal Initial Findings Meeting held Draft Review Report submitted Draft Model Review Report Revised Model Documentation Final Model Review Report Model and model documentation revised as needed District MSC PCX Headquarters Review Group Recommend model for certification/approval for use? Model Documentation Published reports Table 2 information Model software or spreadsheet
11
BUILDING STRONG ® Model Review Process (continued) PCX recommend approval to HQ PCX posts approved model and documentation in PCX Toolbox HQ certify model/appro ve for use? Yes Model and model documentation revised as needed PCX memo describing model limitations submitted to MSC Recommend model for certification/approval for use? Yes No or District MSC PCX Headquarters Review Group
12
BUILDING STRONG ® Schedule Start SOW to Notice to Proceed – 8-12 weeks NTP to Final Model Review Report – 15-18 weeks Revise model – depends on PDT PCX recommendation to HQ – 4 weeks HQ review and certify - ? Timing Requirements and/or development stage Identify models at (prior to) Feasibility Scoping Meeting Initiate model review prior to Alternative Formulations Briefing Scheduling and Timing
13
BUILDING STRONG ® ATR – 3 reviewers extra time to review model In-house - $30-50k Contract - $80-140k PCX labor ~$10-15k Model proponent labor ► Prepare model documentation ► Assist in Model Cert contract ► Revise model and documentation Model Certification Cost
14
BUILDING STRONG ® 3 National models certified IWR Planning Suite Beach-FX HEC-FDA All published USFWS Habitat Suitability Index models approved for use Many reviews of single use models Model Certification Experience
15
BUILDING STRONG ® ECO-PCX Model Reviews Island Community Index Model, NAB 3 Everglades models Upper Miss Fish Passage Effectiveness Index Wetlands Value Assessment, MVN Habitat Evaluation and Assessment Tools (HEAT) ERDC Floodplain forest and wet coastal prairie community models, SWG Des Plaines Community HSI and HGM, LRC Arid Streams HGM, SPL 4 Ecological Models, MVM
16
BUILDING STRONG ® Available Models Ecosystem Restoration Gateway, Tools Tab http://cw-environment.usace.army.mil/tools.cfm?CoP=Restore http://cw-environment.usace.army.mil/tools.cfm?CoP=Restore
17
BUILDING STRONG ®
18
Identify models early Prepare model documentation Test/validate model Check software Identify expertise needed Be open to process Pool funds for multiple-use models How can the model proponent help?
19
BUILDING STRONG ® Questions?Questions?