1 Project Phases Review Questions

2 1. In which phase are the specifications produced?
a. Construction Design Phase- Schematic Design Phase- Construction Documents Planning Phase

3 1. In which phase are the specifications produced?
a. Construction Design Phase- Schematic Design Phase- Construction Documents Planning Phase

4 2. Whose responsibility is it to produce the shop drawings?
The Architect/Engineer The Contractor The Owner The Sub-Contractor

5 2. Whose responsibility is it to produce the shop drawings?
The Architect/Engineer The Contractor The Owner The Sub-Contractor

6 Design Phase- Schematic Design Phase- Construction Documents Phase
3. Which phase fixes and describes the size and character of the entire project? Design Phase- Schematic Design Phase- Construction Documents Phase Bidding/Contract Negotiation Phase Design Phase – Design Development Phase

7 Design Phase- Schematic Design Phase- Construction Documents Phase
3. Which phase fixes and describes the size and character of the entire project? Design Phase- Schematic Design Phase- Construction Documents Phase Bidding/Contract Negotiation Phase Design Phase – Design Development Phase

8 4. The Construction Phase begins…
When the first clod of earth is moved by a bulldozer When the surveyor measures the site When the bids are received When the agreement is executed

9 4. The Construction Phase begins…
When the first clod of earth is moved by a bulldozer When the surveyor measures the site When the bids are received When the agreement is executed

10 5. What activities take place in the planning/pre-design phase?
The engineers develop the mechanical and electrical systems The site is selected and the demolition is done Feasibility studies and budget is set The program is evaluated and the engineers are selected

11 5. What activities take place in the planning/pre-design phase?
The engineers develop the mechanical and electrical systems The site is selected and the demolition is done Feasibility studies and budget is set The program is evaluated and the engineers are selected

12 Bidding/Contract Negotiation Construction Post Construction
6. During which project phase does the A/E review the owner’s program and budget requirements and suggest alternative approaches? Planning/Pre-Design Design Bidding/Contract Negotiation Construction Post Construction

13 Bidding/Contract Negotiation Construction Post Construction
6. During which project phase does the A/E review the owner’s program and budget requirements and suggest alternative approaches? Planning/Pre-Design Design Bidding/Contract Negotiation Construction Post Construction

14 7. During the Planning/Pre-Design Phase, the A/E may be retained to:
Develop outline specifications Describe the character of the mechanical system Prepare renderings Assist in financial feasibility studies

15 7. During the Planning/Pre-Design Phase, the A/E may be retained to:
Develop outline specifications Describe the character of the mechanical system Prepare renderings Assist in financial feasibility studies

16 8. A project’s “life cycle” includes all of the following EXCEPT:
Planning Financing Construction Evaluation Demolition

17 8. A project’s “life cycle” includes all of the following EXCEPT:
Planning Financing Construction Evaluation Demolition

18 9. The Design Phase includes all of the following EXCEPT:
Surveys Design Development Schematic Design Bid Security

19 9. The Design Phase includes all of the following EXCEPT:
Construction Document Phase Design Development Phase Schematic Design Phase Bid Security

20 Outline Specification Rough Draft Specification UniFormat Elements
10. The specification type document prepared during the Design Development phase is called the: Outline Specification Rough Draft Specification UniFormat Elements

21 Outline Specification Rough Draft Specification UniFormat Elements
10. The specification type document prepared during the Design Development phase is called the: Outline Specification Rough Draft Specification UniFormat Elements

22 Answers C B D A