ESPLOST Update Savannah-Chatham County Public Schools September 5, 2007
2
ESPLOST Fifth payment received $4,938,238.85 (June Collections) Total of $28,907,832.44 Total Interest received of $229,959.57
3
ESPLOST
4
Project Management URS in association with Pat Mathis was selected on July 11. Contract reviewed and ready for Board Approval (Agenda Item September 5, 2007) URS will start immediately after contract approval.
5
ESPLOST ESPLOST Project Updates Woodville-Tompkins Phase I W/T Institute Opened September 4, 2007 W/T Phase II Architect Selection – Agenda Item September 5, 2007 Evaluating RFP responses for Cosmetology and Culinary Arts Labs
6
ESPLOST ESPLOST Project Updates Security/Surveillance Consultant RFP Godley Station Land Survey RFP Security Fencing School Design Committee Met on August 13 Committee beginning with central office staff to identify aspects of school design important to the areas of curriculum, operations, technology and safety. Committee will expand to include external participants once we establish the core design non- negotiables.
7
ESPLOST ESPLOST / Finance ESPLOST Financial Report distributed to board members Will be updated monthly Gave overview of ESPLOST to Audit Committee – August 30, 2007 Audit Requirement of ESPLOST Based on Calendar Year
8
ESPLOST Update Board Discussion / Questions