Download presentation
Presentation is loading. Please wait.
Published byAlyson Hart Modified over 8 years ago
1
Materials Requirements Planning
2
Collins Industries Largest manufacturer of ambulances in the world International competitor 12 major ambulance designs 18,000 different inventory items 6,000 manufactured parts 12,000 purchased parts MRP seems to be a good way to manage inventories: IBM’s MAPICS system is used
3
Independent and Dependent Demand Independent Demand A B(4) C(2) D(2)E(1) D(3) F(2) Dependent Demand Independent demand is uncertain. Dependent demand is certain.
4
Dependent demand : Demand for items that are subassemblies or component parts to be used in production of finished goods. Once the independent demand is known, the dependent demand can be determined. Dependent Demand
5
Demand Characteristics 12345 Week 400 – 300 – 200 – 100 – No. of tables Continuous demand M T W Th F M T W Th F 400 400 – 300 300 – 200 200 – 100 100 – No. of tables Discrete demand Independent demand 100 tables Dependent demand 100 x 1 = 100 tabletops 100 x 4 = 400 table legs
6
Dependent vs Independent Demand Time Demand Stable demand “Lumpy” demand Amount on hand Safety stock
7
Material Requirements Planning Defined ) Materials requirements planning (MRP) is a computerized inventory planning and control system for determining when (no earlier and no later) and how many of each of the parts, components, and materials should be ordered or produced Dependent demand drives MRP MRP is a software system
8
Material Requirements Planning System Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed Determines the dates when orders for those materials should be released, based on lead times
9
9 © The McGraw-Hill Companies, Inc., 2004 Firm orders from known customers Forecasts of demand from random customers Aggregate production plan Bill of material file Engineering design changes Inventory record file Inventory transactions Master production Schedule (MPS) Primary reports Secondary reports Planned order schedule for inventory and production control (work orders, purchase orders), rescheduling notices Exception reports Planning reports Reports for performance control Material planning (MRP computer program)
10
MRP Inputs 1: Master Production Schedule Drives MRP process with a schedule of finished products; states which end items are to be produced, when these are needed, and in what quantities Quantities may consist of a combination of customer orders & demand forecasts Quantities represent what needs to be produced, not what can be produced
11
Master Production Schedule (MPS) Time-phased plan specifying how many and when the firm plans to build each end item Aggregate Plan (Product Groups) Aggregate Plan (Product Groups) MPS (Specific End Items)
12
Master Production Schedule Item / Week Oct 3 Oct. 10 Oct. 17 Oct.24 Oct. 31 Clipboard8595120100100 Lapdesk0500500 Lapboard75120472017 Pencil Case125125125125125 Shows items to be produced Derived from aggregate plan Example:
13
MRP Inputs 2: Bill-of-Materials Bill of materials (BOM) : One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product. Product structure tree : Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
14
Bicycle(1) P/N 1000 Handle Bars (1) P/N 1001 Frame Assembly (1) P/N 1002 Wheels (2) P/N 1003 Frame (1) P/N 1004 Product Structure Tree: Example 2 Product Structure Tree: Example 2
15
Product Drawing: Example 3 Top clip (1)Bottom clip (1) Pivot (1)Spring (1) Rivets (2) Finished clipboardPressboard (1) Clipboard
16
Product Structure Tree ( Example 3) Clipboard Level 0 Level 1 Level 2 Spring (1) Bottom Clip (1) Top Clip (1) Pivot (1) Rivets (2) Clip Ass’y (1) Pressboard (1)
17
MRP Inputs 3: Inventory Records File One of the three primary inputs of MRP Includes information on the inventory status of each item by time period Gross requirements Scheduled receipts Amount on hand Lead times Lot sizes And more....
18
MRP Terminology (1 of 3) Gross requirements Scheduled receipts Projected on hand Net requirements Planned-order receipts Planned-order releases
19
MPR Terminology (2 of 3) Gross requirements Total expected demand Scheduled receipts Open orders scheduled to arrive Projected on hand Expected inventory on hand at the beginning of each time period
20
MRP Processing Terminology (3 of 3) Net requirements Actual amount needed in each time period Planned-order receipts Quantity expected to be received at the beginning of the period Offset by lead time Planned-order releases Planned amount to be ordered in each time period
21
MRP Processing Logic: Assembly Time Chart 12345 67 891011 Procurement of raw material D Procurement of raw material F Procurement of part C Procurement of part H Procurement of raw material I Fabrication of part G Fabrication of part E Subassembly A Subassembly B Final assembly and inspection Weeks
22
Calculation of Gross Requirements Therefore, these are the gross requirements for B Periods 10 1 2 3 Master schedule for S sold directly 405015 A C B 5 6 7 8 9 10 11 Lead time = 4 for A Master schedule for A 402030 S B C 8 9 10 12 11 13 Lead time = 6 for S Master schedule for S 10 40+10 = 50 40 50 20 15+30 = 45 1 2 3 4 5 6 7 8 Periods Gross requirements: B
23
The MRP Matrix Gross RequirementsDerived from MPS or planned order releases of the parent Scheduled ReceiptsOn order and scheduled to be received Projected on HandBeg InvAnticipated quantity on hand at the end of the period Net RequirementsGross requirements net of inventory and scheduled receipts Planned Order Receipts When orders need to be received Planned Order Releases When orders need to be placed to be received on time ITEM NAME OR NO.LLC - LOW LEVEL CODEPERIOD LOT SIZE QTY MADE INLY - LEAD TIME12345
24
MRP Processing: Example 1-School Mate Products Master Production Schedule 12345 Clipboard8595120100100 Lapdesk0600600 Item Master File (ınventory record file CLIPBOARDLAPDESKPRESSBOARD On hand2520150 On order175 (Period 1)00 (sch receipt) LLC001 Lot sizeL4LMult 50Min 100 Lead time111
25
School Mate Products Product Structure Record Clipboard Lapdesk Pressboard (2) Trim (3’) Beanbag (1) Glue (4 oz) Level 0 Pressboard (1) Clip Ass’y (1) Rivets (2) Level 1
26
School Mate Products ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Gross Requirements8595120100100 Scheduled Receipts175 Projected on Hand25 Net Requirements Planned Order Receipts Planned Order Releases
27
School Mate Products ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Gross Requirements8595120100100 Scheduled Receipts175 Projected on Hand25115 Net Requirements0 Planned Order Receipts Planned Order Releases (25 + 175) = 200 units available (200 - 85) = 115 on hand at the end of Period 1
28
School Mate Products ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Gross Requirements8595120100100 Scheduled Receipts175 Projected on Hand2511520 Net Requirements00 Planned Order Receipts Planned Order Releases 115 units available (115 - 85) = 20 on hand at the end of Period 2
29
School Mate Products ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Gross Requirements8595120100100 Scheduled Receipts175 Projected on Hand25115200 Net Requirements00100 Planned Order Receipts100 Planned Order Releases100 20 units available (20 - 120) = -100 — 100 additional Clipboards are required Order must be placed in Period 2 to be received in Period 3
30
School Mate Products ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Gross Requirements8595120100100 Scheduled Receipts175 Projected on Hand2511520000 Net Requirements00100100100 Planned Order Receipts100100100 Planned Order Releases100100100 Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and Planned Order Releases
31
School Mate Products ITEM: LAPDESKLLC: 0PERIOD LOT SIZE: MULT 50LT: 112345 Gross Requirements0600600 Scheduled Receipts Projected on Hand20 Net Requirements Planned Order Receipts Planned Order Releases
32
School Mate Products ITEM: LAPDESKLLC: 0PERIOD LOT SIZE: MULT 50LT: 112345 Gross Requirements0600600 Scheduled Receipts Projected on Hand2020101000 Net Requirements04050 Planned Order Receipts5050 Planned Order Releases5050 Following the same logic, the Lapdesk MRP matrix is completed as shown
33
School Mate Products ITEM: PRESSBOARDLLC: 0PERIOD LOT SIZE: MIN 100LT: 112345 Gross Requirements Scheduled Receipts Projected on Hand150 Net Requirements Planned Order Receipts Planned Order Releases ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Planned Order Releases100100100 ITEM: LAPDESKLLC: 0PERIOD LOT SIZE: MULT 50LT: 112345 Planned Order Releases5050
34
School Mate Products ITEM: PRESSBOARDLLC: 0PERIOD LOT SIZE: MIN 100LT: 112345 Gross Requirements1001002001000 Scheduled Receipts Projected on Hand150 Net Requirements Planned Order Receipts Planned Order Releases ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Planned Order Releases100100100 ITEM: LAPDESKLLC: 0PERIOD LOT SIZE: MULT 50LT: 112345 Planned Order Releases5050 x2 x2 x1 x1 x1
35
School Mate Products ITEM: PRESSBOARDLLC: 0PERIOD LOT SIZE: MIN 100LT: 112345 Gross Requirements1001002001000 Scheduled Receipts Projected on Hand1505050000 Net Requirements50150100 Planned Order Receipts100150100 Planned Order Releases100150100 ITEM: CLIPBOARDLLC: 0PERIOD LOT SIZE: L4LLT: 112345 Planned Order Releases100100100 ITEM: LAPDESKLLC: 0PERIOD LOT SIZE: MULT 50LT: 112345 Planned Order Releases5050
36
School Mate Products Planned Order Report PERIOD ITEM12345 Clipboard100100100 Lapdesk5050 Pressboard100150100
37
MRP Processing: Example 2 Example 2 A(2)B(1) D(5)C(2) X C(3) Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10
38
A(2) X It takes 2 A’s for each X
39
B(1)A(2) X It takes 1 B for each X
40
A(2)B(1) X C(3) It takes 3 C’s for each A
41
A(2)B(1) C(2) X C(3) It takes 2 C’s for each B
42
A(2)B(1) D(5)C(2) X C(3) It takes 5 D’s for each B
43
MRP Outputs Planned orders (schedule indicating the amount and timing of orders) Work orders Purchase orders Order releases (authorization for the execution of planned orders) Changes to previous plans or existing schedules (revision of due dates or order quantities, or cancellations of orders) Action notices Rescheduling notices
44
Benefits of MRP Reduced inventories without reduced customer service Ability to track material requirements Ability to evaluate capacity requirements Means of allocating production time Increased customer satisfaction due to meeting delivery schedules Faster response to market changes Improved labor and equipment utilization. Better inventory planning and scheduling
45
Requirements of MRP Computer system and necessary software Mainly discrete products Stable lead times Accurate and up-to-date Master schedules Bills of materials Inventory status records Integrity of data
46
Extensions of MRP
47
Closed loop MRP Capacity planning - load reports MRP II - Manufacturing Resources Planning Enterprise Resources Planning
48
Forecast & Firm Orders Material Requirements Planning Aggregate Production Planning Resource Availability Master Production Scheduling Shop Floor Schedules Capacity Requirements Planning Realistic? No, modify MPS Yes MRP and The Production Planning Process
49
Closed Loop MRP
50
Capacity Planning Capacity requirements planning : The process of determining short-range capacity requirements. Load reports : Department or work center reports that compare known and expected future capacity requirements with projected capacity availability. Time fences : Series of time intervals during which order changes are allowed or restricted.
51
Capacity Requirements Planning (CRP) Computerized system that projects load from material plan Creates load profile Identifies underloads and overloads
52
Capacity Usually expressed as standard machine hours or labor hours Capacity= (no. machines or workers) x (no. shifts) x (utilization) x (efficiency)
53
Capacity Terms Load reports Department or work center reports that compare known and expected future capacity requirements with projected capacity availability. Load profile Compares released and planned orders with work center capacity Capacity Productive capability; includes utilization and efficiency Utilization % of available working time spent working
54
More Capacity Terms Efficiency Refers to how well a machine or worker porforms compared to a standard output level Load The standard hours of work assigned to a facility Load percent The ratio of load to capacity Load % = (load/capacity)x100%
55
Determining Loads and Capacities 2 copiers, 2 operators 5 days/wk, 8 hr/day 1/2 hr meals, 1/2 hr maintenance per day The machines are new, so efficiency is estimated at 100% Utilization= 7/8 = 87.5% Daily capacity= 2 machines x 2 shifts x 8 hours/shift x 100% efficiency x 87.5% utilization = 28 hours or 1,680 minutes
56
Determining Loads and Capacities JOBNO. OFSETUPRUN TIME NO.COPIESTIME (MIN)(MIN/UNIT) TOTAL TIME 105005.20.085.2 + (500 x 0.08) =45.2 201,00010.60.1010.6 + (1,000 x 0.10) =110.6 305,0003.40.123.4 + (5,000 x 0.12) =603.4 4010,00011.20.1411.2 + (10,000 x 0.14) =1,411.2 502,00015.30.1015.3 + (2,000 x 0.10) =215.3 2385.7 min Load percent = 2,385.7 / 1,680 = 1.42 x 100% = 142% Add another shift: Daily capacity= 2 machines x 3 shifts x 8 hours/shift x 100% efficiency x 87.5% utilization = 42 hours or 2,520 minutes Revised load percent = 2,385.7 / 2,520 = 0.9467 x 100% = 94.67%
57
Initial Load Profile Hours of capacity 123456123456123456123456 Time (weeks) Normalcapacity 120 120 – 110 110 – 100 100 – 90 90 – 80 80 – 70 70 – 60 60 – 50 50 – 40 40 – 30 30 – 20 20 – 10 10 – 0 0 –
58
Remedies for Underloads 1.Acquire more work 2.Pull work ahead that is scheduled for later time periods 3.Reduce normal capacity
59
Remedies for Overloads Eliminate unnecessary requirements Reroute jobs to alternative machines or work centers Change lot-sizing or safety stock requirements Split lots between two or more machines Send pieces to the second operation before the entire lot has completed the first operation Increase normal capacity Subcontract Increase the efficiency of the operation Push work back to later time periods Revise master schedule
60
Adjusted Load Profile Hours of capacity 123456123456123456123456 Time (weeks) Normalcapacity 120 120 – 110 110 – 100 100 – 90 90 – 80 80 – 70 70 – 60 60 – 50 50 – 40 40 – 30 30 – 20 20 – 10 10 – 0 0 – Pull ahead Push back Overtime Work an extra shift
61
Expanded MRP with emphasis placed on integration of: Financial planning Marketing Engineering Purchasing Manufacturing Human resources Manufacturing Resources Planning- MRP II Manufacturing Resources Planning- MRP II
62
Manufacturing Resources Planning (MRP II) Goal: Plan and monitor all resources of a manufacturing firm (closed loop): manufacturing marketing finance engineering Simulate the manufacturing system
63
MarketDemand Productionplan Problems? Rough-cut capacity planning Yes No Yes No Finance Marketing Manufacturing Adjust production plan Master production schedule MRP Capacity req. planning Problems? Requirementsschedules Adjust master schedule MRP II
64
Enterprise Resource Planning (ERP) The next step in the evolution that began with MRP and evolved into MRP II ERP system is a computer system that integrates application programs in finance, accounting, sales, purchasing, distribution, manufacturing, human resources and other functions in the firm.
65
MRP II with ties to customers and suppliers (connects with supply-chain and customer management applications) ERP represents an expanded effort to integrate standardized record keeping that will permit information sharing among different areas of an organizaiton in order to manage the system more effectively ERP integrates financial, manufacturing and human resources on a single computer system. ERP
66
Enterprise Resource Planning (ERP) Attempts to integrate all departments and functions across a company onto a single computer system that can serve all those different departments’ particular needs Organizes and manages a company’s business processes by sharing information across functional areas Standardized record-keeping permit information sharing and communication throughout the organization
67
ERP ERP allows companies to: 1.Automate and integrate many of their business processes 2.Share a common database and business practices throughout the enterprise 3.Produce information in real time ERP systems also include: 1.Supply Chain Management software and 2.Customer Relationship Management software
68
ERP Modules
69
ERP’s Central Database Finance & Accounting Sales & Marketing Human Resources Production & Materials Management ERP Data Repository
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.