Presentation is loading. Please wait.

Presentation is loading. Please wait.

Phone 9.Sept.2004A.Fabich, CERN1 modifying beam line TT2A A.Fabich Phone conference 9.Sept.2004 All information available on

Similar presentations


Presentation on theme: "Phone 9.Sept.2004A.Fabich, CERN1 modifying beam line TT2A A.Fabich Phone conference 9.Sept.2004 All information available on"— Presentation transcript:

1 Phone 9.Sept.2004A.Fabich, CERN1 modifying beam line TT2A A.Fabich Phone conference 9.Sept.2004 All information available on http://proj-hiptarget.web.cern.ch/

2 Phone 9.Sept.2004A.Fabich, CERN2

3 Phone 9.Sept.2004A.Fabich, CERN3 Going down, down … (in fact we are looking up here) TT2 with a slope of about 7 degree

4 Phone 9.Sept.2004A.Fabich, CERN4 Entrance to TT2A around the corner … around the corner

5 Phone 9.Sept.2004A.Fabich, CERN5 Option 2 Option 3

6 Phone 9.Sept.2004A.Fabich, CERN6 Elements to install/remove Blocks at entrance TT2A (around the corner) Metallic chassis of nToF cooling Quadrupole at entrance Dipole/quadrupole between option 2&3 Solenoid (4 tons) Beam attenuator (iron block 7.5 tons) Mercury loop …

7 Phone 9.Sept.2004A.Fabich, CERN7 contacts –Patrice Ziegler Former responsible of this tunnel –Christian Lacroix Given by Patrice Ziegler –J. Bernard (with S. Prodon) Invited by Helmut for meeting November 2003

8 Phone 9.Sept.2004A.Fabich, CERN8 Chat with Patrice For transport usually a track vehicle Lifting with pneumatic lifter Displacing a dipole one team for half a day –Also needed: vacuum, power cables, water Solenoid one day for transport Just recently they exchanged some quads


Download ppt "Phone 9.Sept.2004A.Fabich, CERN1 modifying beam line TT2A A.Fabich Phone conference 9.Sept.2004 All information available on"

Similar presentations


Ads by Google